| 2022-09-01 15:55:02 | ADDITION AND REMODEL |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected] |
| | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 |
| | AMENDMENT |
| | |
| | CORRECTIONS NEEDED - |
| | |
| | 1) DRAWING A303 - RESTROOM DOOR NEAR THE REAR STAIR |
| | APPEARS TO SWING IN THE EGRESS PATH - FBC 1005.7.1 |
| | DOORS. |
| | DOORS, WHEN FULLY OPENED, SHALL NOT REDUCE THE REQUIRED |
| | WIDTH BY MORE THAN 7 INCHES (178 MM). DOORS IN ANY |
| | POSITION SHALL NOT REDUCE THE REQUIRED WIDTH BY MORE |
| | THAN ONE-HALF. |
| | |
| | 2) PLEASE PROVIDE COMPLETE (FRONT PAGES AND THE |
| | INSTALLATION INSTRUCTIONS) MIAMI DADE OR FLORIDA STATE |
| | PRODUCT APPROVALS FOR THE NEW EXTERIOR WINDOWS, DOORS |
| | AND ROOFING SYSTEMS - ALL PRODUCT APPROVALS NEED TO BE |
| | REVIEWED AND MARKED APPROVED BY THE BUILDING DESIGNER |
| | OF RECORD FBC WPB 107.3.4 |
| | |
| | 3) DRAWING A 403 - ELEVATIONS ARE NOT LABELED CORRECTLY |
| | (BOTH ARE LABELED EXISTING). |
| | |
| | 4) DRAWING A 201 - PLEASE SHOW THE USE FOR EACH ROOM OR |
| | SPACE. |
| | |
| | 5) PLEASE SHOW THAT TERMITE TREATMENT IS A REQUIREMENT |
| | PER FBC 1816 |
| | |
| | 6) DRAWING A 501 - SHOW THE CEILING HEIGHT FOR THE |
| | EGRESS CATWALK AT STAIRS - FBC 1003.2 |
| | |
| | 7) DRAWING A 604 - GAZEBO WALL DETAIL - WHAT IS (W-4H |
| | AND W-4B) ? |
| | |
| | 8) PLEASE SHOW ALL CEILING HEIGHTS (OFFICE, STORAGE |
| | ETC.) - FBC 1208.2 |
| | |
| | 9) DRAWING A 102 - UNDER OCCUPANCY LOAD I DO NOT SEE |
| | THE POOL AREA OCCUPANT LOAD - PLEASE PROVIDE BUILDING |
| | AREA SQUARE FOOTAGES. |
| | |
| | 10) PLEASE PROVIDE A BUILDING SPRINKLER LAYOUT PLAN - |
| | FBC 903.2.1 |
| | |
| | 11) PLEASE SHOW THE LOCATION FOR THE OCCUPANT LOAD SIGN |
| | PER FBC 1004.9 |
| | |
| | 12) ON DRAWING A 101 IN THE "BUILDING CODE ANALYSIS" |
| | CHART PLEASE DESCRIBE THE BUILDING SEPARATION FROM THE |
| | ADJOINING BUILDINGS - FBC 508 NON-SEPARATED, SEPARATED |
| | - SHOW THE WALL SEPARATION TYPE - FIRE BARRIER FBC |
| | 707.3.9 OR FIRE WALL FBC 706 - SHOW THE OCCUPANCY |
| | CLASSIFICATION FOR THE ADJOINING UNITS OR BUILDINGS FBC |
| | CHAPTER 3. |
| | |
| | 13) PLEASE SHOW WALL DESIGNATIONS ON THE FLOOR PLANS - |
| | SHOW FIRE WALLS ETC. FBC WPB 107.2 |
| | |
| | 14) THE REAR WALL NEEDS TO SHOW AS 1 HOUR FIRE RATED - |
| | FBC TABLE 602 |
| | |
| | 15) BASED ON THE DISTANCE FROM THE CENTER OF THE ALLY |
| | TO THE REAR WALL OPENINGS - PLEASE SHOW THE ALLOWABLE |
| | NON PROTECTED OPENING CALCULATIONS - FBC TABLE 705.8 |
| | |
| | 16) PLEASE SHOW THE POOL BARRIER (DOORS, LOCKS, LATCH |
| | HEIGHT ETC.) AT THE STAIR AND ELEVATOR DOORS TO COMPLY |
| | WITH FBC 454.1.3.1.9 |
| | |
| | 17) PLEASE SHOW THE ACCESSIBLE POOL ENTRY - FBC A 242.2 |
| | SWIMMING POOLS. |
| | AT LEAST TWO ACCESSIBLE MEANS OF ENTRY SHALL BE |
| | PROVIDED FOR SWIMMING POOLS. ACCESSIBLE MEANS OF ENTRY |
| | SHALL BE SWIMMING POOL LIFTS COMPLYING WITH 1009.2; |
| | SLOPED ENTRIES COMPLYING WITH 1009.3; TRANSFER WALLS |
| | COMPLYING WITH 1009.4; TRANSFER SYSTEMS COMPLYING WITH |
| | 1009.5; AND POOL STAIRS COMPLYING WITH 1009.6. AT LEAST |
| | ONE ACCESSIBLE MEANS OF ENTRY PROVIDED SHALL COMPLY |
| | WITH 1009.2 OR 1009.3. |
| | |
| | 18) PLEASE SHOW THE DIFFERENT DINING AREA LOCATIONS FOR |
| | THE ACCESSIBLE SEATING - FBC 226 |
| | |
| | 19) PLEASE SHOW AT LEAST 1 ACCESSIBLE SEAT AT EACH BAR |
| | LOCATION (SHOW COUTER HEIGHT, KNEE AND TOE CLEARANCES |
