| 2022-08-05 16:46:55 | NEW SFR |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected] |
| | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 |
| | AMENDMENT |
| | |
| | CORRECTIONS NEEDED - |
| | |
| | 1) PLEASE PROVIDE A COMPLETE (FRONT PAGES AND THE |
| | INSTALLATION INSTRUCTIONS) MIAMI DADE OR FLORIDA STATE |
| | PRODUCT APPROVAL FOR THE ROOF SYSTEM. |
| | |
| | 2) SITE PLAN NEEDS TO SHOW THE LOT DRAINAGE - AWAY FROM |
| | THE HOUSE AND AWAY FROM THE ADJACENT PROPERTY - PLEASE |
| | PROVIDE A SURVEY/SITE PLAN SHOWING THE FOLLOWING |
| | INFORMATION FBC WPB 107.2.5 SITE PLAN. THE CONSTRUCTION |
| | DOCUMENTS SUBMITTED WITH THE APPLICATION FOR PERMIT |
| | SHALL BE ACCOMPANIED BY A SITE PLAN SHOWING TO SCALE |
| | THE SIZE AND LOCATION OF NEW CONSTRUCTION AND EXISTING |
| | STRUCTURES ON THE SITE, DISTANCES FROM LOT LINES, THE |
| | ESTABLISHED STREET GRADES AND THE PROPOSED FINISHED |
| | GRADES, DEPICTING THE PROPOSED LOT DRAINAGE AND, AS |
| | APPLICABLE, FLOOD HAZARD AREAS, FLOODWAYS, AND DESIGN |
| | FLOOD ELEVATIONS; AND IT SHALL BE DRAWN IN ACCORDANCE |
| | WITH AN ACCURATE AND INCLUDED ON A BOUNDARY LINE |
| | SURVEY. (PLEASE PROVIDE CUT SECTIONS FOR ANY PROPOSED |
| | WATER RETAINING SWALES) |
| | |
| | 3) PLEASE SHOW THE REQUIRED ROOF VENTILATION (THIS TYPE |
| | OF ROOF CONSTRUCTION WOULD SOMETIMES USE SPRAYFOAM |
| | (ICYNENE) INSULATION WHICH WOULD NOT REQUIRE THE ATTIC |
| | SPACE TO BE VENTED) - FBC R806.1 VENTILATION REQUIRED. |
| | ENCLOSED ATTICS AND ENCLOSED RAFTER SPACES FORMED WHERE |
| | CEILINGS ARE APPLIED DIRECTLY TO THE UNDERSIDE OF ROOF |
| | RAFTERS SHALL HAVE CROSS VENTILATION FOR EACH SEPARATE |
| | SPACE BY VENTILATING OPENINGS PROTECTED AGAINST THE |
| | ENTRANCE OF RAIN OR SNOW. VENTILATION OPENINGS SHALL |
| | HAVE A LEAST DIMENSION OF 1/16 INCH (1.6 MM) MINIMUM |
| | AND 1/4 INCH (6.4 MM) MAXIMUM. VENTILATION OPENINGS |
| | HAVING A LEAST DIMENSION LARGER THAN 1/4 INCH (6.4 MM) |
| | SHALL BE PROVIDED WITH CORROSION-RESISTANT WIRE CLOTH |
| | SCREENING, HARDWARE CLOTH, PERFORATED VINYL OR SIMILAR |
| | MATERIAL WITH OPENINGS HAVING A LEAST DIMENSION OF 1/16 |
| | INCH (1.6 MM) MINIMUM AND 1/4 INCH (6.4 MM) MAXIMUM. |
| | OPENINGS IN ROOF FRAMING MEMBERS SHALL CONFORM TO THE |
| | REQUIREMENTS OF SECTION R802.7. REQUIRED VENTILATION |
| | OPENINGS SHALL OPEN DIRECTLY TO THE OUTSIDE AIR AND |
| | SHALL BE PROTECTED TO PREVENT THE ENTRY OF BIRDS, |
| | RODENTS, SNAKES AND OTHER SIMILAR CREATURES. |
| | |
| | 4) PLEASE SHOW THE ROOF SCUPPER TO BE AT THE LEVEL OF |
| | THE FINISHED ROOF - FBC R903.4 ROOF DRAINAGE. |
| | UNLESS ROOFS ARE SLOPED TO DRAIN OVER ROOF EDGES, ROOF |
| | DRAINS SHALL BE INSTALLED AT EACH LOW POINT OF THE |
| | ROOF. WHERE REQUIRED FOR ROOF DRAINAGE, SCUPPERS SHALL |
| | BE PLACED LEVEL WITH THE ROOF SURFACE IN A WALL OR |
| | PARAPET. THE SCUPPER SHALL BE LOCATED AS DETERMINED BY |
| | THE ROOF SLOPE AND CONTRIBUTING ROOF AREA. |
| | |
| | 5) PLEASE SHOW THE OVER FLOW ROOF SCUPPER TO BE 2 TO 4" |
| | FROM THE FINISHED ROOF - FBC R903.4.1 OVERFLOW DRAINS |
| | AND SCUPPERS. |
| | WHEN OTHER MEANS OF DRAINAGE OF OVERFLOW WATER IS NOT |
| | PROVIDED, OVERFLOW SCUPPERS SHALL BE PLACED IN WALLS OR |
| | PARAPETS NOT LESS THAN 2 INCHES (51 MM) NOR MORE THAN 4 |
| | INCHES (102 MM) ABOVE THE FINISHED ROOF COVERING. |
| | |
| | 6) EXTERIOR WALL DETAIL ON DRAWING 6 SHOULD SHOW THE U |
| | BLOCK BEAM AT THE TRUSS LEDGER TO PROVIDE FOR THE |
| | BOLTING OF THE LEDGER. |
| | |
| | 7) ADDRESS SHOWN ON THE DRAWING NEEDS TO MATCH THE |
| | ADDRESS SHOWN ON THE BUILDING PERMIT APPLICATION. |