| 2023-05-11 17:53:28 | NEW SINGLE FAMILY RESIDENCE(R3) FOURTH BUILDING REVIEW |
| | COMMENTS |
| | CODE: FBC 7TH EDITION (2020) AND CITY AMENDMENTS. |
| | PERMIT #22060913 |
| | 922 AVON RD |
| | |
| | ORIGINAL COMMENT: |
| | 2- PROVIDE ENERGY CALCULATIONS AS REQUIRED BY SEC. |
| | R101.5 FBC-ENERGY CONSERVATION. |
| | NOTE: PLEASE MAKE SURE FORM IS PROPERLY SIGNED BY ALL |
| | REQUIRED PARTIES AND IS COORDINATED WITH PLANS TO AVOID |
| | CONFLICTS/DELAYS. |
| | |
| | PREVIOUS COMMENT: |
| | RESPONSE: [ COMMENTS NOT ADDRESSED.] |
| | ENERGY CALCULATIONS SUBMITTED: |
| | A)THE BUILDING'S OWNER, THE OWNER'S ARCHITECT, OR OTHER |
| | AUTHORIZED AGENT LEGALLY DESIGNATED BY THE OWNER SHALL |
| | CERTIFY AT THE OWNER/AGENT LINE AT THE BOTTOM OF FORM |
| | THAT THE BUILDING IS IN COMPLIANCE WITH THE CODE, AS |
| | PER SECTION 553.907, FLORIDA STATUTES, PRIOR TO |
| | RECEIVING THE PERMIT TO BEGIN CONSTRUCTION OR |
| | RENOVATION AS REQUIRED BY SECTION R103.1.1.2 FBC-ENERGY |
| | CONSERVATION. |
| | |
| | NEW RESPONSE ON 05/11/23: |
| | REPEAT COMMENT. NOT ADDRESSED. |
| | |
| | B)PROVIDE COMPLETE INFORMATION ON TOP OF FORM, |
| | INCLUDING BUILDER'S NAME. SEC. R101.5.1.1.2 FBC-ENERGY |
| | CONSERVATION. |
| | |
| | NEW RESPONSE ON 05/11/23: |
| | REPEAT COMMENT. NOT ADDRESSED. |
| | |
| | C)CEILING INFORMATION ON ITEM #11 DOESN'T MATCH PLANS. |
| | PLANS SHOW VENTED ATTIC AND ROOF INSULATION. |
| | |
| | NEW RESPONSE ON 05/11/23: |
| | REPEAT COMMENT. NOT ADDRESSED. |
| | |
| | D) WINDOWS ORIENTATION AND AREA DON'T MATCH PLANS. |
| | REVISE AS REQUIRED. SEC. R101.5.1.1.2 FBC-ENERGY |
| | CONSERVATION. |
| | |
| | NEW RESPONSE ON 05/11/23: |
| | REPEAT COMMENT. NOT ADDRESSED. |
| | |
| | E)BUILDER TO COMPLETE THE ENERGY PERFORMANCE LEVEL |
| | (EPL) DISPLAY CARD. SEC. R405.4.3 FBC-ENERGY |
| | CONSERVATION. |
| | |
| | NEW RESPONSE ON 05/11/23: |
| | REPEAT COMMENT. NOT ADDRESSED. |
| | |
| | NEW COMMENT BASED ON REVISED PLANS: |
| | F)REVISE SPACES INFORMATION ON PAGE 2. NEW PLANS DON'T |
| | SHOW A KITCHEN ANYMORE. |
| | SEC. R101.5.1.1.2 FBC-ENERGY CONSERVATION. |
| | |
| | 7- GUEST HOUSE ROOF FRAME DETAIL PLAN. |
| | ORIGINAL COMMENT: |
| | D)SPECIFY ROOF SHEATHING NAILING SPECIFICATIONS TO |
| | COMPLY WITH NEW 2020 FBC-RESIDENTIAL SPECIFICATIONS. |
| | SPECIFY THICKNESS, NAIL TYPE, SIZE AND SPACING. NOTE: |
| | NEED TO USE RING SHANK NAILS. ROOF SHEATHING NEEDS TO |
| | BE NAILED AT 4 INCHES O.C. IN THE FIELD AND EDGES AS |
| | REQUIRED BY SEC. R803.2.3.1 AND TABLE R803.2.3.1 |
