| Date |
Text |
| 2023-05-04 10:56:20 | THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE |
| | MARSHAL, WITH THE FOLLOWING COMMENTS: |
| | |
| | 1) THERE IS AN INDICATION OF A FIRE SPRINKLER |
| | PROTECTION; HOWEVER, THERE IS NO INDICATION OF FIRE |
| | SPRINKLER DOCUMENTATION REQUIRED BY F.A.C 61G |
| | |
| | THE FIRE SPRINKLER AND FIRE ALARM DOCUMENTS IS REQUIRED |
| | TO BE SUBMITTED WITH THIS MASTER PERMIT. AFTER APPROVAL |
| | OF THIS MASTER WITH THE FS & FA DOCUMENTS, SHOP |
| | DRAWINGS CAN THEN BE SUBMITTED THAT WILL BE COMPLIANT |
| | WITH THE MASTER FS & FA DOCUMENTS. |
| | |
| | THE FS & FA DOCUMENTS ARE NOT REQUIRED TO BE FULL SET |
| | PLAN SUBMITTALS. THEY CAN BE WRITTEN DOCUMENTS BUT MUST |
| | CONTAIN THE REQUIRED INFO SETTING THE DESIGN CRITERIA |
| | PER THE NOTED F.A.C. |
| | |
| | FAC 61G15-32.002 DEFINES THE FIRE PROTECTION SYSTEM |
| | ENGINEERING DOCUMENT (5) AS WELL AS THE FIRE PROTECTION |
| | SYSTEM LAYOUT DOCUMENT (6). 61G15-32.003 OUTLINES THE |
| | COMMON REQUIREMENTS TO ALL FIRE PROTECTIONS ENGINEERING |
| | DOCUMENTS WITH 32.004 (2) (A-J) OUTLINING THE MINIMUM |
| | INFORMATION TO BE PROVIDED ON FIRE PROTECTION |
| | ENGINEERING DOCUMENTS FOR WATER BASED SYSTEMS. AS |
| | STATED IN THE DEFINITIONS, THE CONTRACTOR IS TO DEVELOP |
| | THE LAYOUT DOCUMENTS BASED ON THE DESIGN CRITERIA |
| | PROVIDED IN THE FIRE PROTECTION ENGINEERING DOCUMENTS |
| | BY THE ENGINEER OF RECORD FOR THE FIRE SPRINKLER |
| | SYSTEM. THE FIRE PROTECTION SYSTEM ENGINEERING |
| | DOCUMENTS ARE SUBMITTED FOR THE MASTER PERMIT (BUILDING |
| | PERMIT PER FBC) AND THE LAYOUT DOCUMENTS ARE SUBMITTED |
| | FOR THE FIRE SPRINKLER INSTALLATION PERMIT. |
| | |
| | PER FLORIDA ADMINISTRATIVE CODE SECTION 61G15-32.004, |
| | FIRE PROTECTION ENGINEERING DOCUMENTS SHALL INCLUDE THE |
| | POINT OF SERVICE FOR THE WATER SUPPLY, A LIST OF |
| | APPLICABLE NFPA STANDARDS APPLICABLE TO THE PROJECT, |
| | CLASSIFICATION OF HAZARD OCCUPANCY FOR EACH ROOM OR |
| | AREA, SUPPRESSION SYSTEM TYPE, DESIGN DENSITIES, WATER |
| | SUPPLY DATA (FIRE PUMP DATA, HYDRANT FLOW TEST DATA) |
| | AND ANY PERFORMANCE BASED INFORMATION SUCH AS |
| | PRE-ENGINEERED SYSTEMS. |
| | |
| | 61G15-30.003 MINIMUM REQUIREMENTS FOR ENGINEERING |
| | DOCUMENTS. |
| | (1) ENGINEERING DOCUMENTS ARE PREPARED IN THE COURSE OF |
| | PERFORMING ENGINEERING SERVICES. WHEN PREPARED FOR |
| | INCLUSION WITH AN APPLICATION FOR A GENERAL BUILDING |
| | PERMIT, THE DOCUMENTS SHALL MEET ALL ENGINEER???S |
| | RESPONSIBILITY RULES, SET FORTH IN CHAPTERS 61G15-31, |
| | 61G15-32, 61G15-33, AND 61G15-34, F.A.C., AND BE OF |
| | SUFFICIENT CLARITY TO INDICATE THE LOCATION, NATURE AND |
