| 2023-04-13 15:03:31 | 1ST REVIEW FBC-2020 FUEL GAS |
| | PERMIT- 23020122 |
| | 4/13/23 |
| | |
| | CODES IN EFFECT: |
| | FBC FG- FLORIDA FUEL GAS CODE 7TH EDITION 2020 |
| | FS- FLORIDA STATUTES |
| | FAC- FLORIDA ADMINISTRATIVE CODE |
| | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC |
| | |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | 1) THE M PLANS ALL HAVE KEY PLANS SHOWING TWO AREAS OF |
| | WORK. TO HELP EXPEDITE THE REVIEW PLEASE LABEL THE |
| | ROOMS AND PLANS ACCORDING TO THE MECHANICAL SCHEDULES |
| | (M801 & M802) WHICH SHOW B-1&2 IN THE BOILER PLANT AND |
| | B-H-1 & 2 IN THE BOILER ROOM- SEC. 107.2.1 WPB. PLEASE |
| | NOTE THE BOILER LOCATIONS IN THE SAFETY RELIEF VALVE |
| | SCHEDULE DO NOT MATCH THE LOCATIONS IN THE EQUIPMENT |
| | SCHEDULES. |
| | |
| | 2) M202: PLEASE PROVIDE A KEYNOTE WHICH SHOWS THE TYPES |
| | AND SIZES OF GAS PIPING SHOWN IN THE ENLARGED PLANS, |
| | AND PROVIDE A KEYNOTE WHICH REFERENCES THE LOCATION OF |
| | THE GAS TRAIN DETAIL. IT APPEARS TO BE DETAIL 6/M402. |
| | PLEASE PROVIDE THE SIZES OF GAS PIPING SHOWN IN THE |
| | DETAIL AND THE SYSTEM PRESSURES BEFORE AND AFTER THE |
| | REGULATORS (PRV'S)- SEC. 402.3 & 410.2 FBC FG. PLEASE |
| | NOTE A COMPLETE REVIEW CANNOT BE COMPLETED WITHOUT THE |
| | MBH OF B-1&2 WHICH IS NOT SHOWN LISTED IN THE SCHEDULE. |
| | |
| | 3) M202: INDICATE HOW COMBUSTION AIR WILL BE PROVIDED |
| | FOR B-1&2 AND PROVIDE CALCULATIONS- SEC. 304.1 FBC FG. |
| | NOTE 14 INDICATES A NEW SUPPLY FAN SAF-1 ON THE ROOF |
| | ABOVE THE BOILER PLANT. IS THIS THE SOURCE OF THE |
| | COMBUSTION AIR? PLEASE PROVIDE FURTHER DETAILS. |
| | |
| | 4) M202: PROVIDE A BOILER VENTING DIAGRAM THAT SHOWS |
| | THE TYPE AND SIZE OF VENT FLUE, AND VENT FLUE RUN |
| | LENGTH FROM BOILER OUTLET TO TERMINATION CAP ABOVE THE |
| | ROOF- SECS. 502.5, 503.1, & 631.2 FBC FG. |
| | |
| | 5) M202: PLEASE SHOW THE CLEARANCE DISTANCE |
| | MEASUREMENTS FROM THE BOILER FLUE OUTLETS TO THE SAF-1 |
| | INTAKE- SEC. 501.3.1. FBC M. |
| | |
| | 6) M802 & M803: PLEASE SHOW IN THE SCHEDULE NOTES FOR |
| | THE BOILERS THAT THEY ARE LISTED IN ACCORDANCE WITH THE |
| | REQUIREMENTS OF ANSI Z21.13/CSA 4.9 OR UL 795- SEC. |
| | 631.1 FBC FG. |
| | |
| | 7) M203: PLEASE PROVIDE A KEYNOTE WHICH SHOWS THE TYPES |
| | AND SIZES OF GAS PIPING SHOWN IN THE ENLARGED PLANS FOR |
| | H-B-1 & H-B-2, AND PROVIDE A KEYNOTE WHICH REFERENCES |
| | THE LOCATION OF THE GAS TRAIN DETAIL. IT APPEARS TO BE |
| | DETAIL 4/M403. PLEASE PROVIDE THE SIZES OF GAS PIPING |
| | SHOWN IN THE DETAIL AND THE SYSTEM PRESSURES BEFORE AND |
| | AFTER THE REGULATORS (PRV'S)- SEC. 402.3 & 410.2 FBC |
| | FG. |
| | |
| | 8) M203: PLEASE INCLUDE ROOF DEMOLITION AND RENOVATION |
| | PLANS FOR THE BOILER ROOM AS WERE PROVIDED FOR THE |
| | BOILER PLANT ROOM- SEC. 107.2.1 WPB. |
| | |
| | 9) M203 INDICATE HOW COMBUSTION AIR WILL BE PROVIDED |
| | FOR H-B-1 & H-B-2 AND PROVIDE CALCULATIONS- SEC. 304.1 |
| | FBC FG. |
| | |
| | 10) M203: PROVIDE A BOILER VENTING DIAGRAM THAT SHOWS |
| | THE TYPE AND SIZE OF VENT FLUE, AND VENT FLUE RUN |
| | LENGTH FROM BOILER OUTLET TO TERMINATION CAP ABOVE THE |
| | ROOF- SECS. 502.5, 503.1, & 631.2 FBC FG. |
| | |
| | 11) M802 & M803: PLEASE PROVIDE EQUIPMENT SCHEDULES FOR |
| | THE GAS REGULATORS- SEC. 410.2. |
| | |
| | 12) M101: THE PLAN SHOWS AN EXISTING GAS LINE SUPPLYING |
| | A TEMPORARY STEAM BOILER. I WAS UNABLE TO LOCATE A |
| | PERMIT OR APPROVED PLANS FOR THE GAS PIPING AND |
| | TEMPORARY BOILER INSTALLATIONS. PLEASE PROVIDE COMPLETE |
| | PLANS AND DETAILS INCLUDING A GAS RISER DRAWING- SEC. |
| | 107.3.5.1.5 FBC FG. |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL/PLUMBING PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |
| | [email protected] |
| | |