| | FBC-RESIDENTIAL. |
| | |
| | PREVIOUS COMMENT: |
| | RESPONSE: [ NOT RESOLVED.] |
| | ROOF SHEATHING SPECIFICATIONS SHOWN ON THE COMPONENT |
| | AND CLADDING PRESSURE ZONES ON SHEET S.3. DON'T COMPLY |
| | WITH TABLE R803.2.3.1 FBC-RESIDENTIAL. REVISE AS |
| | REQUIRED. |
| | NOTE: COORDINATE WITH ITEM 4(B) ABOVE. |
| | |
| | NEW RESPONSE ON 05/11/23: |
| | NEW DESIGNER OF RECORD. REVISE THE ROOF NAILING PATTERN |
| | SPECIFIED ON SHEET S-3 UNDER "MAX. COMPONENTS AND |
| | CLADDING DESIGN WIND PRESSURES". SPECIFICATIONS ARE |
| | INCOMPLETE. IT ONLY SPECIFIES THE SPACING AT THE EDGE. |
| | NEED TO PROVIDE ROOF SHEATHING NAILING SPECIFICATIONS |
| | FOR ALL ROOF ZONES. TABLE R803.2.3.1 FBC-RESIDENTIAL. |
| | NOTE: PLYWOOD ROOF SHEATHING NAILING IS REQUIRED ALL |
| | THE TIME. IT IS NOT CLEAR WHY ARCHITECT WROTE NOTE "IF |
| | REQUIRED". CLARIFY AS REQUIRED. SEC. 107.2.1 CITY |
| | AMENDMENTS. |
| | |
| | ORIGINAL COMMENTS: |
| | 16- PRODUCT APPROVALS |
| | PROVIDE PRODUCT APPROVAL AS REQUIRED BY FAC 61G20-3.001 |
| | FOR: |
| | (NOTE: THIS MAY BE SUBMITTED LATER AS A DEFERRED |
| | SUBMITTAL. PROVIDE COMPLETE INFORMATION FOR REVIEW |
| | PRIOR TO INSTALLATION TO AVOID CONFLICTS/DELAYS. ALL |
| | PRODUCT APPROVALS NEED TO BE APPROVED IN WRITING BY |
| | DESIGNER OF RECORD PRIOR TO SUBMITTAL): |
| | |
| | ORIGINAL COMMENT: |
| | A)FLAT ROOF. AND, CLEARLY MARK WHICH APPROVED ASSEMBLY |
| | IS GOING TO BE INSTALLED TO VERIFY COMPLIANCE WITH THE |
| | DESIGN PRESSURES OF SEC. R301.1 FBC-RESIDENTIAL. |
| | NOTE: IF THE SELECTED ASSEMBLY DOESN'T MEET THE DESIGN |
| | PRESSURES FOR ALL ROOF ZONES, THEN SIGNED AND SEALED |
| | RAS 117 CALCULATIONS ARE REQUIRED. |
| | |
| | PREVIOUS COMMENT: |
| | RESPONSE: [ NOT RESOLVED. THE C & C PRESSURES SPECIFIED |
| | ON SHEET S.1 FOR THE DOORS AND WINDOWS ARE QUITE HIGH |
| | FOR A BUILDING LESS THAN 15 FT IN HEIGHT. ] |
| | REPEAT COMMENT. NOT ADDRESSED AND CONTRACTOR IS NOT |
| | SPECIFYING IF SUBMITTING NOW OR LATER AS DEFERRED |
| | SUBMITTAL. |
| | |
| | NEW RESPONSE ON 05/11/23: |
| | REPEAT COMMENT. NOT ADDRESSED AND CONTRACTOR IS NOT |
| | SPECIFYING IF SUBMITTING NOW OR LATER AS DEFERRED |
| | SUBMITTAL. |
| | NOTE: PRODUCT APPROVAL NEEDS TO BE REVIEWED AND |
| | APPROVED IN WRITING (NOT SIGNING AND SEALING) BY |
| | DESIGNER OF RECORD AS REQUIRED BY SEC. 107.3.4.1 CITY |
| | AMENDMENTS. |
| | |
| | PREVIOUS COMMENT: |
| | B)SLIDING GLASS DOORS THAT MEET THE DESIGN PRESSURES |
