Plan Review Notes For Permit 21090266
Permit Number 21090266
Review Stop B
Sequence Number 1
Notes
Date Text
2021-10-20 11:04:50PLAN
 REVIEW COMMENTS
 4400 BEACON CIRCLE
 2 STORY OFFICE BUILDING
 BUSINESS OCCUPANCY
 TYPE II-B CONSTRUCTION, SPRINKLERED
 FLOOD ZONE: X
 21,081 GROSS SQ-FT
 GROUND FLOOR ELEVATION: 16.0' NAVD88
  
 1ST REVIEW: BC SEVENTH EDITION (2020)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) SUBMIT A SIGNED AND SEALED GEOTECHNICAL REPORT. FBC
 1803.2
  
 2) SUBMIT A SCHEMATIC FIRE SPRINKLER PLAN WITH
 STANDPIPES AND RISER DIAGRAM. FBC AMENDMENTS 107.3.5.1
  
 3) SUBMIT A PLAN FOR SAFEGUARDS DURING CONSTRUCTION AND
 MOT. FBC CHAPTER 33
  
 4) ON SHEET G003, UNDER THE DEFERRED SUBMITTALS, NOTE
 (1) FOR THE WELDING AND BOLTING REQUIREMENTS AND (2)
 NOTE (5) FOR THE WINDOW INSTALLATION REFERENCE THE
 PREVIOUS CODE (2017 FBC-B) RATHER THAN THE CURRENT ONE
 (2020 FBC-B) . PLEASE CORRECT.
  
 5) THE PERMIT CAN NOT BE ISSUED UNTIL THERE IS A
 RECORDED UNITY OF TITLE OR RE-PLAT OF THE THREE PARCELS
 SHOWN ON THE SURVEY FOR THIS PROJECT.
  
 6) THE CALCULATIONS FOR THE OCCUPANT LOAD FOR THE DAY
 CARE IS INCORRECT. THE NET SQ-FT OF 192 DIVIDED BY 35
 SQ-FT PER OCCUPANT (FBC TABLE 1004.5) RESULTS IN 5.48
 PEOPLE WHICH ROUNDS UP TO 6 OCCUPANTS. IN ORDER TO BE
 CLASSIFIED AS PART OF THE PRIMARY OCCUPANCY, THERE CAN
 BE NO MORE THAN 5 OCCUPANTS. WHEN THERE IS MORE THAN 5
 OCCUPANTS THE DAY CARE IS CLASSIFIED AS A GROUP I-4
 OCCUPANCY. FBC 308.6 & 308.6.3
  
 7) ON SHEET S001, UNDER 1060 DESIGN AND CONSTRUCTION
 STANDARDS, THE 2017 FBC IS SPECIFIED. PLEASE REVISE TO
 2020 FBC.
  
 8) ON SHEET S001 THE WIND LOADS SPECIFY THE ULTIMATE
 WIND VELOCITY AS 168 MPH AND THE ALLOWABLE STRESS
 DESIGN VELOCITY AS 101 MPH. THE NOMINAL ASD IS THE
 ULTIMATE WIND SPEED MULTIPLIED BY THE SQUARE ROOT OF
 0.6, WHICH IS 130 MPH. PLEASE CORRECT. FBC 1609.3.1
  
 9) ON SHEET ID1122, THE SINK IN BREAK ROOM 207 DOES NOT
 HAVE THE REQUIRED CLEAR FLOOR SPACE FOR A PARALLEL
 APPROACH AND THE REQUIRED KNEE AND TOE IS NOT SHOWN.
 SHOW COMPLIANCE WITH FBC ACCESSIBILITY 606.2 .
  
 10) ON SHEET ID1121, THE COUNTER TOP IN TESTING ROOM
 104 IS SHOWN AT 3' (36") AND ON SHEET ID1122, THE
 COUNTER TOP IN PRODUCTION ROOM 115 IS SHOWN AT 3'
 (36"). SHOW COMPLIANCE WITH FBC ACCESSIBILITY 902.3 FOR
 HEIGHTS OF DINING AND WORK SURFACES.
  
 11) ON SHEET ID1122, THE BUILT-IN COUNTER TOP IN BREAK
 ROOM 128 IS SPECIFIED AS 3'-6" (42") IN HEIGHT. SHOW
 COMPLIANCE WITH FBC ACCESSIBILITY 902.3 FOR HEIGHTS OF
 DINING AND WORK SURFACES.
  
 12) ON SHEET G003, THERE IS A HEADING "PROVISO DEFERRED
 SUBMITTAL". AMONG THE ITEMS THAT ARE LISTED FOR
 DEFERRED SUBMITTAL ARE PRODUCTS REGULATED BY DBPR RULE
 9N-03, WHICH INCLUDES EXTERIOR DOORS, WINDOWS,
 STOREFRONTS, MULLIONS, WALL LOUVERS, ROOFING MATERIALS,
 ETC. IF YOU WISH TO DEFER THESE ITEMS IT IS NOT
 REQUIRED THAT YOU SUBMIT THEM PRIOR TO RECEIVING THE
 PERMIT. THEY DO HAVE TO BE SUBMITTED AND APPROVED
 BEFORE THEY ARE INSTALLED. FBC AMENDMENTS 107.3.4.1
 DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS SECTION,
 DEFERRED SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF
 THE DESIGN THAT ARE NOT SUBMITTED AT THE TIME OF THE
 APPLICATION AND THAT ARE TO BE SUBMITTED TO THE
 BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL
 OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF
 THE BUILDING OFFICIAL. THE REGISTERED DESIGN
 PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE
 DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR
 REVIEW BY THE BUILDING OFFICIAL. THE REGISTERED DESIGN
 PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE
 DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR
 REVIEW BY THE BUILDING OFFICIAL.
 DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE
 SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN
 RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD
 THEM TO THE BUILDING OFFICIAL WITH A NOTATION
 INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE
 BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO
 THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL
 ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED
 SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING
 OFFICIAL.
  
 13) THE PRODUCT APPROVALS THAT WERE SUBMITTED HAVE NOT
 BEEN REVIEWED AND APPROVED IN WRITING BY THE DESIGNER
 OF RECORD FOR THIS PROJECT. FBC AMENDMENTS 107.3.4
  
 14) THE PRODUCT APPROVALS FOR THE ROOFING AND PV RACKS
 ONLY HAVE THE COVERSHEETS. THE EVALUATION REPORT AND
 INSTALLATION INSTRUCTIONS WITH THE DESIGN PRESSURES ARE
 MISSING. THE SPECIFIC ROOF COVERING ASSEMBLIES AND THE
 DESIGN PRESSURES ARE REQUIRED TO BE CIRCLED OR HI-LITED
 IN THE PRODUCT APPROVAL. ENHANCED FASTENING
 CALCULATIONS MAY BE REQUIRED. FBC AMENDMENTS 107.2.1
  
 15) FOR ALL OF THE PRODUCT APPROVALS, SPECIFY ( HI-LITE
 OR CIRCLE) THE SPECIFIC ITEMS AND THEIR MAXIMUM DESIGN
 PRESSURES IN THE APPROVALS. FBC AMENDMENTS 107.2.1
  
 16) SUBMIT PRODUCT APPROVALS OR SITE SPECIFIC
 ENGINEERING FOR THE PRE-FAB METAL CANOPY SHOWN IN
 DETAIL #3 ON SHEET A605. FBC AMENDMENTS 107.3.4
  
 17) ADDITIONAL COMMENTS MAY BE GENERATED FROM THE
 RESPONSES TO THESE COMMENTS.
  
  
  
  
  
  
  
  
  
  
  
  