| Date |
Text |
| 2023-03-30 09:44:22 | STRUCTURAL AFFIDAVIT FAILED-DATES ON DRAWINGS SIGNED |
| | AND SEALED DOUCMENTS ARE NOT 11.29.22 PLEASE UPDATED |
| | ACCORDINGLY |
| | GEOTECHNINCAL REPORT UPDATED RECENTLY FOLLOWING |
| | BUILDING COMMENT- SEE NARRATIVE MUST BE PART OF THE |
| | STRUCTURAL AFFIDAVIT. |
| | |
| | |
| 2023-03-29 13:46:38 | PLUMBING AFFIDAVIT REVIEW FAILED. |
| | 1) THE AFFIDAVIT LISTS ALL CIVIL (C) SHEETS DATES- |
| | 11/29/22. CIVIL SHEETS UPLOADED FOR REVIEW HAVE DEC. |
| | 2022 DATES. |
| | 2) THE AFFIDAVIT LISTS ALL PLUMBING (P) SHEETS DATES- |
| | 11/29/22. |
| | SHEETS P-001, P-101, P-102, P-601, & P-603 UPLOADED FOR |
| | REVIEW ARE DATED 3/24/23. |
| | 3) SHEETS P-101, P-102, & P-603 ARE NOT LISTED IN THE |
| | AFFIDAVIT. PLEASE NOTE THESE SHEETS ARE ALSO NOT LISTED |
| | IN THE INDEX ON SHEET G-100. |
| | |
| 2023-03-29 11:40:13 | |
| | ELECTRIC AFFIDAVIT REVIEW PASSED. MP |
| 2023-03-29 09:37:31 | THE AFFIDAVIT FOR THE MECHANICAL PLAN REVIEW INDICATES |
| | THAT SHEETS M-001, M-002, M-101A, M-101B. THE AFFIDAVIT |
| | DOES NOT INDICATE THAT THE FOLLOWING SHEETS THAT WERE |
| | SUBMITTED IN THE DRAWING PACKAGE HAVE BEEN REVIEWED AS |
| | THEY ARE NOT LISTED IN THE MECHANICAL AFFIDAVIT. SHEET |
| | M-605A AND M-605B. THE MECHANICAL AFFIDAVIT HAS FAILED. |
| | ME |
| 2023-03-29 09:03:29 | BUILDING AFFIDAVIT : FAILED |
| | LATEST BUILDING AFFIDAVIT SHEETS DATES SHOULD REFLECT |
| | LATEST VERSION. EXAMPLE G-100 WAS UPLOADED 03.22.2023 |
| | AND YOUR AFFIDAVIT SAYS SHEETS IS DATED 11.29.2022 |
| | PLEASE UPDATED ACCORDINGLY FOR ALL LATEST SHEETS PART |
| | OF THE AFFIDAVIT. |