| Date |
Text |
| 2021-07-01 09:20:55 | 1ST REVIEW FBC-2020 PLUMBING |
| | PERMIIT- 21051188 |
| | 6/30/21 |
| | |
| | CODES IN EFFECT: |
| | FBC P- FLORIDA PLUMBING CODE 7TH EDITION 2020 |
| | FBC ACC- FLORIDA ACCESSIBILITY CODE 7TH EDITION 2020 |
| | FBC B- FLORIDA BUILDING CODE 7TH EDITION 2020 |
| | FBC EC- FLORIDA ENERGY CONSERVATION CODE 7TH EDITION |
| | 2020 |
| | FS- FLORIDA STATUTES |
| | FAC- FLORIDA ADMINISTRATIVE CODE |
| | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC |
| | |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | 1) PLEASE NOTE THAT INSTALLATION OF THE IRRIGATION |
| | SYSTEM AND THE GREASE INTERCEPTOR SHALL BE UNDER |
| | SEPARATE PERMIT AND WILL REQUIRE SEPARATE PRIMARY |
| | PERMIT APPLICATIONS AND PLAN SUBMITTALS- SECTION 105.1 |
| | & 107.2.1. THE CIVIL PLAN C8 SHOWS EXISTING BACKFLOW |
| | PREVENTERS FOR THE POTABLE WATER SERVICE AND FIRE LINE- |
| | PLEASE NOTE THAT REPLACEMENT OR RELOCATION OF THE |
| | DEVICES WILL REQUIRE SEPARATE PRIMARY PERMIT |
| | APPLICATIONS AND PLAN SUBMITTALS. |
| | |
| | 2) SHEETS A0.24 & A0.24: THE FINISH WALL SCHEDULE FOR |
| | THE MEN'S, WOMEN'S AND FAMILY TOILET ROOMS, AND THE |
| | UTILITY ROOMS INDICATES NON-COMPLIANT PAINTED DRYWALL |
| | FOR FINISHED WALL SURROUND MATERIALS AT PLUMBING |
| | FIXTURE LOCATIONS INCLUDING THE MOP SINKS- SEE SECTION |
| | 310.3 FBC P AND SECTION 1210.2.2 FBC B AND PROVIDE A |
| | HARD, NON-ABSORBENT MATERIAL SUCH AS TILE. |
| | |
| | 3) A1.31, A1.32, A5.3: PROVIDE ROOF AND OVERFLOW DRAIN |
| | EQUIPMENT SCHEDULES AND PROVIDE INSTALLATION DETAILS- |
| | SECTION 1105.1 FBC P. |
| | |
| | 4) A4.03: SHOW THE CLEAR FLOOR SPACE DIAGRAM AND |
| | DIMENSION AT THE ACCESSIBLE URINAL- SECTIONS 213.3.3 & |
| | 605.3 FBC ACC. |
| | |
| | 5) A4.03 & A4.04: PROVIDE THE LENGTH DIMENSIONS OF THE |
| | STANDARD TOILET STALLS- SECTION 405.3.1 FBC P. |
| | |
| | 6) A4.03 & A4.03: PROVIDE TURNING SPACE DIAGRAMS IN THE |
| | TOILET ROOMS AND COMPARTMENTS- SECTION 603.2.1 FBC ACC. |
| | |
| | 7) A4.03 & A4.04: PROVIDE THE CLEAR WIDTH OPENINGS OF |
| | THE TOILET COMPARTMENT DOORS- SECTION 604.8.1.2 AND |
| | 404.2.3 FBC ACC. |
| | |
| | 8) A4.04: PROVIDE A DOOR FOR THE MEN'S TOILET |
| | COMPARTMENT- FIGURE 604.8.1.6 FBC ACC. |
| | |
| | 8) A4.04: PROVIDE THE MANEUVERING CLEARANCE DIAGRAM AND |
| | DIMENSIONS FOR THE MEN'S AND WOMEN'S TOILET COMPARTMENT |
| | DOOR- FIGURE 404.2.4.1(A) FBC ACC. |
| | |
| | 9) A4.03 & A4.04: SHOW THE MINIMUM 4-INCH CLEARANCES |
| | FROM THE DOOR OPENINGS TO THE ADJACENT SIDE WALLS- |
| | SECTION 604.8.1.6 FBC ACC. |
| | |
| | 10) A4.03: THE DOOR IN TOILET ROOM 1023 SHALL NOT SWING |
| | INTO THE CLEAR FLOOR SPACE OF THE LAVATORY- SECTION |
| | 603.2.3 FBC ACC. |
| | |
| | 11) A4.03 & A4.04: PLEASE PROVIDE ENLARGED DRAWINGS FOR |
| | ALL TOILET ROOMS SHOWN ON THE 1ST AND 2ND FLOORS |
| | INCLUDING RMS- 1028, 2042, 2044- SECTIONS 213.1 ? |
| | 213.3.7 FBC ACC. |
