| Date |
Text |
| 2021-09-23 14:51:33 | 09/23/21 1ST POOL REVIEW**DENIED** WITH COMMENTS |
| | |
| | NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| | TIME, AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| | GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| | |
| | 1. WOULD YOU PLEASE SUBMIT TOTAL DYNAMIC HEAD |
| | CALCULATIONS FOR THE MAXIMUM SYSTEM FLOW COMPONENTS? IT |
| | REQUIRES THAT THE MAXIMUM SYSTEM FLOW RATE DOES NOT |
| | EXCEED THE LISTED MAXIMUM FLOW RATE OF THE SUCTION |
| | OUTLET FITTING ASSEMBLY (DRAIN COVER). THE TDH |
| | CALCULATIONS MUST INCLUDE ALL THE SYSTEM COMPONENTS |
| | INCLUDING SUCTION AND RETURN PIPING, FITTINGS, VALVES, |
| | HEATER, FILTER, AND CHLORINATOR. ALL SYSTEM COMPONENTS |
| | EXCEPT THE PUMP PER THE ANSI/APSP/ICC 7 - 2015 SECS. |
| | 4.4.9, 4.4.9.1 MAXIMUM SYSTEM FLOW RATE?UNSECURED |
| | CONTROL SYSTEMS. |
| | |
| | 2. WOULD YOU PLEASE SUBMIT A COPY OF THE POOL PUMP |
| | CURVE. IDENTIFY ON THE PUMP CURVE WHICH CURVE KEY IS |
| | SPECIFIC TO THE PUMP BEING INSTALLED ON THIS POOL. THIS |
| | IS NEEDED TO CONFIRM THE MAXIMUM SYSTEM FLOW FROM THE |
| | TDH CALCULATIONS PER THE ANSI/APSP/ICC 7 - 2015 SECS. |
| | 4.4.9, 4.4.9.1. |
| | |
| | 3. A SUB GAS PERMIT IS REQUIRED BY A LICENSED |
| | CONTRACTOR FOR THE SCOPE OF WORK PER THE WPB AMENDMENTS |
| | TO THE FBC SEC. 105.1. |
| | |
| | WHEN RESUBMITTING PLANS, PLEASE INDICATE THE REVISION & |
| | REMOVE ANY VOIDED SHEETS & REPLACE ANY NECESSARY PAGES. |
| | A TRANSMITTAL LETTER LISTING THE ORIGINAL REVIEW |
| | COMMENT NUMBER, WITH A DESCRIPTION OF THE REVISION, |
| | MADE, IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE |
| | THE CHANGES CAN BE FOUND WILL HELP EXPEDITE YOUR |
| | PERMIT. THANK YOU FOR YOUR ANTICIPATED COOPERATION. |
| | |
| | HTTPS://CODES.ICCSAFE.ORG/CODES/FLORIDA |
| | |
| | LUIS A. CRESPO |
| | PLUMBING PLAN EXAMINER / INSPECTOR |
| | EMAIL: [email protected] OFFICE: 561 805-6720 |
| | |