| 2022-09-20 12:24:25 | 1ST BUILDING REVIEW |
| | RESULTS: CORRECTIONS NEEDED |
| | |
| | CHRISTOPHER S. THROOP, C.B.O., CFM |
| | PLANS EXAMINER II |
| | CITY OF WEST PALM BEACH |
| | (561) 805-6726 |
| | [email protected] |
| | |
| | CODES IN EFFECT: |
| | 2020 FLORIDA BUILDING CODE, 7TH EDITION W/2017 WEST |
| | PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING CODE, |
| | CHAPTER 1 ADMINISTRATION |
| | NFPA 70 2017 EDITION NEC 2017 |
| | |
| | ADDRESS THE FOLLOWING COMMENTS AND RE-SUBMIT: |
| | |
| | 1. PROVIDE A SITE PLAN.... |
| | 107.2.5 SITE PLAN. THE CONSTRUCTION DOCUMENTS SUBMITTED |
| | WITH THE APPLICATION FOR PERMIT SHALL BE ACCOMPANIED BY |
| | A SITE PLAN SHOWING TO SCALE THE SIZE AND LOCATION OF |
| | NEW CONSTRUCTION AND EXISTING STRUCTURES ON THE SITE, |
| | AND IT SHALL BE DRAWN IN ACCORDANCE WITH AN ACCURATE |
| | AND INCLUDED BOUNDARY LINE SURVEY. |
| | |
| | 2. PROVIDE A SITE DRAINAGE PLAN PER FBC R401.3 |
| | IT SHALL BE DRAWN IN ACCORDANCE WITH AN ACCURATE AND |
| | INCLUDED BOUNDARY LINE SURVEY. |
| | FBC R401.3 SITE DRAINAGE |
| | SURFACE DRAINAGE SHALL BE DIVERTED TO A STORM SEWER |
| | CONVEYANCE OR OTHER APPROVED POINT OF COLLECTION THAT |
| | DOES NOT CREATE A HAZARD. |
| | LOTS SHALL BE GRADED TO DRAIN SURFACE WATER AWAY FROM |
| | FOUNDATION WALLS. THE GRADE SHALL FALL A MINIMUM OF 6 |
| | INCHES WITHIN THE FIRST 10 FEET. |
| | |
| | 3.PROVIDE THE FINISH FLOOR ELEVATION NON-FLOOD ZONE |
| | R403.1.7.3 FOUNDATION ELEVATION. |
| | ON GRADED SITES, THE TOP OF ANY EXTERIOR FOUNDATION |
| | SHALL EXTEND ABOVE THE ELEVATION OF THE STREET GUTTER |
| | AT POINT OF DISCHARGE OR THE INLET OF AN APPROVED |
| | DRAINAGE DEVICE A MINIMUM OF 12 INCHES (305 MM) PLUS 2 |
| | PERCENT. ALTERNATE ELEVATIONS ARE PERMITTED SUBJECT TO |
| | THE APPROVAL OF THE BUILDING OFFICIAL, PROVIDED IT CAN |
| | BE DEMONSTRATED THAT REQUIRED DRAINAGE TO THE POINT OF |
| | DISCHARGE AND AWAY FROM THE STRUCTURE IS PROVIDED AT |
| | ALL LOCATIONS ON THE SITE. |
| | |
| | 4.PROVIDE A SOILS REPORT. |
| | R401.4 SOIL TESTS. |
| | WHERE QUANTIFIABLE DATA CREATED BY ACCEPTED SOIL |
| | SCIENCE METHODOLOGIES INDICATE EXPANSIVE, COMPRESSIBLE, |
| | SHIFTING OR OTHER QUESTIONABLE SOIL CHARACTERISTICS ARE |
| | LIKELY TO BE PRESENT, THE BUILDING OFFICIAL SHALL |
| | DETERMINE WHETHER TO REQUIRE A SOIL TEST TO DETERMINE |
| | THE SOIL???S CHARACTERISTICS AT A PARTICULAR LOCATION. |
| | THIS TEST SHALL BE DONE BY AN APPROVED AGENCY USING AN |
| | APPROVED METHOD. |
| | FBC1803.2 INVESTIGATIONS REQUIRED. |
| | |
| | 5.PROVIDE THE DESIGN PRESSURES FOR NEW ROOFING PER |
| | FIGURE R301.2(7) COMPONENT AND CLADDING PRESSURE ZONES |
| | R301.2.1.1WIND DESIGN REQUIRED. |
| | |
| | 6.PROVIDE A ROOF SHEATHING FASTENER SCHEDULE PER THE |
| | CALCULATED DESIGN PRESSURES. |
| | TABLE R301.2.1.2 WINDBORNE DEBRIS PROTECTION FASTENING |
| | SCHEDULE FOR WOOD STRUCTURAL PANELS. |
| | |
| | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |