| 2021-10-20 11:04:50 | PLAN |
| | REVIEW COMMENTS |
| | 4400 BEACON CIRCLE |
| | 2 STORY OFFICE BUILDING |
| | BUSINESS OCCUPANCY |
| | TYPE II-B CONSTRUCTION, SPRINKLERED |
| | FLOOD ZONE: X |
| | 21,081 GROSS SQ-FT |
| | GROUND FLOOR ELEVATION: 16.0' NAVD88 |
| | |
| | 1ST REVIEW: BC SEVENTH EDITION (2020) |
| | ROBERT MCDOUGAL, CBO |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | (561) 805-6714 |
| | [email protected] |
| | |
| | DENIED BY BUILDING |
| | PLEASE ADDRESS THE ITEMS NOTED BELOW: |
| | |
| | 1) SUBMIT A SIGNED AND SEALED GEOTECHNICAL REPORT. FBC |
| | 1803.2 |
| | |
| | 2) SUBMIT A SCHEMATIC FIRE SPRINKLER PLAN WITH |
| | STANDPIPES AND RISER DIAGRAM. FBC AMENDMENTS 107.3.5.1 |
| | |
| | 3) SUBMIT A PLAN FOR SAFEGUARDS DURING CONSTRUCTION AND |
| | MOT. FBC CHAPTER 33 |
| | |
| | 4) ON SHEET G003, UNDER THE DEFERRED SUBMITTALS, NOTE |
| | (1) FOR THE WELDING AND BOLTING REQUIREMENTS AND (2) |
| | NOTE (5) FOR THE WINDOW INSTALLATION REFERENCE THE |
| | PREVIOUS CODE (2017 FBC-B) RATHER THAN THE CURRENT ONE |
| | (2020 FBC-B) . PLEASE CORRECT. |
| | |
| | 5) THE PERMIT CAN NOT BE ISSUED UNTIL THERE IS A |
| | RECORDED UNITY OF TITLE OR RE-PLAT OF THE THREE PARCELS |
| | SHOWN ON THE SURVEY FOR THIS PROJECT. |
| | |
| | 6) THE CALCULATIONS FOR THE OCCUPANT LOAD FOR THE DAY |
| | CARE IS INCORRECT. THE NET SQ-FT OF 192 DIVIDED BY 35 |
| | SQ-FT PER OCCUPANT (FBC TABLE 1004.5) RESULTS IN 5.48 |
| | PEOPLE WHICH ROUNDS UP TO 6 OCCUPANTS. IN ORDER TO BE |
| | CLASSIFIED AS PART OF THE PRIMARY OCCUPANCY, THERE CAN |
| | BE NO MORE THAN 5 OCCUPANTS. WHEN THERE IS MORE THAN 5 |
| | OCCUPANTS THE DAY CARE IS CLASSIFIED AS A GROUP I-4 |
| | OCCUPANCY. FBC 308.6 & 308.6.3 |
| | |
| | 7) ON SHEET S001, UNDER 1060 DESIGN AND CONSTRUCTION |
| | STANDARDS, THE 2017 FBC IS SPECIFIED. PLEASE REVISE TO |
| | 2020 FBC. |
| | |
| | 8) ON SHEET S001 THE WIND LOADS SPECIFY THE ULTIMATE |
| | WIND VELOCITY AS 168 MPH AND THE ALLOWABLE STRESS |
| | DESIGN VELOCITY AS 101 MPH. THE NOMINAL ASD IS THE |
| | ULTIMATE WIND SPEED MULTIPLIED BY THE SQUARE ROOT OF |
| | 0.6, WHICH IS 130 MPH. PLEASE CORRECT. FBC 1609.3.1 |
| | |
| | 9) ON SHEET ID1122, THE SINK IN BREAK ROOM 207 DOES NOT |
| | HAVE THE REQUIRED CLEAR FLOOR SPACE FOR A PARALLEL |
| | APPROACH AND THE REQUIRED KNEE AND TOE IS NOT SHOWN. |
| | SHOW COMPLIANCE WITH FBC ACCESSIBILITY 606.2 . |
| | |
| | 10) ON SHEET ID1121, THE COUNTER TOP IN TESTING ROOM |
| | 104 IS SHOWN AT 3' (36") AND ON SHEET ID1122, THE |
| | COUNTER TOP IN PRODUCTION ROOM 115 IS SHOWN AT 3' |
| | (36"). SHOW COMPLIANCE WITH FBC ACCESSIBILITY 902.3 FOR |
| | HEIGHTS OF DINING AND WORK SURFACES. |
| | |
