| Date |
Text |
| 2022-02-16 09:54:40 | BATTERY STORAGE BUILDING |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected] |
| | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 |
| | AMENDMENT |
| | |
| | CORRECTIONS NEEDED - |
| | |
| | 1) WIND DESIGN SHOWN - RISK CATEGORY II WIND SPEED |
| | 167MPH - A RISK CATEGORY II REQUIRES A MINIMUM WIND |
| | SPEED OF 170MPH - PER FBC WPB SECTION 120. |
| | |
| | 2) ALL PRODUCT APPROVALS NEED TO BE REVIEWED AND MARKED |
| | APPROVED BY THE BUILDING DESIGNER OF RECORD - FBC WPB |
| | 107.3.4 |
| | |
| | 3) PLEASE PROVIDE THE COMPLETE (FRONT PAGES AND THE |
| | INSTALLATION INSTRUCTIONS) MIAMI DADE OR FLORIDA STATE |
| | PRODUCT APPROVALS FOR THE ROOFING SYSTEM. |
| | |
| | 4) PRODUCT APPROVALS PROVIDED FOR THE EXTERIOR SWING |
| | DOORS AND OVERHEAD ROLLING DOOR SHOWS ATTACHMENT TO |
| | WOOD, METAL AND CONCRETE SUBSTRATE - THE ATTACHMENT TO |
| | FRP FRAMING WILL REQUIRE A SITE SPECIFIC ATTACHMENT |
| | DETAIL FROM A DESIGN PROFESSIONAL. |
| | |
| | 5) PLEASE PROVIDE DETAILS FOR THE FOUNDATION SLAB FROM |
| | A DESIGN PROFESSIONAL - SHOW THE WIND DESIGN DATA USED |
| | ON THE SLAB DRAWINGS FBC 1603.1.4 |
| | |
| | 6) PLEASE SHOW THE DIMENSIONS FROM THE PROPERTY LINE |
| | AND OTHER BUILDINGS TO THE SHED - PLEASE PROVIDE A SITE |
| | PLAN SHOWING THE FOLLOWING INFORMATION 107.2.5 SITE |
| | PLAN. THE CONSTRUCTION DOCUMENTS SUBMITTED WITH THE |
| | APPLICATION FOR PERMIT SHALL BE ACCOMPANIED BY A SITE |
| | PLAN SHOWING TO SCALE THE SIZE AND LOCATION OF NEW |
| | CONSTRUCTION AND EXISTING STRUCTURES ON THE SITE, |
| | DISTANCES FROM LOT LINES, THE ESTABLISHED STREET GRADES |
| | AND THE PROPOSED FINISHED GRADES, DEPICTING THE |
| | PROPOSED LOT DRAINAGE AND, AS APPLICABLE, FLOOD HAZARD |
| | AREAS, FLOODWAYS, AND DESIGN FLOOD ELEVATIONS; AND IT |
| | SHALL BE DRAWN IN ACCORDANCE WITH AN ACCURATE AND |
| | INCLUDED ON A BOUNDARY LINE SURVEY. |
| | |
| | 7) PLEASE SHOW THE BUILDING OCCUPANCY CLASSIFICATION |
| | PER FBC CHAPTER 3 - (H) OCCUPANCY CLASSIFICATION |
| | REQUIRES ADDITIONAL INFORMATION FBC 414.1.3 INFORMATION |
| | REQUIRED. |
| | A REPORT SHALL BE SUBMITTED TO THE BUILDING OFFICIAL |
| | IDENTIFYING THE MAXIMUM EXPECTED QUANTITIES OF |
| | HAZARDOUS MATERIALS TO BE STORED, USED IN A CLOSED |
| | SYSTEM AND USED IN AN OPEN SYSTEM, AND SUBDIVIDED TO |
| | SEPARATELY ADDRESS HAZARDOUS MATERIAL CLASSIFICATION |
| | CATEGORIES BASED ON TABLES 307.1(1) AND 307.1(2). THE |
| | METHODS OF PROTECTION FROM SUCH HAZARDS, INCLUDING BUT |
| | NOT LIMITED TO CONTROL AREAS, FIRE PROTECTION SYSTEMS |
| | AND GROUP H OCCUPANCIES SHALL BE INDICATED IN THE |
| | REPORT AND ON THE CONSTRUCTION DOCUMENTS. THE OPINION |
| | AND REPORT SHALL BE PREPARED BY A QUALIFIED PERSON, |
| | FIRM OR CORPORATION APPROVED BY THE BUILDING OFFICIAL |
| | AND PROVIDED WITHOUT CHARGE TO THE ENFORCING AGENCY. |
| | |
| | FOR BUILDINGS AND STRUCTURES WITH AN OCCUPANCY IN GROUP |
| | H, SEPARATE FLOOR PLANS SHALL BE SUBMITTED IDENTIFYING |
| | THE LOCATIONS OF ANTICIPATED CONTENTS AND PROCESSES SO |
| | AS TO REFLECT THE NATURE OF EACH OCCUPIED PORTION OF |
| | EVERY BUILDING AND STRUCTURE. |
| | |
| | |
| | |