| Date |
Text |
| 2023-07-06 09:40:59 | NFIP REVIEW: |
| | |
| | 1- THIS BUILDING IS GOING TO BE BUILT IN A AE FLOOD |
| | ZONE WITH THE BASE FLOOD BFE: 6 FEET BASED ON NAVD |
| | 1988. |
| | CITY OF WEST PALM BEACH ORDINANCE REQUIRES A TWO (2) |
| | FOOT FREE BOARD ABOVE THE BASE FLOOD ELEVATION (SEC. |
| | 18-284 CITY ORDINANCE NO. 4729-17). |
| | DESIGNER OF RECORD NEEDS TO SPECIFY THE PROPOSED FINISH |
| | ELEVATIONS, INCLUDING ALL EQUIPMENT SERVING THE TWO |
| | BUILDINGS. |
| | |
| | DURING THE PERMITTING/CONSTRUCTION OF THIS STRUCTURE |
| | THREE DIFFERENT FLOOD ELEVATION CERTIFICATES WILL BE |
| | REQUIRED (SEC. 107.3.5.1.1 CITY AMENDMENTS): |
| | A) CONSTRUCTION DRAWINGS. |
| | B) BUILDING UNDER CONSTRUCTION. |
| | C) FINISHED CONSTRUCTION. |
| | |
| | NOTE: |
| | NEED TO PROVIDE THE CONSTRUCTION DRAWINGS ELEVATION |
| | CERTIFICATE NOW FOR REVIEW. |
| | ALSO, NEED TO PROVIDE SURVEY TO VERIFY ELEVATIONS |
| | SPECIFIED ON ELEVATION CERTIFICATE. |
| | |
| | WHEN RESUBMITTING, A TRANSMITTAL LETTER LISTING THE |
| | ORIGINAL REVIEW COMMENT WITH A DESCRIPTION OF WHERE AND |
| | HOW THE COMMENT WAS ADDRESSED WILL HELP TO EXPEDITE THE |
| | REVIEW PROCESS. THANK YOU FOR YOUR ANTICIPATED |
| | COOPERATION. |
| | |
| | PLEASE FEEL FREE TO CONTACT ME IF YOU HAVE ANY |
| | QUESTIONS REGARDING THESE COMMENTS, |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | (561)805-6712 |
| | [email protected] |
| | |