| Date |
Text |
| 2022-07-27 11:52:03 | ****CORRECTIONS**** |
| | |
| | SAMANTHA HILL |
| | BUILDING PLANS EXAMINER |
| | [email protected] |
| | 561-805-6724 |
| | |
| | |
| | PLEASE SEE THE "DEMOLITION PERMIT APPLICATION |
| | CHECKLIST" WHICH YOU CAN FIND AT THE FOLLOWING WEBSITE |
| | (IF NOT AVAILABLE, EMAIL [email protected] AND REQUEST): |
| | |
| | HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B |
| | UILDING-PERMIT-FORMS |
| | |
| | THE FOLLOWING ITEMS ARE REQUIRED PRIOR TO ISSUANCE OF A |
| | DEMO PERMIT PER FLORIDA BUILDING CODE, BUILDING 3303, |
| | FBC 107: |
| | |
| | 1. UTILITY RELEASE - FLORIDA POWER & LIGHT (ELECTRIC) |
| | RELEASE OF SERVICE CONFIRMATION |
| | |
| | 2. UTILITY RELEASE - FLORIDA PUBLIC UTILITIES (GAS) |
| | RELEASE OF SERVICE CONFIRMATION |
| | |
| | 3. UTILITY RELEASE - CITY OF WEST PALM BEACH WATER |
| | DEPARTMENT, REQUEST FOR METER PULL, ON THEIR FORM |
| | "DEMOLITION APPLICATION" |
| | |
| | HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B |
| | UILDING-PERMIT-FORMS |
| | |
| | IF A HYDRANT METER OR BACKFLOW PREVENTER IS DESIRED, |
| | THEN A PARTIAL RELEASE WILL BE NOTED ON THEIR FORM. |
| | |
| | FAX THE COMPLETED "DEMOLITION APPLICATION" FORM TO |
| | 561-822-2183. |
| | |
| | 4. SEWER LATERAL CAPPING PERMIT IS REQUIRED (SUBMIT |
| | APPLICATION TO BUILDING DIVISION); SCHEDULE A FINAL |
| | PLUMBING #703. PLEASE NOTIFY US VIA EMAIL AFTER FINAL |
| | INSPECTION HAS PASSED). |
| | |
| | 5. EXTERMINATION LETTER - LETTER FROM A LICENSED PEST |
| | CONTROL COMPANY STATING THAT DEMOLITION ADDRESS HAS |
| | BEEN INSPECTED AND/OR TREATED FOR RODENTS. |
| | |
| | 6. PLEASE CLARIFY, ARE THE CONCRETE FOOTINGS AND BLOCK |
| | PIERS BEING REMOVED? IF YES, THE FOLLOWING ITEMS ARE |
| | REQUIRED: |
| | |
| | 7. COMPLETE THE DEMO DEBRIS FORM, FEES WILL BE ADDED TO |
| | YOUR PERMIT "DEMOLITION DEBRIS DISPOSAL FEE": |
| | |
| | HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B |
| | UILDING-PERMIT-FORMS |
| | |
| | IF THE FORM IS UNAVAILABLE ONLINE, REQUEST AT |
| | [email protected]. |
| | |
| | 8. SUBMIT A STORMWATER POLLUTION PREVENTION PLAN. |
| | |
| | 9. SUBMIT A LETTER INDICATING HOW DUST CONTROL WILL BE |
| | ACCOMPLISHED. IF ON SITE WATER IS USED, A BACKFLOW |
| | PREVENTER IS REQUIRED. |
| | |
| | |