| Plan Review Notes For Permit 21081686 |
| Permit Number |
21081686 |
|
| Review Stop |
ENG |
| Sequence Number |
1 |
|
| Notes |
| Date |
Text |
| 2021-12-09 07:39:49 | AT THIS TIME ENGINEERING AND PUBLIC UTILITIES ARE NOT | | | SIGNING OFF ON ANY PERMITS UNTIL SUCH TIME THAT AN | | | AGREEMENT HAS BEEN REACHED REGARDING LIFT STATION NO. | | | 77. THE VILLAS, PARCEL L2 AND THE HOTEL ARE ALL | | | CONTRIBUTING FLOW. WE ARE WAITING ON THE COST ESTIMATE | | | AND TIME LINE WHICH IS BEING PREPARED BY MOCK ROOS & | | | ASSOC. UNDER CONTRACT WITH THE OWNERS. | | | | | | VINCENT J. NOEL, P.S.M. | | | ENGINEERING LAND DEVELOPMENT MANAGER | | | CITY OF WEST PALM BEACH | | | ENGINEERING SERVICES DEPARTMENT | | | 401 CLEMATIS ST., 4TH FLOOR | | | WEST PALM BEACH, FL 33401 | | | PHONE: 561-494-1096 | | | FAX: 561-494-1116 | | | CELL 561-644-7288 | | | [email protected] | | | |
|