| 2022-08-12 16:07:14 | SFR ADDITION - REMODEL |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected] |
| | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 |
| | AMENDMENT |
| | |
| | CORRECTIONS NEEDED - |
| | |
| | 1) THERE ARE MULTIPLE ROOFING SYSTEMS IN THE ROOFING |
| | PRODUCT APPROVAL - - PRODUCT APPROVAL (18-0919.07) FOR |
| | THE FLAT DECK ROOFING = NEED TO CHOOSE A ROOFING SYSTEM |
| | IN THE PRODUCT APPROVAL THAT SHOWS THE REQUIRED WIND |
| | DESIGN PRESSURE (ROOFING WIND DESIGN PRESSURES ARE NOT |
| | SHOWN ON THE DRAWINGS ) PER FBC R TABLE R301.2(2) - |
| | PLEASE CIRCLE THE ROOFING SYSTEM TO BE USED IN THE |
| | PRODUCT APPROVAL - IF NEEDED PLEASE PROVIDE ADDITIONAL |
| | ATTACHMENT DETAILS FROM AN ARCHITECT OR ENGINEER FOR |
| | THE ROOF ZONES 2 AND 3 WHICH MAY REQUIRE A HIGHER WIND |
| | PRESSURE THEN THE CHOSEN ROOFING SYSTEM - SEE NOTES ON |
| | THE PRODUCT APPROVAL. |
| | |
| | |
| | FYI - - ROOFING SYSTEM PRODUCT APPROVALS MAY BE |
| | DEFERRED SUBMITTALS BY LISTING ITEMS TO BE DEFERRED ON |
| | THE CONSTRUCTION DOCUMENTS - 107.3.4.1 DEFERRED |
| | SUBMITTALS. FOR THE PURPOSES OF THIS SECTION, DEFERRED |
| | SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF THE DESIGN |
| | THAT ARE NOT SUBMITTED AT THE TIME OF THE APPLICATION |
| | AND THAT ARE TO BE SUBMITTED TO THE BUILDING OFFICIAL |
| | WITHIN A SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL |
| | ITEMS SHALL HAVE THE PRIOR APPROVAL OF THE BUILDING |
| | OFFICIAL. THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE SHALL LIST THE DEFERRED SUBMITTALS |
| | ON THE CONSTRUCTION DOCUMENTS FOR REVIEW BY THE |
| | BUILDING OFFICIAL. DOCUMENTS FOR DEFERRED SUBMITTAL |
| | ITEMS SHALL BE SUBMITTED TO THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL REVIEW |
| | THEM AND FORWARD THEM TO THE BUILDING OFFICIAL WITH A |
| | NOTATION INDICATING THAT THE DEFERRED SUBMITTAL |
| | DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE IN GENERAL |
| | CONFORMANCE TO THE DESIGN OF THE BUILDING. THE DEFERRED |
| | SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL THE |
| | DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE |
| | BUILDING OFFICIAL. |
| | |
| | |