| | 11) ON SHEET ID1122, THE BUILT-IN COUNTER TOP IN BREAK |
| | ROOM 128 IS SPECIFIED AS 3'-6" (42") IN HEIGHT. SHOW |
| | COMPLIANCE WITH FBC ACCESSIBILITY 902.3 FOR HEIGHTS OF |
| | DINING AND WORK SURFACES. |
| | |
| | 12) ON SHEET G003, THERE IS A HEADING "PROVISO DEFERRED |
| | SUBMITTAL". AMONG THE ITEMS THAT ARE LISTED FOR |
| | DEFERRED SUBMITTAL ARE PRODUCTS REGULATED BY DBPR RULE |
| | 9N-03, WHICH INCLUDES EXTERIOR DOORS, WINDOWS, |
| | STOREFRONTS, MULLIONS, WALL LOUVERS, ROOFING MATERIALS, |
| | ETC. IF YOU WISH TO DEFER THESE ITEMS IT IS NOT |
| | REQUIRED THAT YOU SUBMIT THEM PRIOR TO RECEIVING THE |
| | PERMIT. THEY DO HAVE TO BE SUBMITTED AND APPROVED |
| | BEFORE THEY ARE INSTALLED. FBC AMENDMENTS 107.3.4.1 |
| | DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS SECTION, |
| | DEFERRED SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF |
| | THE DESIGN THAT ARE NOT SUBMITTED AT THE TIME OF THE |
| | APPLICATION AND THAT ARE TO BE SUBMITTED TO THE |
| | BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL |
| | OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF |
| | THE BUILDING OFFICIAL. THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE |
| | DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR |
| | REVIEW BY THE BUILDING OFFICIAL. THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE |
| | DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR |
| | REVIEW BY THE BUILDING OFFICIAL. |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| | THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| | OFFICIAL. |
| | |
| | 13) THE PRODUCT APPROVALS THAT WERE SUBMITTED HAVE NOT |
| | BEEN REVIEWED AND APPROVED IN WRITING BY THE DESIGNER |
| | OF RECORD FOR THIS PROJECT. FBC AMENDMENTS 107.3.4 |
| | |
| | 14) THE PRODUCT APPROVALS FOR THE ROOFING AND PV RACKS |
| | ONLY HAVE THE COVERSHEETS. THE EVALUATION REPORT AND |
| | INSTALLATION INSTRUCTIONS WITH THE DESIGN PRESSURES ARE |
| | MISSING. THE SPECIFIC ROOF COVERING ASSEMBLIES AND THE |
| | DESIGN PRESSURES ARE REQUIRED TO BE CIRCLED OR HI-LITED |
| | IN THE PRODUCT APPROVAL. ENHANCED FASTENING |
| | CALCULATIONS MAY BE REQUIRED. FBC AMENDMENTS 107.2.1 |
| | |
| | 15) FOR ALL OF THE PRODUCT APPROVALS, SPECIFY ( HI-LITE |
| | OR CIRCLE) THE SPECIFIC ITEMS AND THEIR MAXIMUM DESIGN |
| | PRESSURES IN THE APPROVALS. FBC AMENDMENTS 107.2.1 |
| | |
| | 16) SUBMIT PRODUCT APPROVALS OR SITE SPECIFIC |
| | ENGINEERING FOR THE PRE-FAB METAL CANOPY SHOWN IN |
| | DETAIL #3 ON SHEET A605. FBC AMENDMENTS 107.3.4 |
| | |
| | 17) ADDITIONAL COMMENTS MAY BE GENERATED FROM THE |
| | RESPONSES TO THESE COMMENTS. |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |