| 2021-11-29 08:36:56 | 11/29/21 1ST PLUMBING REVIEW**DENIED** WITH COMMENTS |
| | |
| | NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| | TIME, AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| | GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| | |
| | 1. A DRAWING WAS SUBMITTED FOR PLUMBING WORK BUT THE |
| | CITY OF WEST PALM BEACH HAS NO RECORD OF A DEMO OR |
| | BUILDING WORK FOR THAT STRUCTURE. WOULD YOU PLEASE |
| | PROVIDE A LAYOUT OF WHAT IS BEING DEMO OR ADDED, THE |
| | SOURCE OF HOT WATER? SEPARATE PERMIT REQUIRED PER THE |
| | WPB AMENDMENTS TO THE FBC SEC. 105.1. PLEASE REFER TO |
| | BUILDING COMMENTS. |
| | |
| | 2. WHERE ARE THE TWO UNITS ON THE SECOND FLOOR |
| | CONNECTING TO THE BUILDING DRAIN AND WHAT SIZE IS THE |
| | FIXTURE LOAD PER THE 2020 FBC TABLE 710.1(1) BUILDING |
| | DRAINS AND SEWER. |
| | |
| | 3. WOULD YOU PLEASE SHOW THE LOCATION OF WATER HEATERS |
| | PER THE WPB AMEND TO FBC 107.2.1. |
| | |
| | 4. IF WATER PIPING IS BEING REPLACED, PLEASE PROVIDE A |
| | WATER ISOMETRIC PER THE WPB AMEND TO FBC |
| | 107.3.5.1.3(13) |
| | |
| | 5. A BACKFLOW DEVICE WILL BE REQUIRED ON THE WATER |
| | SERVICE AT THE METER A SEPARATE PERMIT WILL BE |
| | REQUIRED. PER WPB UTILITIES DEPARTMENT CROSS CONNECTION |
| | MANUAL. |
| | |
| | WHEN RESUBMITTING PLANS, PLEASE INDICATE THE REVISION & |
| | REMOVE ANY VOIDED SHEETS & REPLACE ANY NECESSARY PAGES. |
| | A TRANSMITTAL LETTER LISTING THE ORIGINAL REVIEW |
| | COMMENT NUMBER, WITH A DESCRIPTION OF THE REVISION |
| | MADE, IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE |
| | THE CHANGES CAN BE FOUND, WILL HELP EXPEDITE YOUR |
| | PERMIT. THANK YOU FOR YOUR ANTICIPATED COOPERATION. |
| | |
| | HTTPS://CODES.ICCSAFE.ORG/CODES/FLORIDA |
| | |
| | LUIS A. CRESPO |
| | PLUMBING PLAN EXAMINER / INSPECTOR |
| | EMAIL: [email protected] OFFICE: 561 805-6720 |
| | |