| 2022-01-11 11:14:12 | SECOND ROOFING REVIEW: |
| | |
| | 1-PROVIDE PRODUCT APPROVAL AS REQUIRED BY FAC |
| | 61G20-3.001 FOR |
| | (NOTE: THIS MAY BE SUBMITTED LATER AS A DEFERRED |
| | SUBMITTAL. PROVIDE COMPLETE INFORMATION FOR REVIEW |
| | PRIOR TO INSTALLATION TO AVOID CONFLICTS/DELAYS. ALL |
| | PRODUCT APPROVALS NEED TO BE APPROVED IN WRITING BY |
| | DESIGNER OF RECORD PRIOR TO SUBMITTAL): |
| | |
| | A)HIP & RIDGE METAL SUPPORT TO BE USED. AND, CLEARLY |
| | MARK SPECIFIC METAL CHANNEL TO BE INSTALLED. SEE |
| | PERFORMANCE LIMITATIONS TABLES ON PRODUCT APPROVAL |
| | SUBMITTED. |
| | |
| | RESPONSE: |
| | NOT SUBMITTED. |
| | |
| | B) ROOF UNDERLAYMENT FL14317-R12 SUBMITTED: CLEARLY |
| | MARK WHICH TESTED ASSEMBLY IS GOING TO BE INSTALLED. |
| | SEC. 5.8.2 AND SEC. 5.8.3 OF PRODUCT APPROVAL |
| | SUBMITTED. |
| | THERE ARE 6 ASSEMBLIES. SPECIFY WHICH ASSEMBLY FROM |
| | SEC. 5.8.3.1 IS GOING TO BE INSTALLED. |
| | |
| | RESPONSE: |
| | STILL NOT CLEAR WHICH ASSEMBLY TO BE USED. TABLE 2 ON |
| | PAGE 4 OF 6 OF PRODUCT APPROVAL WAS MARKED, BUT IT |
| | DOESN'T CLARIFY IF USING ASTM D226 TYPE II FELT OR |
| | CITADEL PLUS AS THE SUBSTRATE. I F USING ASTM D226 FELT |
| | , THEN PROVIDE FRSA/TRI PRESCRIPTIVE METHOD USED. IF |
| | USING CITADEL PLUS , THEN CIRCLE WHICH ASSEMBLY IS |
| | GOING TO BE USED. SEE SEC. 5.8.2 OF PRODUCT APPROVAL |
| | SUBMITTED. |
| | |
| | |
| | PLEASE FEEL FREE TO CONTACT ME IF YOU HAVE ANY |
| | QUESTIONS REGARDING THESE COMMENTS, |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | (561)805-6712 |
| | [email protected] |
| | |