Plan Review Notes
Plan Review Notes For Permit 21070766
Permit Number 21070766
Review Stop P
Sequence Number 1
Notes
Date Text
2021-07-21 13:00:3307/21/21 1ST PLUMBING REVIEW**DENIED** WITH COMMENTS
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME, AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1. SUBMIT TOTAL DYNAMIC HEAD CALCULATIONS FOR THE
 MAXIMUM SYSTEM FLOW. THE MAXIMUM FLOW OF THE PUMP FROM
 ITS PUMP CURVE IS NO LONGER ALLOWED TO BE USED IN
 DETERMINING THE MAXIMUM SYSTEM FLOW RATE PER
 ANSI/APSP/ICC 7 - 2013 SECS. 4.4.9, 4.4.9.1. THE 2013
 EDITION ADDRESSES THE FLOW RATE IN GALLONS PER MINUTE
 (GPM). IT REQUIRES THAT THE MAXIMUM SYSTEM FLOW RATE
 DOES NOT EXCEED THE LISTED MAXIMUM FLOW RATE OF THE
 SUCTION OUTLET FITTING ASSEMBLY (DRAIN COVER). THE TDH
 CALCULATIONS MUST INCLUDE ALL THE SYSTEM COMPONENTS,
 INCLUDING SUCTION AND RETURN PIPING, FITTINGS, VALVES,
 HEATER, FILTER, AND CHLORINATOR. ALL SYSTEM COMPONENTS
 EXCEPT THE PUMP. 4.4.9.1 MAXIMUM SYSTEM FLOW
 RATE?UNSECURED CONTROL SYSTEMS. THE MAXIMUM SYSTEM FLOW
 RATE IS THE PUMP?S FLOW RATE AT THE HIGHEST
 USER-SELECTABLE SPEED WHILE THE SYSTEM IS CONFIGURED TO
 OPERATE AT THE LOWEST ACHIEVABLE SYSTEM TDH WHEN ALL
 FLOW IS FROM THE SUBMERGED SUCTION SYSTEM (SKIMMER
 OFF), THE FILTER(S) IS CLEAN (WHEN INCLUDED), AND ALL
 PRESSURE-SIDE VALVES ARE IN THE OPEN (MAXIMUM FLOW)
 POSITION. THIS OPERATING POINT IS DETERMINED BY ONE OF
 THE FOLLOWING:
  
 - MEASURING WITH FLOW METER ACCURATE TO ?10% AND
 INSTALLED ACCORDING TO THE MANUFACTURER'S
 SPECIFICATION, OR
  
 - COMPUTING USING COMPLETE SYSTEM TDH CALCULATIONS AND
 THEN LOOKING UP THE FLOW RATE USING THE MANUFACTURER'S
 CERTIFIED PUMP CURVE, OR
  
 - MEASURING SYSTEM TDH AT THE PUMP?S DRAIN PLUGS AND
 THEN LOOKING UP THE FLOW RATE USING THE MANUFACTURER'S
 CERTIFIED PUMP CURVE.
  
 2. SUBMIT THE POOL PUMP CURVE. IDENTIFY ON THE PUMP
 CURVE WHICH CURVE KEY IS SPECIFIC TO THE PUMP BEING
 INSTALLED ON THIS POOL. THIS IS NEEDED TO CONFIRM THE
 MAXIMUM SYSTEM FLOW FROM THE TDH CALCULATIONS PER THE
 ANSI/APSP/ICC 7 - 2013 SECS. 4.4.9, 4.4.9.1
  
 3. SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE MAIN
 DRAIN, THE PUMP, FILTER AND CHLORINATOR PER THE WPB
 AMENDMENTS TO FBC SEC. 107.2.1.
  
 WHEN RESUBMITTING PLANS, PLEASE INDICATE THE REVISION &
 REMOVE ANY VOIDED SHEETS & REPLACE ANY NECESSARY PAGES.
 A TRANSMITTAL LETTER LISTING THE ORIGINAL REVIEW
 COMMENT NUMBER, WITH A DESCRIPTION OF THE REVISION,
 MADE, IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE
 THE CHANGES CAN BE FOUND WILL HELP EXPEDITE YOUR
 PERMIT. THANK YOU FOR YOUR ANTICIPATED COOPERATION.
  
 HTTPS://CODES.ICCSAFE.ORG/CODES/FLORIDA
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  