| Date |
Text |
| 2022-08-04 10:04:03 | BATTERY STORAGE BUILDING |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected] |
| | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 |
| | AMENDMENT |
| | |
| | CORRECTIONS NEEDED - |
| | |
| | 1) PRODUCT APPROVAL (FL16039-R17) FOR THE ROOFING |
| | SYSTEM - THE PRODUCT APPROVAL DOES NOT INCLUDE FRP |
| | PANELS AS AN APPROVED SUBSTRATE. |
| | |
| | 2) PLEASE CIRCLE ROOFING SYSTEMS TO BE USED IN THE |
| | ROOFING PRODUCT APPROVALS. |
| | |
| | 3) ROOFING SYSTEMS AND PRODUCT APPROVALS FOR SUCH MAY |
| | BE DEFERRED SUBMITTALS BY LISTING ITEMS TO BE DEFERRED |
| | ON THE CONSTRUCTION DOCUMENTS - 107.3.4.1 DEFERRED |
| | SUBMITTALS. FOR THE PURPOSES OF THIS SECTION, DEFERRED |
| | SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF THE DESIGN |
| | THAT ARE NOT SUBMITTED AT THE TIME OF THE APPLICATION |
| | AND THAT ARE TO BE SUBMITTED TO THE BUILDING OFFICIAL |
| | WITHIN A SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL |
| | ITEMS SHALL HAVE THE PRIOR APPROVAL OF THE BUILDING |
| | OFFICIAL. THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE SHALL LIST THE DEFERRED SUBMITTALS |
| | ON THE CONSTRUCTION DOCUMENTS FOR REVIEW BY THE |
| | BUILDING OFFICIAL. DOCUMENTS FOR DEFERRED SUBMITTAL |
| | ITEMS SHALL BE SUBMITTED TO THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL REVIEW |
| | THEM AND FORWARD THEM TO THE BUILDING OFFICIAL WITH A |
| | NOTATION INDICATING THAT THE DEFERRED SUBMITTAL |
| | DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE IN GENERAL |
| | CONFORMANCE TO THE DESIGN OF THE BUILDING. THE DEFERRED |
| | SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL THE |
| | DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE |
| | BUILDING OFFICIAL. |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |