| Date |
Text |
| 2021-07-27 08:28:02 | PLAN REVIEW BUILDING |
| | |
| | CHRISTOPHER S. THROOP, C.B.O., CFM |
| | PLANS EXAMINER II PX3169/SFP306 |
| | INSPECTOR BN4338 |
| | BUILDING OFFICIAL BU1635 |
| | ASFPM CERTIFIED FLOODPLAIN MANAGER US-21-11935 |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | CITY OF WEST PALM BEACH |
| | (561) 805-6726 |
| | [email protected] |
| | |
| | CODES IN EFFECT: |
| | 2020 FLORIDA BUILDING CODE, 7TH EDITION W/2017 WEST |
| | PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING CODE, |
| | CHAPTER 1 ADMINISTRATION |
| | 2017 NEC |
| | |
| | 1ST REVIEW |
| | |
| | RESULTS: DENIED |
| | ADDRESS THE ATTACHED COMMENTS AND RE-SUBMIT |
| | |
| | NOTICE: A SEPERATE PERMIT IS REQUIRED FOR FREE STANDING |
| | GARAGE. |
| | NOTICE: A SEPERATE PERMIT IS REQUIRED FOR SITE WALLS. |
| | |
| | 1. PROVIDE AN UPDATED BOUNDRY LINE SURVEY. |
| | 107.2 CONSTRUCTION DOCUMENTS. CONSTRUCTION DOCUMENTS |
| | SHALL BE IN ACCORDANCE WITH SECTIONS107.2.1 THROUGH |
| | 107.2.5. |
| | |
| | 2. PROVIDE SOILS REPORT. |
| | FBC 1803.1 GENERAL. GEOTECHNICAL INVESTIGATIONS SHALL |
| | BE CONDUCTED IN ACCORDANCE WITH SECTION 1803.2 AND |
| | REPORTED IN ACCORDANCE WITH SECTION 1803.6. |
| | |
| | 3. PROVIDE PRODUCT APPROVALS FOR WINDOWS AND EXT. |
| | DOORS. |
| | FBC 107.3.4 PROVIDE PRODUCT APPROVALS FOR THOSE |
| | PRODUCTS WHICH ARE REGULATED BY FAC RULE 9N-3 REVIEWED |
| | AND APPROVED IN WRITING BY THE DESIGNER OF RECORD. |
| | |
| | DEFERRAL OPTION: |
| | |
| | 107.3.4.1 DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS |
| | SECTION, DEFERRED SUBMITTALS ARE DEFINED AS THOSE |
| | PORTIONS OF THE DESIGN THAT ARE NOT SUBMITTED AT THE |
| | TIME OF THE APPLICATION AND THAT ARE TO BE SUBMITTED TO |
| | THE BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. |
| | DEFERRAL OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR |
| | APPROVAL OF THE BUILDING OFFICIAL. THE REGISTERED |
| | DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST |
| | THE DEFERRED SUBMITTALS ON |
| | THE CONSTRUCTION DOCUMENTS FOR REVIEW BY THE BUILDING |
| | OFFICIAL. |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| | THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| | OFFICIAL. |
| | |
| | 4. ROOF PLAN PAGE A-3.1 STATES ROOF ASSEMBLY INSULATION |
| | R VALUE AS R-30. ENERGY SUBMITTAL STATES ROOF ASSEMBLY |
| | R VALUE AS R-20. |
| | PLEASE CLARIFY. |
| | 107.2 CONSTRUCTION DOCUMENTS. CONSTRUCTION DOCUMENTS |
| | SHALL BE IN ACCORDANCE WITH SECTIONS107.2.1 THROUGH |
| | 107.2.5. |
| | |
| | 5. PROVIDE THE ICC-ES REPORT FOR THE PROPOSED ICYNENE |
| | SPRAY FOAM INSULATION. |
| | 107.2 CONSTRUCTION DOCUMENTS. CONSTRUCTION DOCUMENTS |
| | SHALL BE IN ACCORDANCE WITH SECTIONS107.2.1 THROUGH |
| | 107.2.5. |
| | |
| | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED |
| | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. |
| | |
| | WHEN RESUBMITING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. |
| | |