2023-06-27 10:14:30PLAN REVIEW COMMENTS
  
 3RD REVIEW: FBC SEVENTH EDITION (2020)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) [NOT RESOLVED. ALSO SEE THE THRESHOLD REVIEW
 COMMENTS. PLEASE SEE THE CITY OF WPB THRESHOLD
 INSPECTION INSTRUCTIONS AND POLICY BOOKLET. THE
 THRESHOLD STATEMENT IS NOT ON THE STRUCTURAL DRAWINGS.]
 THIS PROJECT INVOLVES STRUCTURAL MODIFICATIONS TO A
 THRESHOLD BUILDING. A THRESHOLD INSPECTOR WILL BE
 REQUIRED. PLEASE ADDRESS THE FOLLOWING:
  
 THRESHOLD BUILDING / FL S. S. 553.71(7) "THRESHOLD
 BUILDING" MEANING ANY BUILDING WHICH IS GREATER THAN
 (3) STORIES OR 50 FT. IN HEIGHT, OR WHICH HAS AN
 ASSEMBLY OCCUPANCY CLASSIFICATION AS DEFINED IN THE
 FLORIDA BUILDING CODE WHICH EXCEEDS 5,000 SQ. FT. IN
 AREA AND AN OCCUPANT CONTENT OF GREATER THAN 500
 PERSONS.
  
 A) FBC (CITY AMENDMENTS)110.8.1 THRESHOLD INSPECTION
 PLAN. THE ENFORCING AGENCY SHALL REQUIRE A SPECIAL
 INSPECTOR TO PERFORM STRUCTURAL INSPECTIONS ON A
 THRESHOLD BUILDING PURSUANT TO A STRUCTURAL INSPECTION
 PLAN PREPARED BY THE ENGINEER OF RECORD. THE STRUCTURAL
 INSPECTION PLAN MUST BE SUBMITTED TO THE ENFORCING
 AGENCY PRIOR TO THE ISSUANCE OF A BUILDING PERMIT FOR
 THE CONSTRUCTION OF A THRESHOLD BUILDING. THE PURPOSE
 OF THE STRUCTURAL INSPECTION PLAN IS TO PROVIDE
 SPECIFIC INSPECTION PROCEDURES AND SCHEDULES SO THAT
 THE BUILDING CAN BE ADEQUATELY INSPECTED FOR COMPLIANCE
 WITH THE PERMITTED DOCUMENTS.
  
 B) THRESHOLD INSPECTOR: WPB AMENDMENT 110.8.1 W.P.B.
 CONSTRUCTION SERVICES DEPARTMENT REQUEST FOR THRESHOLD
 BUILDINGS A SPECIAL INSPECTOR AS REQUIRED BY 553.79(5)
 FLORIDA STATUTES TO THE MINIMUM INSPECTIONS REQUIRED BY
 THIS CODE. THE THRESHOLD INSPECTION FORMS ARE REQUIRED
 TO BE FILED OUT BY ALL PARTIES WITH INTEREST, NOTARIZED
 AND RETURNED TO THIS OFFICE, AND REVIEWED AND APPROVED
 BEFORE PERMIT ISSUANCE WILL TAKE PLACE.
  
 C) THRESHOLD BLDG. REQUIRED STATEMENT: W.P.B. AMENDMENT
 110.8.4.4 ALL PLANS FOR THE BUILDING WHICH ARE REQUIRED
 TO BE SIGNED AND SEALED BY THE ARCHITECT OR ENGINEER OF
 RECORD CONTAIN A STATEMENT THAT, TO THE BEST OF THE
 ARCHITECT'S OR ENGINEER'S KNOWLEDGE, THE PLANS AND
 SPECIFICATIONS COMPLY WITH THE APPLICABLE MINIMUM
 BUILDING CODES AND THE APPLICABLE FIRE-SAFETY STANDARDS
 AS DETERMINED BY THE LOCAL AUTHORITY IN ACCORDANCE WITH
 THIS SECTION AND CHAPTER 633 FLORIDA STATUTES.
  
 D) FOR THE SPECIAL INSPECTOR PLEASE PROVIDE A RESUME OF
 INSPECTION EXPERIENCE ON PREVIOUS PROJECT. THE RESUME
 MUST BE ACCOMPANIED BY ALL CERTIFICATES AS SPECIFIED
 HEREIN. THE BUILDING OFFICIAL OR HIS DESIGNEE WILL
 REVIEW THE RESUME. AFTER THE RESUME IS REVIEWED, AN
 INTERVIEW WILL BE SCHEDULED. UNDER NO CIRCUMSTANCES
 WILL AN INSPECTOR BE INTERVIEWED FOR WORK WITHOUT FIRST
 MEETING THE ABOVE CRITERIA.
  
 E) THE CONTRACTOR WILL PRODUCE A JOB SUMMARY OR HISTORY
 FOR THIS TYPE OF CONSTRUCTION.
  
