| 2022-02-15 10:27:48 | OFFICE BUILD OUT |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected] |
| | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 |
| | AMENDMENT |
| | |
| | CORRECTIONS NEEDED - |
| | |
| | 1) PLEASE SHOW THE DOOR (18078) LOCATED IN THE FIRE |
| | RATED WALLS TO BE FIRE RATED PER FBC 716 |
| | |
| | 2) DRAWING (A2-31) DETAIL H SHOWS (18") FOR THE CENTER |
| | OF THE TOILET PAPER HOLDER TO THE FACE OF THE TOILET - |
| | PLEASE CORRECT - ACCESSIBLE RESTROOMS - DRAWING A0-00D |
| | - PLEASE SHOW THE DIMENSION OF THE TOILET PAPER HOLDER |
| | FROM THE FACE OF THE TOILET TO THE CENTER OF THE TOILET |
| | PAPER HOLDER - FBC A 604.7 DISPENSERS. |
| | TOILET PAPER DISPENSERS SHALL COMPLY WITH 309.4 AND |
| | SHALL BE 7 INCHES (180 MM) MINIMUM AND 9 INCHES (230 |
| | MM) MAXIMUM IN FRONT OF THE WATER CLOSET MEASURED TO |
| | THE CENTERLINE OF THE DISPENSER. |
| | |
| | 3) PLEASE USE THE WORDS "REFLECTING OR REFLECTIVE" |
| | SURFACE - ACCESSIBLE RESTROOM - DRAWING A0-00D - FOR |
| | THE MIRROR PLEASE SHOW THE DIMENSION FROM THE FINISHED |
| | FLOOR TO THE REFLECTIVE SURFACE FBC A 603.3 MIRRORS. |
| | MIRRORS LOCATED ABOVE LAVATORIES OR COUNTERTOPS SHALL |
| | BE INSTALLED WITH THE BOTTOM EDGE OF THE REFLECTING |
| | SURFACE 40 INCHES (1015 MM) MAXIMUM ABOVE THE FINISH |
| | FLOOR OR GROUND. |
| | |
| | 4) PLEASE PROVIDE THE ROOF TOP MECHANICAL SCREENING |
| | DETAILS FROM A DESIGN PROFESSIONAL TO MEET THE WIND |
| | LOADS FBC 1609 |
| | ROOF TOP SCREENING DETAILS MAY BE DEFERRED SUBMITTALS |
| | BY LISTING ITEMS TO BE DEFERRED ON THE CONSTRUCTION |
| | DOCUMENTS - 107.3.4.1 DEFERRED SUBMITTALS. FOR THE |
| | PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS ARE |
| | DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT |
| | SUBMITTED AT THE TIME OF THE APPLICATION AND THAT ARE |
| | TO BE SUBMITTED TO THE BUILDING OFFICIAL WITHIN A |
| | SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL ITEMS SHALL |
| | HAVE THE PRIOR APPROVAL OF THE BUILDING OFFICIAL. THE |
| | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE |
| | SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION |
| | DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| | THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| | OFFICIAL. |