| 2022-10-21 08:08:14 | |
| | 1ST REVIEW FBC-2020 FUEL GAS |
| | PERMIT- 22050891 |
| | 10/20/2022 |
| | |
| | CODES IN EFFECT: |
| | FBC FG- FLORIDA FUEL GAS CODE 7TH EDITION 2020 |
| | FS- FLORIDA STATUTES |
| | FAC- FLORIDA ADMINISTRATIVE CODE |
| | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC |
| | |
| | PLAN REVIEW RESULTS: DENIED. PLEASE NOTE THE GAS PLAN |
| | SUBMITTAL IS INCOMPLETE. PLEASE REVIEW THE COMMENTS AND |
| | DETERMINE IF THE GAS SYSTEMS, AND EQUIPMENT AND |
| | APPLIANCE INSTALLATIONS WILL REMAIN UNDER THE MASTER |
| | PERMIT, OR WILL BE INSTALLED UNDER SEPARATE PERMITS. |
| | THE CONTRACTOR HAS THE OPTION OF INCLUDING A PORTION OF |
| | THE SYSTEM (WATER HEATERS AND BOILER) UNDER THE MASTER |
| | WITH NOTES TO INDICATE THE KITCHEN, FIREPLACE, AND GAS |
| | GRILLS WILL BE INSTALLED UNDER SEPARATE PERMITS. |
| | CONCERNING THE POOL HEATERS PLEASE SEE COMMENT #12 |
| | BELOW. |
| | |
| | 1) SHEET FG001: PLEASE UPDATE THE CODE REFERENCES TO |
| | INDICATE THE 2020 FLORIDA FUEL GAS CODE 7TH EDITION- |
| | SEC. 107.2.1 WPB. |
| | |
| | 2) FG001 DETAIL 1: PROVIDE PIPE UNIONS WITHIN 1 FT. OF |
| | EITHER SIDE OF THE REGULATOR- SEC. 410. 2(7) FBC FG. |
| | |
| | 3) FG200 & FG201: TO HELP EXPEDITE THE REVIEW PLEASE |
| | PROVIDE THE BRANCH PIPE LENGTH MEASUREMENTS ON THE |
| | DRAWINGS AND THE TOTAL DEVELOPED LENGTH OF THE SYSTEM- |
| | SEC. 402.4.1 FBC FG. |
| | |
| | 4) FG104A & FG200: PLEASE SHOW GAS TIGHT CAPS AT THE |
| | SUPPLY PIPES TO THE FUTURE KITCHEN APPLIANCES- SEC. |
| | 404.15 FBC FG. |
| | |
| | 5) FG001 & P503: SUBMIT MANUFACTURER'S SPECIFICATIONS |
| | FOR THE GAS WATER HEATERS (GWH 1-3)- SEC. 624.1 FBC FG. |
| | PLEASE NOTE INSTALLATION OF THE UNITS SHALL BE IN |
| | ACCORDANCE WITH THE MANUFACTURER'S GUIDELINES WHICH |
| | SHALL BE ONSITE FOR INSPECTION. |
| | |
| | 6) FG001 & P503: PROVIDE EQUIPMENT SCHEDULES FOR THE |
| | MECHANICAL BOILERS AND SUBMIT MANUFACTURER'S |
| | SPECIFICATIONS- SEC. 631.1 FBC FG. PLEASE NOTE |
| | INSTALLATION OF THE UNITS SHALL BE IN ACCORDANCE WITH |
| | THE MANUFACTURER'S GUIDELINES WHICH SHALL BE ONSITE FOR |
| | INSPECTION. |
| | |
| | 7) FG105A: PLEASE SUBMIT AN UPPER ROOF PLAN SHOWING THE |
| | TERMINATION LOCATIONS OF THE AIR INTAKE AND EXHAUST |
| | OUTLETS FOR THE DOMESTIC AND MECHANICAL BOILERS- SEC. |
| | 503.6.5 FBC FG. PLEASE NOTE INSTALLATION OF THE UNITS |
| | SHALL BE IN ACCORDANCE WITH THE MANUFACTURER'S |
| | GUIDELINES WHICH SHALL BE ONSITE FOR INSPECTION. |
| | |
| | 8) FG105A: SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE |
| | UL 1738 AIR INTAKE AND EXHAUST DUCTS- SECS. 502.1, |
| | 5032.3, & 503.8 FBC FG. PLEASE NOTE INSTALLATION OF THE |
| | DUCT SHALL BE IN ACCORDANCE WITH THE MANUFACTURER???S |
| | GUIDELINES WHICH SHALL BE ONSITE FOR INSPECTION. |
| | |
| | 9) FG200: SHOW THE TOTAL BTU LOAD OF THE WATER HEATERS |
| | AND BOILERS AT THE 3-INCH PIPE ENTRANCE INTO THE ROOM- |
