| Date |
Text |
| 2022-03-25 13:15:24 | BUILDING PLAN REVIEW |
| | |
| | CHRISTOPHER S. THROOP, C.B.O., CFM |
| | PLANS EXAMINER II PX3169/SFP306 |
| | INSPECTOR BN4338 |
| | BUILDING OFFICIAL BU1635 |
| | ASFPM CERTIFIED FLOODPLAIN MANAGER US-21-11935 |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | CITY OF WEST PALM BEACH |
| | (561) 805-6726 |
| | [email protected] |
| | |
| | CODES IN EFFECT: |
| | 2020 FLORIDA BUILDING CODE, 7TH EDITION W/2017 WEST |
| | PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING CODE, |
| | CHAPTER 1 ADMINISTRATION |
| | NFPA 70 2017 EDITION NEC 2017 |
| | |
| | 2ND REVIEW |
| | |
| | RESULTS: DENIED |
| | ADDRESS THE ATTACHED COMMENTS AND RE-SUBMIT |
| | |
| | COMMENTS FROM 1ST REVIEW HAVE NOT BEEN ADDRESSED. SEE |
| | BELOW. |
| | |
| | FOR NEW SITE BUILT CABINETS |
| | |
| | 1. PROVIDE A SITE PLAN W/BOUNDRY LINE SURVEY. IDENTIFY |
| | LOCATION OF WORK. |
| | 107.2.5 SITE PLAN. THE CONSTRUCTION DOCUMENTS SUBMITTED |
| | WITH THE APPLICATION FOR PERMIT SHALL BE ACCOMPANIED BY |
| | A SITE PLAN SHOWING TO SCALE THE SIZE AND LOCATION OF |
| | NEW CONSTRUCTION AND EXISTING STRUCTURES ON THE |
| | SITE,... AND IT SHALL BE DRAWN IN ACCORDANCE WITH AN |
| | ACCURATE AND INCLUDED BOUNDARY LINE SURVEY. |
| | PROVIDE DEMENSIONS TO PROPERTY LINES. |
| | |
| | 2. PROVIDE WIND DESIGN LOADS PER R301. |
| | FBC 107.3.5.3 PROVIDE WIND DESIGN LOADS/DESIGN |
| | PRESSURES PURSUANT TO FBC-R301.2. |
| | R301.2.1 WIND DESIGN CRITERIA. |
| | BUILDINGS AND PORTIONS THEREOF SHALL BE CONSTRUCTED IN |
| | ACCORDANCE WITH THE WIND PROVISIONS OF THIS CODE USING |
| | THE BASIC WIND SPEED IN TABLE R301.2(1) AS DETERMINED |
| | FROM FIGURE R301.2(4). |
| | |
| | 3. PROVIDE FRAMING PLAN FOR CABINET. |
| | 107.2 CONSTRUCTION DOCUMENTS. CONSTRUCTION DOCUMENTS |
| | SHALL BE IN ACCORDANCE WITH SECTIONS107.2.1 THROUGH |
| | 107.2.5. |
| | |
| | 4. PROVIDE FOUNDATION DETAIL. |
| | 107.2 CONSTRUCTION DOCUMENTS. CONSTRUCTION DOCUMENTS |
| | SHALL BE IN ACCORDANCE WITH SECTIONS107.2.1 THROUGH |
| | 107.2.5. |
| | |
| | 5. PROVIDE STRUCTURAL WALL DETAIL. |
| | CMU - PROVIDE VERTICAL REINFORCING FROM FOUNDATION TO |
| | BOND BEAM. |
| | METAL FRAMING - PROVIDE STUD GUAGE AND FASTENER |
| | SCHEDULE. |
| | 107.2 CONSTRUCTION DOCUMENTS. CONSTRUCTION DOCUMENTS |
| | SHALL BE IN ACCORDANCE WITH SECTIONS107.2.1 THROUGH |
| | 107.2.5. |
| | |
| | 6. PROVIDE FIRE BOX COMBUSTION AIR OPENINGS PER |
| | MANUFACTURERS INSTALLATION INSTRUCTIONS. |
| | 107.2 CONSTRUCTION DOCUMENTS. CONSTRUCTION DOCUMENTS |
| | SHALL BE IN ACCORDANCE WITH SECTIONS107.2.1 THROUGH |
| | 107.2.5. |
| | |
| | 7. PROVIDE MANUFACTURERS INSTALLATION INSTRUCTIONS. |
| | 107.2 CONSTRUCTION DOCUMENTS. CONSTRUCTION DOCUMENTS |
| | SHALL BE IN ACCORDANCE WITH SECTIONS107.2.1 THROUGH |
| | 107.2.5. |
| | |
| | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. |
| | |
| | WHEN RESUBMITING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. |
| | |