| 2021-10-06 11:02:17 | BUILDING PLAN REVIEW |
| | |
| | CHRISTOPHER S. THROOP, C.B.O., CFM |
| | PLANS EXAMINER II PX3169/SFP306 |
| | INSPECTOR BN4338 |
| | BUILDING OFFICIAL BU1635 |
| | ASFPM CERTIFIED FLOODPLAIN MANAGER US-21-11935 |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | CITY OF WEST PALM BEACH |
| | (561) 805-6726 |
| | [email protected] |
| | |
| | CODES IN EFFECT: |
| | 2020 FLORIDA BUILDING CODE, 7TH EDITION W/2017 WEST |
| | PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING CODE, |
| | CHAPTER 1 ADMINISTRATION |
| | 2017 NEC |
| | |
| | 1ST REVIEW |
| | |
| | RESULTS: DENIED |
| | ADDRESS THE ATTACHED COMMENTS AND RE-SUBMIT |
| | |
| | NOTICE: LOT SPLIT HAS BEEN APPROVED BY THE CITY. NEW |
| | ADDRESS WILL BE 431 BARNETT ST. UNITY OF TITLE |
| | REQUIRED. |
| | |
| | 1. SUBMIT NEW SITE PLAN WITH NEW ADDRESS. IDENTIFY |
| | PROPOSED STRUCTURES ON LOT WITH SETBACK DEMENSIONS TO |
| | PROPERTY LINES. |
| | PROVIDE A SITE PLAN W/BOUNDRY LINE SURVEY |
| | 107.2.5 SITE PLAN. THE CONSTRUCTION DOCUMENTS SUBMITTED |
| | WITH THE APPLICATION FOR PERMIT SHALL BE ACCOMPANIED BY |
| | A SITE PLAN SHOWING TO SCALE THE SIZE AND LOCATION OF |
| | NEW CONSTRUCTION AND EXISTING STRUCTURES ON THE |
| | SITE,... AND IT SHALL BE DRAWN IN ACCORDANCE WITH AN |
| | ACCURATE AND INCLUDED BOUNDARY LINE SURVEY. |
| | |
| | 2. SUBMIT NEW PLANS WITH CORRECTED ADDRESS. |
| | 107.2 CONSTRUCTION DOCUMENTS. CONSTRUCTION DOCUMENTS |
| | SHALL BE IN ACCORDANCE WITH SECTIONS107.2.1 THROUGH |
| | 107.2.5. |
| | |
| | 3. PROVIDE FINISHED FLOOR ELEVATION. |
| | FINISH FLOOR ELEVATION ? NON-FLOOD ZONE |
| | R403.1.7.3 FOUNDATION ELEVATION. |
| | ON GRADED SITES, THE TOP OF ANY EXTERIOR FOUNDATION |
| | SHALL EXTEND ABOVE THE ELEVATION OF THE STREET GUTTER |
| | AT POINT OF DISCHARGE OR THE INLET OF AN APPROVED |
| | DRAINAGE DEVICE A MINIMUM OF 12 INCHES (305 MM) PLUS 2 |
| | PERCENT. |
| | ALTERNATE ELEVATIONS ARE PERMITTED SUBJECT TO THE |
| | APPROVAL OF THE BUILDING OFFICIAL, PROVIDED IT CAN BE |
| | DEMONSTRATED THAT REQUIRED DRAINAGE TO THE POINT OF |
| | DISCHARGE AND AWAY FROM THE STRUCTURE IS PROVIDED AT |
| | ALL LOCATIONS ON THE SITE. |
| | |
| | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. |
| | |
| | WHEN RESUBMITING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. |
| | |
| | |
| | |
| | |
| | |