| | EXTENT OF THE WORK PROPOSED AND SHOW IN DETAIL THAT IT |
| | WILL CONFORM TO THE PROVISIONS OF THE FLORIDA BUILDING |
| | CODE, ADOPTED IN SECTION 553.73, F.S., AND APPLICABLE |
| | LAWS, ORDINANCES, RULES AND REGULATIONS, AS DETERMINED |
| | BY THE AHJ. THE DOCUMENTS SHALL INCLUDE: |
| | (A) INFORMATION THAT PROVIDES MATERIAL SPECIFICATIONS |
| | REQUIRED FOR THE SAFE OPERATION OF THE SYSTEM THAT IS A |
| | RESULT OF ENGINEERING CALCULATIONS, KNOWLEDGE AND |
| | EXPERIENCE. |
| | (B) LIST FEDERAL, STATE, MUNICIPAL, AND COUNTY |
| | STANDARDS, CODES, ORDINANCES, LAWS, AND RULES, WITH |
| | THEIR EFFECTIVE DATES, THAT THE ENGINEERING DOCUMENTS |
| | ARE INTENDED TO CONFORM TO. |
| | (C) INFORMATION, AS DETERMINED BY THE ENGINEER OF |
| | RECORD, NEEDED FOR THE SAFE AND EFFICIENT OPERATION OF |
| | THE SYSTEM. |
| | (D) LIST ENGINEERING DESIGN CRITERIA; REFERENCE PROJECT |
| | SPECIFIC STUDIES, REPORTS, AND DELEGATED ENGINEERING |
| | DOCUMENTS. |
| | (E) IDENTIFY CLEARLY ELEMENTS OF THE DESIGN THAT VARY |
| | FROM THE GOVERNING STANDARDS AND DEPICT/IDENTIFY THE |
| | ALTERNATE METHOD USED TO ENSURE COMPLIANCE WITH THE |
| | STATED PURPOSE OF THESE RESPONSIBILITY RULES. |
| | (2) ENGINEERS SHALL LEGIBLY INDICATE THEIR NAME AND |
| | BUSINESS ADDRESS, ON ENGINEERING DOCUMENTS. ENGINEERING |
| | DOCUMENTS WHICH ARE ISSUED FOR PRELIMINARY OR |
| | CONCEPTUAL USE, SHALL CLEARLY NOTE THE INTENDED PURPOSE |
| | OF SUCH DOCUMENTS. |
| | (3) WHEN ELEMENTS OF THE PROJECT ARE SHOWN ON AN |
| | ENGINEERING DOCUMENT ONLY FOR INFORMATION OR |
| | CLARIFICATION AND THE ENGINEER DOES NOT INTEND TO |
| | ACCEPT RESPONSIBILITY FOR THE ELEMENTS, THE ENGINEER |
| | SHALL CLEARLY NOTE ON THE DOCUMENTS THE EXTENT OF HIS |
| | RESPONSIBILITY. |
| | (4) ENGINEERING DRAWINGS SHALL BE LEGIBLE AND CLEARLY |
| | DEFINE AND DELINEATE THE WORK IN THE PROJECT. THEY MUST |
| | ALSO COMPLY WITH CHAPTER 61G15-23, F.A.C., SEALS. |
| | (5) ENGINEERS SHALL CLEARLY NOTE ON ANY PRELIMINARY |
| | ENGINEERING DOCUMENTS THAT SUCH DOCUMENTS ARE NOT IN |
| | FINAL FORM, BUT ARE BEING TRANSMITTED TO THE PUBLIC |
| | AGENCY TO RECEIVE AGENCY REVIEWS, COMMENTS AND |
| | INTERPRETATIONS. THE DOCUMENTS MAY SUBSEQUENTLY BE |
| | REVISED BY THE ENGINEER TO REFLECT RESOLUTION OF ISSUES |
| | WITH THE PUBLIC AGENCY PRIOR TO FINAL ACTION BY THE |
| | AGENCY. CHANGES, REVISIONS AND MODIFICATIONS TO A |
| | PROJECT MAY PROMPT ADDITIONAL DOCUMENT SUBMITTAL FOR |
| | AGENCY APPROVAL ACTION ON THE SAME PROJECT. |
| | |
| | |
| | EVEN IF THE EOR DEFERS TO A LOCAL QUALIFIED CONTRACTOR, |
| | THAT CONTRACTOR MUST SUBMIT THE REQUIRED 61G |
