| Date |
Text |
| 2023-03-21 10:57:28 | [3.21.23 REPEAT COMMENTS] |
| | |
| | INSUFFICIENT |
| | |
| | 1. PROVIDE A SURVEY, PREPARED BY A FLORIDA LICENSED |
| | SURVEYOR, THAT SHOWS THE RIGHT-OF-WAY LINE, THE |
| | SIDEWALK, AND ANY TREES WITHIN THE RIGHT-OF-WAY ALONG |
| | THE FIBER CONDUIT PATH SO THAT STAFF CAN VERIFY THAT |
| | THE BORE AND ANY REQUIRED BORE PITS AND HANDHOLES ARE |
| | WITHIN THE PUBLIC RIGHT-OF-WAY. THE SURVEY NEEDS TO |
| | INCLUDE THE LOCATION OF CONDUIT, PROPOSED HANDHOLES, |
| | AND THE BORE SECTIONS. IN ORDER TO INSTALL HANDHOLES |
| | AND BORE UNDER PRIVATE PROPERTY THE SCOPE OF WORK MUST |
| | BE WITHIN A GENERAL UTILITY EASEMENT. THIS GENERAL |
| | UTILITY EASEMENT MUST BE CLEARLY SHOWN ON THE SURVEY. |
| | |
| | [NEW COMMENT 3.21.23] CONDUIT APPEARS TO CROSS OVER |
| | PRIVATE PROPERTY AT CORNER INTERSECTION OF CLEARWATER |
| | AND AUSTRALIAN. PLEASE SHOW EASEMENT GRANTING THIS |
| | CROSSING. |
| | |
| | 2. THE TUBULAR MARKERS ARE NOT PERMITTED. MARKERS MAY |
| | ONLY BE INSTALLED WITHIN THE HANDHOLES OR OTHERWISE |
| | BURIED. |
| | |
| | 3. PROVIDE A COPY OF THE FDOT PERMIT APPROVING THE WORK |
| | WITHIN THEIR RIGHT-OF-WAY. |
| | |
| | 4. ANY BOREPITS, HANDHOLES, OR EXCAVATION WORK SHALL |
| | PROVIDE AN 8FT. BUFFER FROM THE TRUNK OF THE TREE TO |
| | REDUCE THE RISK TO ROOT SYSTEMS. PLEASE PROVIDE |
| | DIMENSIONS FROM ANY TREES ADJACENT TO EXCAVATIONS. |
| | |
| | |
| | CHRIS KIMMERLY, AICP |
| | URBAN DESIGN PLANNER |
| | 822.1426 [email protected] |
| | |