| | |
| | 12) A4.03 & A4.04: MISSING ACCESSIBILITY COMPLIANCE |
| | DETAILS AND DIMENSIONS FOR THE TOILET ROOMS. |
| | A) CENTERLINES OF THE WATER CLOSET FROM THE SIDE WALLS- |
| | SECTION 604.2. |
| | B) HEIGHTS OF THE WATER CLOSET SEATS FROM THE FINISHED |
| | FLOORS- SECTION 604.4. |
| | C) HEIGHTS OF THE LAVATORY SINK RIM OR COUNTER SURFACE |
| | FROM THE FINISHED FLOOR- SECTION 606.3. |
| | D) HEIGHTS OF THE MIRRORS FROM THE FINISHED FLOORS TO |
| | THE REFLECTIVE SURFACES- SECTION 603.3 |
| | E) LOCATIONS, LENGTHS, AND MOUNTING HEIGHTS OF GRAB |
| | BARS FOR THE WATER CLOSETS- SECTION 604.5 & 609.4, |
| | FIGURES 604. |
| | F) LOCATION OF THE WATER CLOSET FLUSH CONTROLS - |
| | SECTION 604.6. |
| | G) CENTERLINES OF THE TOILET PAPER DISPENSER MEASURED |
| | FROM THE FRONTS OF THE WATER CLOSETS- SECTION AND |
| | FIGURE 604.7. |
| | H) KNEE AND TOE CLEARANCES FOR THE LAVATORIES AND OTHER |
| | ACCESSIBLE SINKS- SECTION 606.2. |
| | |
| | 13) A0.6, A1.11, A1.13: SHOW THE CLEAR FLOOR DIAGRAMS |
| | AND DIMENSIONS FOR THE ACCESSIBLE DRINKING FOUNTAINS- |
| | SECTION 602.2 FBC ACC. REVISE THE DETAIL TO SHOW THE |
| | SPOUT HEIGHT FOR THE STANDING PERSONS? DRINKING |
| | FOUNTAIN- SECTION 602.7. INDICATE HOW THE LOCATIONS OF |
| | THE FOUNTAINS WILL BE IN COMPLIANCE WITH SECTION 307.2 |
| | PROTRUSION LIMITS. |
| | |
| | 14) A1.11, A1.13, & A4.21: SHOW THE LOCATION OF THE |
| | ACCESSIBLE SINK SHOWN IN ELEVATION 5, AND PROVIDE THE |
| | CLEAR FLOOR SPACE DIAGRAM AND DIMENSIONS FOR FORWARD OR |
| | PARALLEL APPROACH- SECTION 305.1 & 606.2 FBC ACC. SHOW |
| | KNEE AND TOE AND TOE CLEARANCE DIAGRAM AND DIMENSIONS |
| | FOR FORWARD APPROACHES- FIGURE 306.3 FBC ACC. |
| | |
| | 15) A1.11, A1.13, & A4.22: SHOW THE LOCATIONS OF THE |
| | ACCESSIBLE SINK, APPLIANCES AND COFFEE MAKERS SHOWN IN |
| | ELEVATION 4 AND PROVIDE THE CLEAR FLOOR SPACE DIAGRAMS |
| | AND DIMENSIONS FOR FORWARD OR PARALLEL APPROACHES, AND |
| | THE REACH RANGES TO CONTROLS- SECTIONS 606.2, 305.1, |
| | 308.1 & 309.1 FBC ACC. |
| | |
| | 16) P2.1: NOTE #4 IS BEING USED TWICE TO IDENTIFY |
| | ELEVATOR SUMPS AND WHAT APPEARS TO BE ROOF DRAIN |
| | VERTICAL LEADERS. PLEASE CHANGE THE NUMBERED NOTE FOR |
| | THE LEADER AND PROVIDE COMPLETE INFORMATION ABOUT THE |
| | LEADERS- SECTION 107.2.1 WPB. |
| | |
| | 17) P2.3 ROOF AND STORM DRAIN PLAN: |
| | A) PROVIDE DRAINAGE CALCULATIONS IN ACCORDANCE WITH |
| | SECTION1106.1 FBC P. |
| | B) PROVIDE STORM DRAINAGE ISOMETRIC DRAWINGS FOR |
| | PRIMARY AND SECONDARY ROOF DRAIN SYSTEMS. INDICATE THE |
| | SIZES OF THE HORIZONTAL AND VERTICAL STORM DRAIN PIPES, |
| | THE GPM FLOW AT EACH ROOF DRAIN LOCATION, AND THE PIPE |
| | RUNS AND DISCHARGE LOCATIONS- TABLES 1106.2 & 1106.3 |
| | FBC P. INDICATE HOW THE RAINWATER FROM THE ROOF WILL BE |
| | DRAINED AWAY FROM THE BUILDING TO AN APPROVED PLACE OF |
| | DISPOSAL- SECTION 1101.2 FBC P. |
| | C) VERIFY THE ROOF IS DESIGNED IN COMPLIANCE WITH |