| | INFORMATION WITH THIS MASTER. |
| | |
| | 61G15-32.008 DESIGN OF FIRE ALARMS AND DETECTION |
| | SYSTEMS. |
| | (1) FIRE ALARMS AND DETECTION SYSTEMS INCLUDE FIRE |
| | PROTECTION SUPERVISION, EMERGENCY ALARM CIRCUITS, |
| | ACTIVATION OF LIFE SAFETY SYSTEM CONTROLS AND REMOTE |
| | SIGNALING OF EMERGENCY CONDITIONS. |
| | (2) THE DESIGN SPECIFICATIONS SHALL BE BASED ON THE |
| | FLORIDA BUILDING CODE (2007), THE FLORIDA FIRE |
| | PREVENTION CODE, OR AS REQUIRED BY THE LOCAL AUTHORITY |
| | HAVING JURISDICTION. |
| | (3) FOR FIRE ALARM PLANS ON SMALL SYSTEMS BELOW THE |
| | THRESHOLD REQUIREMENTS FOR MANDATORY USE OF |
| | PROFESSIONAL ENGINEERING SERVICES, THE ENGINEER OF |
| | RECORD SHALL SPECIFY THE MINIMUM SYSTEM REQUIREMENTS. |
| | (4) TO ENSURE MINIMUM DESIGN QUALITY OF FIRE ALARM AND |
| | DETECTION SYSTEMS ENGINEERING DOCUMENTS, SAID DOCUMENTS |
| | SHALL INCLUDE AS A MINIMUM THE FOLLOWING INFORMATION |
| | WHEN APPLICABLE: |
| | (A) THE PLANS SHALL BE CLEAR, WITH A SYMBOLS LEGEND, |
| | SYSTEM RISER DIAGRAM SHOWING ALL INITIATION AND |
| | NOTIFICATION COMPONENTS, AND CABLING REQUIREMENTS. |
| | INDICATE LOCATIONS WHERE FIRE RATINGS ARE REQUIRED AS |
| | DETERMINED BY THE SYSTEM???S SURVIVABILITY |
| | REQUIREMENTS. IDENTIFY THE GENERAL OCCUPANCY OF THE |
| | PROTECTED PROPERTY, AND FOR EACH ROOM AND AREA UNLESS |
| | IT IS CLEAR FROM FEATURES SHOWN. |
| | (B) LOCATE INITIATION AND NOTIFICATION DEVICES AND |
| | CONNECTIONS TO RELATED SYSTEMS ON THE FLOOR PLANS AND |
| | SECTIONS WHEN NEEDED FOR CLARITY. RELATED SYSTEMS |
| | INCLUDE ELEVATOR CONTROLS SMOKE CONTROL SYSTEMS, |
| | DAMPERS, AND DOORS. |
| | (C) STROBE INTENSITY AND SPEAKER OUTPUT RATINGS FOR ALL |
| | NOTIFICATION DEVICES. |
| | (D) IDENTIFY THE CLASS AND STYLE OF CIRCUITS AS LISTED |
| | IN THE NFPA 72. |
| | (E) IDENTIFY THE FUNCTIONS REQUIRED BY THE ALARM AND |
| | CONTROL SYSTEMS INCLUDING THE TRANSMISSION OF EMERGENCY |
| | SIGNALS BEING MONITORED OR ANNUNCIATED. |
| | (F) INDICATE WHETHER THE FIRE ALARM IS CONVENTIONAL OR |
| | ADDRESSABLE, AND INDICATE ALL ZONING. |
| | (G) LOCATE SURGE PROTECTIVE DEVICES AND REQUIRED |
| | PROTECTIVE FEATURES. |
| | (H) LOCATE SYSTEM DEVICES THAT ARE SUBJECT TO |
| | ENVIRONMENTAL FACTORS, AND INDICATE REQUIREMENTS FOR |
| | THE PROTECTION OF EQUIPMENT FROM TEMPERATURE, HUMIDITY |
| | OR CORROSIVE ATMOSPHERES, INCLUDING COASTAL SALT AIR. |
| | (I) THE PLANS SHALL INCLUDE A SITE PLAN OF THE |
| | IMMEDIATE AREA AROUND THE PROTECTED BUILDING, STRUCTURE |
| | OR EQUIPMENT WHEN ALARM DEVICES ARE REQUIRED OUTSIDE |
| | THE STRUCTURE. |
| | (J) IN BUILDINGS WERE SMOKE DETECTION WILL BE |