 F) NOTE: FOR DIGITAL PLANS, AFTER PERMIT ISSUANCE,
 PLEASE E-MAIL THE PERMIT LIBRARIAN OF THE PERMIT BEING
 ISSUED, THE PERMIT LIBRARIAN WILL THEN E-MAIL YOU THE
 APPROVED AND BATCH STAMPED PLANS SO YOU MAY PRINT YOUR
 PLANS, TWO SETS OF PLANS WILL NEED TO BE PRINTED IN
 COLOR, (1) FOR THE THRESHOLD INSPECTOR, THE OTHER FOR
 THE MEP INSPECTORS OTHER PLANS YOU WISH TO PRINT MAYBE
 IN BLACK & WHITE.
  
 G) 110.8.4.3 ALL SHORING AND RESHORING PROCEDURES,
 PLANS AND DETAILS SHALL BE SUBMITTED TO THE ENFORCEMENT
 AGENCY FOR RECORDKEEPING. EACH SHORING AND RESHORING
 INSTALLATION SHALL BE SUPERVISED, INSPECTED AND
 CERTIFIED TO BE IN COMPLIANCE WITH THE SHORING
 DOCUMENTS BY THE CONTRACTOR.
  
 H) PLEASE CALL THE CITY OF WEST PALM BEACH'S AUTOMATED
 TELEPHONE INSPECTIONS LINE (561) 805-6700 FOR ALL
 BUILDING INSPECTIONS FOR AUDITING OF JOBSITE
 INSPECTIONS WITHOUT THIS THE PERMIT EXPIRES IN 6
 MONTHS, ABANDONMENT OF JOB, NO INSPECTION ACTIVITY.
  
 I) 110.8 THRESHOLD BUILDINGS, OPERATING GUIDELINES FOR
 THRESHOLD INSPECTORS #25. ASSURE THAT THE DESIGNER HAS
 REQUIRED ON THE PLANS OR SPECIFICATIONS ONE MATERIAL,
 APPROVED FOR FIRE STOPPING PENETRATIONS, FOR WALLS AND
 CEILINGS.
  
 J) PLEASE CONTACT ME WITH AN EMAIL ADDRESS AND I WILL
 BE HAPPY TO SEND YOU A COPY OF THE CURRENT (OCTOBER
 2018) GUIDELINES AND POLICIES FOR PROJECTS CONCERNING
 THRESHOLD/SPECIAL INSPECTORS AND RESIDENT INSPECTORS.
  
 2) [RESOLVED.] PROVIDE A COMPLETE FLOOR PLAN OF THE
 BUILDING FOR EACH FLOOR OF THE PROJECT AND IDENTIFY THE
 WORK AREA ON EACH FLOOR. FBC 107.2.1
  
 3) [RESOLVED.] PROVIDE A COVER PAGE WITH THE DESIGN
 PARAMETERS AND RELAVENT CODES (FBC EXISTING BUILDING
 AND OTHERS). THIS INCLUDES DESIGN CRITERIA, LEVEL OF
 ALTERATION, AND CODE ANALYSIS. FBC 107.2.1
  
 4) YOU MAY WISH TO DEFER SUBMITTING SOME CONSTRUCTION
 DOCUMENTS (SHOP DRAWINGS, PRODUCT APPROVALS, ETC.)
 UNTIL A LATER TIME PRIOR TO INSTALLATION. FBC
 AMENDMENTS 107.3.4.1 DEFERRED SUBMITTALS. FOR THE
 PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS ARE
 DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT
 SUBMITTED AT THE TIME OF THE APPLICATION AND THAT ARE
 TO BE SUBMITTED TO THE BUILDING OFFICIAL WITHIN A
 SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL ITEMS SHALL
 HAVE THE PRIOR APPROVAL OF THE BUILDING OFFICIAL. THE
 REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE
 SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION
 DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. THE
 REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE
 SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION
 DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL.
 DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE
 SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN
 RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD
 THEM TO THE BUILDING OFFICIAL WITH A NOTATION
 INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE
 BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO
 THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL
 ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED
 SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING
 OFFICIAL.
  
 5) [RESOLVED.] PLEASE PROVIDE A SIGNED ACKNOWLEDGEMENT
 FROM THE CONTRACTOR, ON LETTERHEAD, STATING THAT THE
 INSTRUCTIONS ON THE WEBSITE OF ASBESTOS PROGRAM
 COORDINATOR, FLORIDA DEPARTMENT OF HEALTH PALM BEACH
 COUNTY WILL BE FOLLOWED AND THAT NOTIFICATION WILL BE
 GIVEN TIMELY. ADDITIONAL INFORMATION REGARDING ASBESTOS
 REQUIREMENTS CAN BE FOUND ON THEIR WEBSITE: HTTP://PALM
 BEACH.FLORIDAHEALTH.GOV/PROGRAMS-AND-SERVICES/ENVIRONME
 NTAL-HEALTH/AIR-QUALITY/ASBESTOS-DEMOLITION-
 RENOVATION.HTML
  
