Plan Review Notes For Permit 22030579
Permit Number 22030579
Review Stop NFIP
Sequence Number 2
Notes
Date Text
2022-10-05 12:26:10NFIP REVIEW
  
 2ND REQUEST
  
 SUBSTANTIAL IMPROVEMENT PER FEMA P-758, 50% RULE.
 NOTICE: PROPERTY IS LOCATED IN A SPECIAL FLOOD HAZARD
 AREA (SFHA). THE VALUE OF WORK ($350,000.00) EXCEEDS
 50% OF THE IMPROVEMENT VALUE ($295,328.00) AS STATED ON
 THE PROPERTY APPRAISERS WEB-SITE. WORK IS CONSIDERED A
 SUBSTANTIAL IMPROVEMENT (S/I) PER FEMA P-758.
  
  
 NOTICE:
  
 PROPERTY IS LOCATED IN A SPECIAL FLOOD HAZARD AREA
 (SFHA). IT IS LOCATED IN FLOOD ZONE AE WITH A BASE
 FLOOD ELEVATION OF 6.0 FEET NAVD. BASED ON THE VALUE OF
 THIS SUBMITTAL, THE WORK ON THE PROPERTY IS CONSIDERED
 A SUBSTANTIAL IMPROVEMENT (S/I) PER FEMA P-758.
  
 2020 FBC EXISTING BUILDING
 1201.3FLOOD HAZARD AREAS.
 IN FLOOD HAZARD AREAS, IF ALL PROPOSED WORK, INCLUDING
 REPAIRS, WORK REQUIRED BECAUSE OF A CHANGE OF
 OCCUPANCY, AND ALTERATIONS, CONSTITUTES SUBSTANTIAL
 IMPROVEMENT, THEN THE BUILDING SHALL COMPLY WITH
 SECTION 1612 OF THE FLORIDA BUILDING CODE, BUILDING, OR
 SECTION R322 OF THE FLORIDA BUILDING CODE, RESIDENTIAL,
 AS APPLICABLE.
  
 CITY ORDINANCE NO. 4658-16
  
 CITY OF WEST PALM BEACH ORDINANCE NO. 4658-16
 AS OF OCTOBER 5, 2017, THE FEDERAL EMERGENCY MANAGEMENT
 AGENCY (FEMA) ESTABLISHED A NEW FLOOD INSURANCE RATE
 MAP (FIRM) UTILIZING THE RECENTLY COMPLETED FLOOD
 HAZARD DETERMINATION (FHD) FOR THE CITY OF WEST PALM
 BEACH, FL.
  
 ALL NEW BASE FLOOD ELEVATIONS (BFE) SHALL BE BASED ON
 NAVD88 DATUM. ON AUGUST 23, 2017, THE CITY OF WEST PALM
 BEACH, BY ORDINANCE, NO. 4658-16, ESTABLISHED A
 TWO-FOOT FREEBOARD ABOVE THE (BFE).
 FINISHED FLOOR ELEVATIONS SHALL BE PLACED ON FOUNDATION
 PLAN AND/OR FLOOR PLAN.
  
 1. PROVIDE AN ELEVATION CERTIFICATE WITH AN ACCURATELY
 COMPLETED BOUNDY LINE SURVEY. (2ND REQUEST)
  
 NOTICE: 3 EC S ARE REQUIRED
  
 1. A CONSTRUCTION DRAWING ELEVATION CERTIFICATE IS
 REQUIRED AT TIME OF PERMIT APPLICATION.
  
 2.A BUILDING UNDER CONSTRUCTION ELEVATION CERTIFICATE
 IS REQUIRED AT PLACEMENT OF 1ST FLOOR.
  
 3.A FINISHED CONSTRUCTION ELEVATION CERTIFICATE IS
 REQUIRED AND SHALL BE SUBMITTED FOR REVIEW AND APPROVAL
 PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF OCCUPANCY.
 NOTE: YOU MAY SUBMIT THIS EC FOR REVIEW AFTER FINAL
 GRADE AND PLACEMENT OF EQUIPMENT SERVICING THE
 BUILDING.
  
  
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS.
  
  
  
  
  