| Date |
Text |
| 2022-07-27 14:02:52 | FAILED |
| | |
| | 1) THE SUBMITTED COMMUNICATION FACILITY PLACEMENT |
| | PERMIT - CITY RIGHTS-OF-WAY (21120571) MUST BE APPROVED |
| | PRIOR TO THIS PERMIT BEING APPROVED. THIS SUBMITTED |
| | PERMIT CONTAINS THE SAME PLANS AS THE WCF ROW PERMIT. |
| | THE COMMENTS BELOW WERE ALSO PROVIDED ON THE WCF ROW |
| | PERMIT. PLEASE ENSURE THAT FUTURE SUBMITTALS FOR BOTH |
| | PERMITS CONTAIN THE SAME INFORMATION. |
| | |
| | 2) THE BORE PIT AND HANDHOLE NOTES ON SHEET P-1 STATE |
| | THAT THE SIDEWALK WILL BE RESTORED; HOWEVER, THESE ARE |
| | ALSO LOCATED WITHIN THE PARKWAY WHICH WILL NEED |
| | RESTORATION. PLEASE UPDATE THE NOTATIONS ACCORDINGLY. |
| | |
| | 3) PROVIDE A CROSS SECTION OF THE UNDERGROUND ELECTRIC |
| | WHICH VERIFIES THAT THERE ARE NO CONFLICTS WITH |
| | EXISTING UTILITIES AND TREE ROOTS. |
| | |
| | 4) THE PLANS SHOW THE BORE PITS, HANDHOLE AND THE POLE |
| | INSTALL IN DIRECT OVERLAP OF ELECTRIC LINES AND WITHIN |
| | 2 FEET OF A GAS LINE. IN ORDER TO VERIFY THAT THE |
| | INSTALLATION WILL NOT INTERFERE WITH THE EXISTING |
| | FACILITIES, PROVIDE A PUBLIC UTILITY LETTER OF NO |
| | OBJECTION FROM FPL AND FPU REGARDING THE INSTALLATION. |
| | |
| | 5) THE EXCAVATION FOR THE HANDHOLE AT THE POWER POLE IS |
| | SHOWN CROSSING ONTO PRIVATE PROPERTY, WHICH IS NOT |
| | PERMITTED UNLESS THE SURVEY CLEARLY SHOWS A UTILITY |
| | EASEMENT AT THIS LOCATION. |
| | |
| | 6) THE POLE STYLE AND HEIGHT MEET CITY REQUIREMENTS. |
| | THE POLE COLOR AT THIS LOCATION SHALL BE RAL/RAYCAP |
| | 7042 TRAFFIC GREY A. |
| | |
| | CONTACT ERIC SCHNEIDER @ (561) 822-1446 |
| | [email protected] |
| | |