| | SEC. 402.2 FBC FG. |
| | |
| | 10) FG201: SHOW SUPPLY PIPE SIZES FROM THE SHUTOFF |
| | VALVES TO THE GAS WATER HEATERS- SEC. 402.3 FBC FG. |
| | |
| | 11) FG201: IT APPEARS NO REGULATORS ARE TO BE INSTALLED |
| | AT THE BOILERS TO REDUCE THE 2 PSI INPUT PRESSURE. |
| | PLEASE INDICATE THE INPUT PRESSURE RATINGS OF THE |
| | UNITS- SEC. 410.1 & 631.1 FBC FG. A) SHOW SUPPLY PIPE |
| | SIZES FROM THE SHUTOFF VALVES TO THE UNITS- SEC. 402.3 |
| | FBC FG. |
| | |
| | 12) FG001 & P503: SUBMIT MANUFACTURER'S SPECIFICATIONS |
| | FOR THE POOL HEATERS- SEC. 617.1 FBC FG. PLEASE NOTE |
| | THAT INSTALLATION OF THE POOL HEATERS INCLUDING FINAL |
| | CONNECTIONS OF GAS AND PLUMBING PIPING SHALL BE UNDER |
| | SEPARATE PERMIT- SEC. 105.1 & 107.2.1 WPB. THE |
| | INSTALLATION OF THE UNITS SHALL BE IN ACCORDANCE WITH |
| | THE MANUFACTURER'S GUIDELINES WHICH SHALL BE ONSITE FOR |
| | INSPECTION. CONCERNING THE AIR INTAKE AND EXHAUST DUCTS |
| | PLEASE SEE COMMENT #8 ABOVE. |
| | |
| | 13) FG201: SHOW SUPPLY PIPE SIZES FROM THE SHUTOFF |
| | VALVES TO THE POOL HEATERS- SEC. 402.3 FBC FG. |
| | |
| | 14) FG200: SHOW THE APPROXIMATE GAS LOAD AT THE FUTURE |
| | KITCHEN- SEC. 402.3 FBC FG. AS NOTED, GAS TIGHT CAPS AT |
| | THE SUPPLY PIPES ARE REQUIRED FOR FUTURE. |
| | |
| | 15) FG001, FG104A, FG200: SUBMIT MANUFACTURER'S |
| | SPECIFICATIONS FOR THE FIREPLACE AND FIREPLACE VENT |
| | SYSTEM AND PROVIDE AN EQUIPMENT SCHEDULE ON THE PLAN- |
| | SECS. 604.1 & 605.1 FBC FG. |
| | |
| | A) REVISE THE RISER DRAWING TO INCLUDE THE CSST PIPING |
| | CALLED OUT IN NOTE FG04 (SHEET FG104A). |
| | |
| | B) PROVIDE COMBUSTION AIR CALCULATIONS AND INDICATE HOW |
| | THE AIR IS TO BE PROVIDED- SEC. 304.1 FBC FG. |
| | |
| | C) PROVIDE A VENTING DIAGRAM INDICATING THE TYPE AND |
| | SIZE OF VENT FLUE, TOTAL VENT FLUE RUN AND TERMINATION |
| | LOCATION. SUBMIT SPECS FOR ALL COMPONENTS OF THE |
| | SYSTEM- SECS. 502.1 & 503.1 FBC FG. |
| | |
| | 15) FG001, FG104A, FG200: SUBMIT MANUFACTURER'S |
| | SPECIFICATIONS FOR THE GAS GRILLS AND PROVIDE AN |
| | EQUIPMENT SCHEDULE ON THE PLAN- SECS. 623.1 FBC FG. |
| | |
| | A) PROVIDE INSTALLATION DETAILS ON THE PLAN SHOWING HOW |
| | THE UNITS WILL BE ANCHORED TO THE OUTDOOR COUNTER |
| | ASSEMBLIES AND HOW COMBUSTION AIR WILL BE PROVIDED- |
| | SEC. 107.2.1 WPB & SEC. 304.1 FBC FG. |
| | |
| | 16) REFER TO SEC. C408.2 FBC ENERGY- PRIOR TO FINAL |
| | PLUMBING AND GAS APPROVAL, THE LICENSED DESIGN |
| | PROFESSIONAL, MECHANICAL ENGINEER, OR APPROVED AGENCY |
| | SHALL PROVIDE EVIDENCE OF MECHANICAL AND SERVICE WATER |
| | HEATING COMMISSIONING WITH THE APPLICABLE PROVISIONS OF |
| | SEC. C408. PLEASE SUBMIT A COMMISSIONING PLAN- SEC. |
| | C408.2.1. |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL/PLUMBING PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |
| | [email protected] |
| | |
| | |
| | |