| Date |
Text |
| 2022-07-11 14:16:04 | NEW SFR |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected] |
| | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 |
| | AMENDMENT |
| | |
| | CORRECTIONS NEEDED - |
| | |
| | 1) PLEASE PROVIDE COMPLETE (FRONT PAGES AND THE |
| | INSTALLATION INSTRUCTIONS) MIAMI DADE OR FLORIDA STATE |
| | PRODUCT APPROVALS FOR THE EXTERIOR WINDOWS, DOORS, MULL |
| | BARS AND ROOFING SYSTEMS. ALL PRODUCT APPROVALS NEED TO |
| | BE REVIEWED AND MARKED APPROVED BY THE BUILDING |
| | DESIGNER OF RECORD OR LISTED ON THE DRAWINGS BY THE |
| | PERMIT NUMBER FBC WPB 107.3.4 |
| | |
| | 2) EMERGENCY ESCAPE WINDOW "A" IS TOO SMALL TO MEET THE |
| | EMERGENCY EGRESS DIMENSIONS ( THE NET CLEAR HEIGHT |
| | OPENING SHALL BE NOT LESS THAN 24 INCHES) - FBC |
| | R310.2.1 |
| | |
| | 3) FBC R320.1.1 ALL NEW SINGLE-FAMILY HOUSES, DUPLEXES, |
| | TRIPLEXES, CONDOMINIUMS AND TOWNHOUSES SHALL PROVIDE AT |
| | LEAST ONE BATHROOM, LOCATED WITH MAXIMUM POSSIBLE |
| | PRIVACY, WHERE BATHROOMS ARE PROVIDED ON HABITABLE |
| | GRADE LEVELS, WITH A DOOR THAT HAS A 29-INCH (737 MM) |
| | CLEAR OPENING. |
| | |
| | 4) PLEASE SHOW ROOF SCUPPER TO BE LEVEL WITH THE ROOF |
| | DECK FBC R903.4 ROOF DRAINAGE. |
| | UNLESS ROOFS ARE SLOPED TO DRAIN OVER ROOF EDGES, ROOF |
| | DRAINS SHALL BE INSTALLED AT EACH LOW POINT OF THE |
| | ROOF. WHERE REQUIRED FOR ROOF DRAINAGE, SCUPPERS SHALL |
| | BE PLACED LEVEL WITH THE ROOF SURFACE IN A WALL OR |
| | PARAPET. |
| | |
| | 5) SCUPPERS SHOWN MEET THE REQUIREMENTS FOR THE |
| | REQUIRED - OVER FLOW SCUPPERS FBC R903.4.1 OVERFLOW |
| | DRAINS AND SCUPPERS. |
| | WHEN OTHER MEANS OF DRAINAGE OF OVERFLOW WATER IS NOT |
| | PROVIDED, OVERFLOW SCUPPERS SHALL BE PLACED IN WALLS OR |
| | PARAPETS NOT LESS THAN 2 INCHES (51 MM) NOR MORE THAN 4 |
| | INCHES |
| | |
| | 6) SITE PLAN NEEDS TO SHOW THE SITE STORM WATER |
| | DRAINAGE - FBC WPB 107.2.5 SITE PLAN. THE CONSTRUCTION |
| | DOCUMENTS SUBMITTED WITH THE APPLICATION FOR PERMIT |
| | SHALL BE ACCOMPANIED BY A SITE PLAN SHOWING TO SCALE |
| | THE SIZE AND LOCATION OF NEW CONSTRUCTION AND EXISTING |
| | STRUCTURES ON THE SITE, DISTANCES FROM LOT LINES, THE |
| | ESTABLISHED STREET GRADES AND THE PROPOSED FINISHED |
| | GRADES, DEPICTING THE PROPOSED LOT DRAINAGE AND, AS |
| | APPLICABLE, FLOOD HAZARD AREAS, FLOODWAYS, AND DESIGN |
| | FLOOD ELEVATIONS; AND IT SHALL BE DRAWN IN ACCORDANCE |
| | WITH AN ACCURATE AND INCLUDED ON A BOUNDARY LINE |
| | SURVEY. (PLEASE PROVIDE CUT SECTIONS FOR ANY PROPOSED |
| | WATER RETAINING SWALES) |
| | |
| | 7) PLEASE SHOW THE REQUIRED SMOKE ALARM LOCATIONS FBC |
| | R314.3 |
| | |
| | 8) PLEASE PROVIDE A SURVEY |
| | |
| | 9) WINDOW, DOOR AND ROOFING SYSTEM PRODUCT APPROVALS |
| | MAY BE DEFERRED SUBMITTALS BY LISTING ITEMS TO BE |
| | DEFERRED ON THE CONSTRUCTION DOCUMENTS - 107.3.4.1 |
| | DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS SECTION, |
| | DEFERRED SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF |
| | THE DESIGN THAT ARE NOT SUBMITTED AT THE TIME OF THE |
| | APPLICATION AND THAT ARE TO BE SUBMITTED TO THE |
| | BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL |
| | OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF |
| | THE BUILDING OFFICIAL. THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE |
| | DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR |
| | REVIEW BY THE BUILDING OFFICIAL. DOCUMENTS FOR DEFERRED |
| | SUBMITTAL ITEMS SHALL BE SUBMITTED TO THE REGISTERED |
| | DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL |
| | REVIEW THEM AND FORWARD THEM TO THE BUILDING OFFICIAL |
| | WITH A NOTATION INDICATING THAT THE DEFERRED SUBMITTAL |
| | DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE IN GENERAL |
| | CONFORMANCE TO THE DESIGN OF THE BUILDING. THE DEFERRED |
| | SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL THE |
| | DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE |
| | BUILDING OFFICIAL. |