| | CALCULATED BY THE ENGINEER OF RECORD ON REVISED S.1 |
| | DRAWING. |
| | |
| | NEW RESPONSE ON 05/11/23: |
| | PRODUCT APPROVAL NEEDS TO BE REVIEWED AND APPROVED IN |
| | WRITING (NOT SIGNING AND SEALING) BY DESIGNER OF RECORD |
| | AS REQUIRED BY SEC. 107.3.4.1 CITY AMENDMENTS. |
| | |
| | PREVIOUS COMMENT: |
| | C)SINGLE HUNG WINDOWS THAT MEET THE DESIGN PRESSURES |
| | CALCULATED BY THE ENGINEER OF RECORD ON REVISED S.1 |
| | DRAWING. |
| | |
| | NEW RESPONSE ON 05/11/23: |
| | PRODUCT APPROVAL NEEDS TO BE REVIEWED AND APPROVED IN |
| | WRITING (NOT SIGNING AND SEALING) BY DESIGNER OF RECORD |
| | AS REQUIRED BY SEC. 107.3.4.1 CITY AMENDMENTS. |
| | |
| | PREVIOUS COMMENT: |
| | D)ENTRY DOOR THAT MEET THE DESIGN PRESSURES CALCULATED |
| | BY THE ENGINEER OF RECORD ON REVISED S.1 DRAWING. |
| | |
| | NEW RESPONSE ON 05/11/23: |
| | REPEAT COMMENT. NO SUBMITTED AND PRODUCT APPROVAL NEEDS |
| | TO BE REVIEWED AND APPROVED IN WRITING (NOT SIGNING AND |
| | SEALING) BY DESIGNER OF RECORD AS REQUIRED BY SEC. |
| | 107.3.4.1 CITY AMENDMENTS. |
| | |
| | ORIGINAL COMMENT: |
| | 17- ENGINEER OF RECORD TO REVIEW AND APPROVE IN WRITING |
| | (NOT SIGNING AND SEALING) ALL PRODUCT APPROVALS AS |
| | REQUIRED BY SEC. 107.3.4.1 CITY AMENDMENTS. |
| | |
| | |
| | NEW COMMENTS BASED ON REVISED DRAWINGS BY NEW DESIGNER |
| | OF RECORD: |
| | 18- FLOOR PLAN LAYOUT WAS CHANGED BUT NEW ELECTRICAL, |
| | PLUMBING AND MECHANICAL PLANS WERE NOT SUBMITTED. NEED |
| | TO PROVIDE REVISED PLANS FOR ALL TRADES. SEC. 107.2.1 |
| | CITY AMENDMENTS. |
| | |
| | 19- REVISE THE ROOF DESIGN PRESSURES SPECIFIED ON SHEET |
| | S-3 UNDER "MAX. COMPONENTS AND CLADDING DESIGN WIND |
| | PRESSURES". SPECIFICATIONS ARE TOO LOW FOR BUILDING |
| | EXPOSURE "C". |
| | SEC. R301.2.1 FBC-RESIDENTIAL. |
| | |
| | 20- REVISE VENTING SPECIFICATIONS ON THE TYPICAL WALL |
| | SECTION ON SHEET S-2. |
| | 7"X24" VENTS AT 4'-0" O.C. DON'T ALLOW CROSS |
| | VENTILATION. THE ROOF IS FRAMED WITH 2X10'S AT 16" |
| | O.C.. REVISE AS REQUIRED BY SEC. R806.1 FBC-RESIDENTIAL |
| | |
| | WHEN RESUBMITTING, A TRANSMITTAL LETTER LISTING THE |
| | ORIGINAL REVIEW COMMENT WITH A DESCRIPTION OF WHERE AND |
| | HOW THE COMMENT WAS ADDRESSED WILL HELP TO EXPEDITE THE |
| | REVIEW PROCESS. THANK YOU FOR YOUR ANTICIPATED |
| | COOPERATION. |
| | |
| | PLEASE FEEL FREE TO CONTACT ME IF YOU HAVE ANY |
| | QUESTIONS REGARDING THESE COMMENTS, |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | (561)805-6712 |
| | [email protected] |
| | |
| | |
| | |