| Date |
Text |
| 2021-08-27 16:28:18 | OFFICE BUILDOUT |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected]. |
| | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 |
| | AMENDMENT |
| | |
| | CORRECTIONS NEEDED - |
| | 1) DRAWING A-101 - DOOR 1259 B AND 1259 A - PLEASE SHOW |
| | THE REQUIRED 48" BETWEEN THE DOORS PER FBC 1010.1.8 |
| | DOOR ARRANGEMENT. |
| | SPACE BETWEEN TWO DOORS IN A SERIES SHALL BE 48 INCHES |
| | (1219 MM) MINIMUM PLUS THE WIDTH OF A DOOR SWINGING |
| | INTO THE SPACE. DOORS IN A SERIES SHALL SWING EITHER IN |
| | THE SAME DIRECTION OR AWAY FROM THE SPACE BETWEEN THE |
| | DOORS. |
| | 2) PLEASE ADD MORE WALL DESIGNATION LABELS ON THE FLOOR |
| | PLANS TO CLARIFY THE WALL TYPES THAT ARE NOT MARKED - |
| | FBC WPB 107.2.1 |
| | 3) DRAWING G-001 - PLEASE SHOW THE MIRROR DIMENSION |
| | FROM THE FINISHED FLOOR TO THE "REFLECTIVE SURFACE" PER |
| | FBC 603.3 MIRRORS. |
| | MIRRORS LOCATED ABOVE LAVATORIES OR COUNTERTOPS SHALL |
| | BE INSTALLED WITH THE BOTTOM EDGE OF THE REFLECTING |
| | SURFACE 40 INCHES (1015 MM) MAXIMUM ABOVE THE FINISH |
| | FLOOR OR GROUND. |
| | 4) JOB COST SHOWN ON THE BUILDING PERMIT APPLICATION |
| | APPEARS TO BE LOW - FBC WPB 109.3 BUILDING PERMIT |
| | VALUATIONS. IF, IN THE OPINION OF THE BUILDING |
| | OFFICIAL, THE CLAIMED VALUATION |
| | OF BUILDING, ALTERATION, STRUCTURE, ELECTRICAL, GAS, |
| | MECHANICAL OR PLUMBING SYSTEMS APPEARS TO BE |
| | UNDERESTIMATED ON THE APPLICATION, THE PERMIT SHALL BE |
| | DENIED, UNLESS THE APPLICANT CAN SHOW |
| | DETAILED, QUANTITY ESTIMATES, AND/OR BONA FIDE SIGNED |
| | CONTRACTS (EXCLUDING LAND VALUE) TO MEET THE |
| | APPROVAL OF THE BUILDING OFFICIAL. FOR PERMITTING |
| | PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL |
| | BE TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL, |
| | ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH, |
| | RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES, |
| | MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING |
| | ONLY LAND VALUE. |
| | |
| | |
| | |