| | OBSTRUCTED BY WALLS, BEAMS OR CEILING FEATURES, THE |
| | ENGINEER OF RECORD SHALL PROVIDE APPLICABLE DESIGN AND |
| | DETAILS TO DIRECT THE INSTALLER TO MITIGATE THE |
| | OBSTRUCTIONS. IN BUILDINGS WITH SMOKE DETECTION UNDER A |
| | PITCHED ROOF, THE PLANS SHALL INDICATE THE ROOF PITCH |
| | AND A BUILDING SECTION SHALL BE PROVIDED AS PART OF THE |
| | ENGINEERING DESIGN DOCUMENTS. |
| | (K) FIRE DETECTION SYSTEMS UTILIZING SMOKE DETECTION IN |
| | SITUATIONS WHERE SMOKE STRATIFICATION IS ANTICIPATED, |
| | THE DESIGN SHALL PROVIDE THE NECESSARY CRITERIA TO |
| | MITIGATE THE DETECTION PROBLEMS. |
| | (L) SYSTEMS DESIGNED USING PERFORMANCE BASED CRITERIA |
| | SHALL BE IDENTIFIED AND REFERENCED TO DESIGN GUIDES OR |
| | STANDARDS APPROVED BY THE LOCAL AUTHORITY HAVING |
| | JURISDICTION CONSISTENT WITH STANDARDS ADOPTED BY THE |
| | FLORIDA FIRE PREVENTION CODE AND THE FLORIDA BUILDING |
| | CODE (2007). |
| | (M) THE SYSTEM DESIGN MUST INDICATE IF THE SYSTEM IS TO |
| | PROVIDE A GENERAL EVACUATION SIGNAL OR A ZONED |
| | EVACUATION FOR ALL HIGH-RISE BUILDINGS OR |
| | MULTI-TENANTED PROPERTIES AS DEFINED IN THE FLORIDA |
| | BUILDING CODE (2007). |
| | (N) WIRING REQUIREMENTS FOR UNDERGROUND, WET LOCATIONS, |
| | CAMPUS STYLE WIRING, PROTECTION AGAINST DAMAGE AND |
| | BURIAL DEPTH SHALL BE SPECIFIED OR INDICATED ON THE |
| | ENGINEERING DESIGN DOCUMENTS. |
| | (O) REQUIREMENTS FOR OPERATIONS AND MAINTENANCE |
| | PROCEDURES, MANUALS, SYSTEM DOCUMENTATION, AND |
| | INSTRUCTION OF OWNER???S OPERATING PERSONNEL, AS NEEDED |
| | TO OPERATE THE SYSTEMS AS INTENDED OVER TIME. |
| | (5) IN THE EVENT THAT THE ENGINEER OF RECORD ELECTS TO |
| | SPECIFY SPECIFIC EQUIPMENT AND TO SHOW THE REQUIRED |
| | WIRING, BATTERY AND VOLTAGE DROP (CIRCUIT ANALYSIS) |
| | CALCULATIONS SHALL BE COMPLETED. THE CALCULATIONS SHALL |
| | BE COMPLETED USING THE EQUIPMENT MANUFACTURE???S DATA |
| | AND APPLICABLE NFPA 72 PROCEDURES. |
| | (6) SYSTEM TEST REQUIREMENTS SHALL BE NOTED ON THE |
| | ENGINEERING DESIGN DOCUMENTS. |
| | (7) WHEN THE ENGINEER DETERMINES THAT SPECIAL |
| | REQUIREMENTS ARE REQUIRED BY THE OWNER, INSURANCE |
| | UNDERWRITER OR LOCAL FIRE CODE AMENDMENTS THESE |
| | REQUIREMENTS SHALL BE DOCUMENTED OR REFERENCED ON THE |
| | ENGINEERING DESIGN DOCUMENTS. |
| | |
| | |
| | |
| | 2) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET |
| | REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE |
| | ABOVE. |
| | |
| | 3) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE |
| | RE-SUBMITTAL OF THE ABOVE. |
| | |
| | |
| | PETER LEDUC |
| | FIRE MARSHAL |
| | 561-804-4709 |
| | [email protected] |
| | |
| | |