 6) [NOT RESOLVED. YOU SUBMITTED DOCUMENT FOR TWO
 DIFFERENT PROFLEX PRODUCTS. THE FLAME SPREAD TEST
 REPORT FOR THE SUPER SIM-90 IS ACCEPTABLE. YOU WILL
 HAVE TO SUBMIT THE SUPER SIM-90 TEST REPORTS FOR THE
 AIR-BORNE AND STRUCTURE-BORNE SOUND.] THE SCOPE OF WORK
 FOR THIS PROJECT WILL REQUIRE THE INSTALLATION OF SOME
 TYPE OF NEW FLOORING IN THE UNIT. SPECIFY THE TYPE OF
 FINISH FLOORING AND THE SOUND INSULATION UNDERLAYMENT
 THAT WILL BE INSTALLED. YOU WILL ALSO NEED TO SUBMIT
 COPIES OF THE ACTUAL TEST REPORTS FOR THE SOUND
 INSULATION INCLUDING FLAME SPREAD AND SMOKE DEVELOPED
 FOR THE APPLICABLE CONSTRUCTION CONDITIONS. FBC 603.1
 FLAME SPREAD - ASTM E 84-09
 FBC 1207.2 AIR-BORNE SOUND. ASTM E 90-04 WALLS,
 PARTITIONS AND FLOOR/CEILING ASSEMBLIES SEPARATING
 DWELLING UNITS FROM EACH OTHER OR FROM PUBLIC OR
 SERVICE AREAS SHALL HAVE A SOUND TRANSMISSION CLASS
 (STC) OF NOT LESS THAN 50 (45 IF FIELD TESTED) FOR
 AIR-BORNE NOISE WHEN TESTED IN ACCORDANCE WITH ASTM E
 90.
 FBC 1207.3 STRUCTURE-BORNE SOUND. ASTM E 492-09
 FLOOR/CEILING ASSEMBLIES BETWEEN DWELLING UNITS OR
 BETWEEN A DWELLING UNIT AND A PUBLIC OR SERVICE AREA
 WITHIN THE STRUCTURE SHALL HAVE AN IMPACT INSULATION
 CLASS (IIC) RATING OF NOT LESS THAN 50 (45 IF FIELD
 TESTED) WHEN TESTED IN ACCORDANCE WITH ASTM E 492.
  
 7) [RESOLVED.] ON SHEET S100, THE FLOOR PENETRATION
 REPAIR DETAIL SPECIFIES PLYWOOD SHEATHING AND WOOD
 JOISTS. THIS IS NOT ALLOWED IN TYPE I AND II
 CONSTRUCTION. 718.5 COMBUSTIBLE MATERIALS IN CONCEALED
 SPACES IN TYPE I OR II CONSTRUCTION. COMBUSTIBLE
 MATERIALS SHALL NOT BE PERMITTED IN CONCEALED SPACES OF
 BUILDINGS OF TYPE I OR II CONSTRUCTION.
  
 8) [RESOLVED.] SHOW COMPLIANCE WITH FBC 1014.1 FOR
 HANDRAILS AT THE PROPOSED STAIRS.
  
 9) [RESOLVED.] SHOW COMPLIANCE WITH FBC 1015.1 FOR
 GUARDS AT THE PROPOSED STAIRS.
  
 10) [NOT RESOLVED. I DID NOT SEE ON THE PLANS WHERE THE
 CLEAR FLOOR SPACES AT FIXTURES OR THE REINFORCED WALL
 AREAS FOR GRAB BARS WERE SHOWN.] SHOW THAT THE
 REMODELED BATHROOMS AND KITCHENS COMPLY WITH FAIR
 HOUSING.
  
 11) [NOT RESOLVED. THE DESIGNER OF RECORD HAS NOT
 APPROVED THE PRODUCT APPROVALS IN WRITING. THE SPECIFIC
 ITEM TYPES, SIZES AND THEIR DESIGN PRESSURES HAVE NOT
 BEEN MARKED UP ON THE PRODUCT APPROVALS. ] FBC 107.3.4
 - PROVIDE PRODUCT APPROVALS FOR THOSE PRODUCTS WHICH
 ARE REGULATED BY FAC 61G20-3.001 PER FLORIDA STATUTE
 553.842 (5) THAT HAVE BEEN REVIEWED AND APPROVED IN
 WRITING BY THE DESIGNER OF RECORD. INDICATE THE
 SPECIFIC ITEMS AND THEIR DESIGN PRESSURES ON THE
 PRODUCT APPROVAL BY CIRCLING OR HI-LIGHTING THEM. THESE
 ITEMS CAN BE DEFERRED IF REQUESTED, HOWEVER, THE
 DOCUMENTS MUST BE SUBMITTED AND APPROVED BY THE
 BUILDING DEPARTMENT BEFORE THEY CAN BE INSTALLED.
  
 12) PLEASE SUBMIT A RESPONSE LETTER INDICATING HOW EACH
 OF THE REVIEW COMMENTS HAS BEEN ADDRESSED. THIS WILL
 HELP SPEED THE REVIEW AND AID ME IN AVOIDING THINGS
 THAT WERE CORRECTED.
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  