| | ETC. ) - FBC 226.2 |
| | |
| | 20) DRAWING A 603 - DETAIL P1, P2, P3 - THE MAX. 36 |
| | INCHES FOR THE GRAB BAR HEIGHT SHOULD BE SHOWN TO THE |
| | TOP OF THE GRIPPING SURFACE FBC A 609.4 |
| | |
| | 21) THE MOVABLE ROOF SYSTEM ENGINEERING FROM "F AND M |
| | MAFCO" NEEDS TO BE SIGNED AND SEALED BY THE DESIGNER - |
| | FBC WPB 107.1 |
| | |
| | 22) THE MOVABLE ROOF SYSTEM ENGINEERING FROM "F AND M |
| | MAFCO" NEEDS TO BE REVIEWED AND MARKED APPROVED BY THE |
| | ENGINEER OF RECORD (LOADS MUST BE CHECKED BY THE |
| | ENGINEER OF RECORD AS NOTED ON THE RETRACTABLE ROOF |
| | DRAWING) FBC WPB 107.3.4 |
| | |
| | 23) PLEASE PROVIDE TYPICAL GUARDRAIL AND HANDRAIL |
| | DETAILS - SHOWING HEIGHTS, OPENING SPECS., HANDRAIL |
| | EXTENSIONS ETC. FBC 1014 AND 1015 |
| | |
| | 24) PLEASE PROVIDE A THRESHOLD INSPECTION PLAN - FBC |
| | (CITY AMENDMENTS)110.8.1 THRESHOLD INSPECTION PLAN. THE |
| | ENFORCING AGENCY SHALL REQUIRE A SPECIAL INSPECTOR TO |
| | PERFORM STRUCTURAL INSPECTIONS ON A THRESHOLD BUILDING |
| | PURSUANT TO A STRUCTURAL INSPECTION PLAN PREPARED BY |
| | THE ENGINEER OF RECORD. |
| | |
| | 25) THE STRUCTURAL DRAWINGS NEED TO CONTAIN THIS NOTE - |
| | THRESHOLD BLDG. REQUIRED STATEMENT: W.P.B. AMENDMENT |
| | 110.8.4.4 ALL PLANS FOR THE BUILDING WHICH ARE REQUIRED |
| | TO BE SIGNED AND SEALED BY THE ARCHITECT OR ENGINEER OF |
| | RECORD CONTAIN A STATEMENT THAT, TO THE BEST OF THE |
| | ARCHITECT'S OR ENGINEER'S KNOWLEDGE, THE PLANS AND |
| | SPECIFICATIONS COMPLY WITH THE APPLICABLE MINIMUM |
| | BUILDING CODES AND THE APPLICABLE FIRE-SAFETY STANDARDS |
| | AS DETERMINED BY THE LOCAL AUTHORITY IN ACCORDANCE WITH |
| | THIS SECTION AND CHAPTER 633 FLORIDA STATUTES. |
| | |
| | 26) PLEASE READ AND FILL OUT THE REQUIRED DOCUMENTS PER |
| | THE "GUIDELINES AND POLICIES FOR PROJECTS CONCERNING |
| | THRESHOLD/SPECIAL INSPECTORS AND RESIDENT INSPECTORS". |
| | YOU CAN E MAIL ME AND ASK FOR A COPY. |
| | |
| | 27) PLEASE PROVIDE A COPY OF THE UNITY OF TITLE. |
| | |
| | 28) A SEPARATE PERMIT IS REQUIRED FOR THE BUILDING |
| | DEMO. |
| | |
| | 29) ITEMS SUCH AS BUT NOT LIMITED TO EXTERIOR WINDOW, |
| | DOOR AND ROOFING SYSTEMS PRODUCT APPROVALS MAY BE |
| | DEFERRED SUBMITTALS BY LISTING ITEMS TO BE DEFERRED ON |
| | THE CONSTRUCTION DOCUMENTS - 107.3.4.1 DEFERRED |
| | SUBMITTALS. FOR THE PURPOSES OF THIS SECTION, DEFERRED |
| | SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF THE DESIGN |
| | THAT ARE NOT SUBMITTED AT THE TIME OF THE APPLICATION |
| | AND THAT ARE TO BE SUBMITTED TO THE BUILDING OFFICIAL |
| | WITHIN A SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL |
| | ITEMS SHALL HAVE THE PRIOR APPROVAL OF THE BUILDING |
| | OFFICIAL. THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE SHALL LIST THE DEFERRED SUBMITTALS |
| | ON THE CONSTRUCTION DOCUMENTS FOR REVIEW BY THE |
| | BUILDING OFFICIAL. DOCUMENTS FOR DEFERRED SUBMITTAL |
| | ITEMS SHALL BE SUBMITTED TO THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL REVIEW |
| | THEM AND FORWARD THEM TO THE BUILDING OFFICIAL WITH A |
| | NOTATION INDICATING THAT THE DEFERRED SUBMITTAL |
| | DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE IN GENERAL |
| | CONFORMANCE TO THE DESIGN OF THE BUILDING. THE DEFERRED |
| | SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL THE |
| | DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE |
| | BUILDING OFFICIAL. |
| | |
| | |