| 2023-06-06 15:40:43 | 1. PORTION OF PROPOSED UNDERGROUND WORK (SHEET 06 PLAN |
| | SURVEY) IS LOCATED ALONG THE TERMINUS OF CHASE ST. THIS |
| | AREA IS SUBJECT TO A NEW STREETSCAPE PROJECT BY THE |
| | CITY. PLEASE COORDINATE UNDERGROUND ELECTRIC PLANS WITH |
| | DANIEL ROBERGE - ENGINEERING |
| | SERVICES PROJECT MANAGER - 494-1040 (1053). |
| | |
| | 2. IS THIS PROPOSED UNDERGROUND ELECTRIC GOING TO A |
| | STANDALONE WIRELESS COMMUNICATIONS FACILITIES (POLE)? |
| | IF SO: |
| | PROVIDE VERIFICATION THAT THE SITE HAS BEEN ISSUED A |
| | COMMUNICATION FACILITY PLACEMENT PERMIT - CITY |
| | RIGHTS-OF-WAY AND A RIGHT-OF-WAY USE PERMIT FOR THE |
| | PLACEMENT OF THE POLE, THE UNDERGROUND ELECTRIC, THE |
| | HANDHOLES, ETC. WITHIN THE CHASE STREET AND S FLAGLER |
| | DRIVE RIGHTS-OF-WAY. THE PLANS INCLUDED WITH THIS |
| | ELECTRICAL PERMIT MUST MATCH THE PLANS APPROVED WITH |
| | THE AFOREMENTIONED PERMITS. |
| | |
| | 3. PAGE 05, 06, AND 07 NEEDS TO SHOW THE RIGHT-OF-WAY |
| | LINE (BASED ON THE SURVEY) AND CLEARLY DEMONSTRATE THAT |
| | THE HANDHOLES, BORE PITS AND UNDERGROUND POWER BORE ARE |
| | COMPLETELY LOCATED WITHIN THE RIGHT-OF-WAY. NOTE: THE |
| | POWER ROUTE APPEARS TO CROSS ONTO PRIVATE PROPERTY ON |
| | THE CITY'S TRINITY PARK SITE AND PULL POWER FROM A |
| | TRANSFORMER THERE. IF THE SURVEY SHOWS A GENERAL |
| | UTILITY EASEMENT AT THIS LOCATION, THEN THE UNDERGROUND |
| | FEATURES MAY CROSS INTO THE EASEMENT. IF NO EASEMENT IS |
| | PRESENT, POWER MUST BE DRAWN FROM AN ALTERNATIVE SOURCE |
| | WITHIN THE PUBLIC RIGHT-OF-WAY. |
| | |
| | CHRIS KIMMERLY, AICP |
| | URBAN DESIGN PLANNER |
| | 822.1426 [email protected] |