Plan Review Notes
Plan Review Notes For Permit 99010946
Permit Number 99010946
Review Stop R
Sequence Number 5
Notes
Date Text
2001-03-06 00:00:00REVISION CHECKLIST:
 1-REVISED DRAWINGS ARE VERY CONFUSING.
 THERE ARE OLD DRAWINGS AND NEW DWGS
 MIXED TOGETHER, INCLUDING ALL THE
 STRUCTURAL DWGS. REVISE ALL DRAWINGS '
 AND DETAILS AS REQUIRED AND CLEARLY
 INDICATE THE DETAILS THAT REALLY APPLY
 TO THIS CONSTRUCTION.
 -SEE PLANS FOR ADDITIONAL COMMENTS.
 2-ENGINEER OF RECORD TO SIGN, SEAL AND
 DATE ALL STRUCTURAL DRAWINGS. THERE
 ARE MANY STRUCTURAL DETAILS/SECTIONS
 SHOWN ON THE ARCHITECTURAL DRAWINGS.
 3-PROVIDE PRODUCT APPROVALS FOR:
 -ENTRY DOORS AS SHOWN ON PLANS.
 -BALCONY SWING DOOR AS SHOWN ON PLANS.
 -SLIDING GLASS DOORS OR FRENCH DOORS
 WITH SIDELITES AND TRANSOM ABOVE
 ASSEMBLY AS SHOWN ON PLANS.
 NOTE: REVISE DRAWINGS TO CLARIFY WHAT
 TYPE OF DOORS TO BE USED.
 -FIXED RECTANGULAR WINDOWS WITH THE
 SIZES SHOWN ON ARCHITECTURAL PLANS.
 -ROUND AND ARCHED WINDOWS. SEE PLANS.
 -WINDOW MULLIONS.
 NOTE: WINDOWS TO HAVE MISSILE IMPACT
 GLAZING MUST HAVE MULLIONS TESTED FOR
 MISSILE IMPACT AS WELL.
 -ROOF TILE.
 4-PROVIDE COMPLETE INSTALLATION DETAILS
 SHOWING CONNECTION OF WINDOWS TO STEEL
 COLUMNS AT BAY WINDOWS. SIGNED, SEALED
 AND DATED BY THE ENGINEER OF RECORD.
 5-CLEARLY SPECIFY HOW TO PROTECT GAS
 APPLIANCE IN GARAGE. PROVIDE COMPLETE
 DETAIL SPECIFYING HOW ARE THE "PIPES"
 ATTACHED, WHAT TYPES OF PIPES? SEE
 COMMENTS ON PLANS. SIGNED, SEALED BY
 THE STRUCTURAL ENGINEER.
 6-SEE COMMENTS BY THE ELECTRICAL PLAN
 REVIEWER.
 7-CLEARLY INDICATE THE DOORS AND WINDOWS
 THAT ARE GOING TO HAVE MISSILE IMPACT
 GLAZING.
 -PROVIDE COMPLETE INFORMATION FOR
 STORM PANELS UNDER A SEPARATE PERMIT.
 8-DRAWINGS SUBMITTED HAVE DOUBLE A1, A2
 AND A3 SHEETS. WHY?.
 -MISSING SHEET A-5.
 9-EXTERIOR ELEVATIONS DON'T MATCH FLOOR
 PLANS. REVISE AS REQUIRED.
 10-PROVIDE ATTIC ACCESS AT SECOND FLOOR
 ROOF. SECTION 2309.6 SBC 1994.
 11-PROVIDE COMPLETE SECTION/DETAIL THRU
 STAIRS. SIGNED, SEALED BY ENGINEER.
 12-SPECIFY DRAFSTOPPING MATERIAL AND
 LOCATION ON SECOND FLOOR FRAMING PLAN.
 SECTION 2305.2.2 SBC 1994.
 13-CLEARLY INDICATE ON PLANS HOW IS THE
 WATER DRAINED FROM TOP FLAT ROOF.
 SEE SECTIONS 1507, 1509.1.2.3 AND
 16.4.6.2 SBC 1994.
 14-SPECIFY THE DESIGN PRESSURES THAT
 WERE CALCULATED BY THE ENGINEER FOR
 ALL EXTERIOR OPENINGS. SEC 1606 SBC/94
 15-OWES $431.10 REVISIONS & RADON FEES.
  
 NOTES:
 -PLEASE RETURN REVIEWED SET AFTER ALL
 REVISIONS ARE DONE TO THE ORIGINAL
 DRAWINGS IN ORDER TO EXPEDITE THE
 REVIEW PROCESS.
  
 -IF YOU HAVE ANY QUESTIONS, PLEASE
 CONTACT JULIO GOMEZ AT 659-8096
 EXT. 8232.