| | SECTION 1101.7 ROOF DESIGN. |
| | ROOFS SHALL BE DESIGNED FOR THE MAXIMUM POSSIBLE DEPTH |
| | OF WATER THAT WILL POND THEREON AS DETERMINED BY THE |
| | RELATIVE LEVELS OF ROOF DECK AND OVERFLOW WEIRS, |
| | SCUPPERS, EDGES OR SERVICEABLE DRAINS IN COMBINATION |
| | WITH THE DEFLECTED STRUCTURAL ELEMENTS. IN DETERMINING |
| | THE MAXIMUM POSSIBLE DEPTH OF WATER, ALL PRIMARY ROOF |
| | DRAINAGE MEANS SHALL BE ASSUMED TO BE BLOCKED. THE |
| | MAXIMUM POSSIBLE DEPTH OF WATER ON THE ROOF SHALL |
| | INCLUDE THE HEIGHT OF THE WATER REQUIRED ABOVE THE |
| | INLET OF THE SECONDARY ROOF DRAINAGE MEANS TO ACHIEVE |
| | THE REQUIRED FLOW RATE OF THE SECONDARY DRAINAGE MEANS |
| | TO ACCOMMODATE THE DESIGN RAINFALL RATE AS REQUIRED BY |
| | SECTION 1106. |
| | |
| | 18) P2.1, P4.1, P5.1 & K1.0: HAND SINKS 001, 504, 505, |
| | 506, 507, & 508 SHALL NOT DRAIN INTO THE GREASE WASTE |
| | LINE AND INTERCEPTOR- SECTION 1003.3.1 FBC P. |
| | |
| | 19) P2.1, P4.1, P5.1 & K1.0: DRAINAGE FROM THE FLOOR |
| | SINKS AT THE CONDENSATE HOOD AND BY THE ICE MAKER/ICE |
| | BIN, AND FROM THE EVAPORATORS AND FLOOR DRAINS IN THE |
| | WALK-IN BOXES SHALL NOT DRAIN INTO THE GREASE WASTE |
| | LINE AND INTERCEPTOR- SECTION 1003.3.1 FBC P. PLEASE |
| | NOTE THAT SEC. 90- 126 PROHIBITS CONDENSATE FROM |
| | COOLING COILS TO DRAIN INTO THE SANITARY SYSTEM. PLEASE |
| | CLARIFY THE PURPOSE OF THE TRENCH DRAIN AND WHAT TYPE |
| | OF WASTE WATER IT IS CONVEYING- SECTION 1003.3.1 FBC P. |
| | |
| | 20) P2.1 & P5.1 ELEVATOR SUMPS: |
| | A) NO SUMP DRAIN IS SHOWN AT ELEV-1- SECTION 712.3.5 |
| | B) THE 1ST FLOOR SANITARY ISOMETRIC DOES NOT SHOW THE |
| | SUMP DRAIN CONNECTION- 712.3.5. |
| | C) PROVIDE A SUMP PIT, AND SUMP PUMP DRAIN DETAIL IN |
| | ACCORDANCE WITH 712.2, 712.3.2, & 712.5. |
| | D) PROVIDE AN EQUIPMENT SCHEDULE FOR THE SUMP PUMP- |
| | 712.3.1, 712.4.2, |
| | E) PROVIDE AN OIL SEPARATOR UNLESS AN APPROVED ALARM |
| | SYSTEM IS INSTALLED IN THE SUMP PIT- 1003.4. |
| | |
| | 21) P2.1 & P5.1: IT APPEARS THAT THE LOCATIONS OF THE |
| | FLOOR SINK TRAPS BY THE HOT WELLS (002) AND THE STEAM |
| | KETTLE (121) ARE EXCEEDING THE MAXIMUM 12 FT. DISTANCE |
| | TO THE MAIN COMBINATION WASTE AND VENT. |
| | |
| | 22) P2.2: THE PLAN APPEARS TO SHOW ROOF DRAINAGE PIPES |
| | PENETRATING INTO THE INTERIOR EXIT STAIRWAY 008 WHICH |
| | IS PROHIBITED PER SECTION 1023.5 FBC B. |
| | |
| | 23) P0.1 & P2.1: PROVIDE A TRAP PRIMER INSTALLATION |
| | DETAIL- SECTION 1002.4.1 FBC P. |
| | |
| | 24) P0.1, P2.1 & P5.1 GREASE INTERCEPTOR- SECTIONS |
| | 1003.3.5 & 1003.3.7 FBC P. |
| | A) PROVIDE SIZING CALCULATIONS. |
| | B) PROVIDE AN EQUIPMENT SCHEDULE. |
| | C) SHOW THE LOCATION OF THE SAMPLING PORT AND PROVIDE |
| | AN INSTALLATION DETAIL. |
| | D) PROVIDE APPROVED TRAFFIC LID SPECIFICATIONS TO |
| | PROTECT THE INTERCEPTOR, SAMPLING PORT ACCESS, AND |
| | CLEANOUT ACCESS FROM VEHICLE DAMAGE. |
| | |
| | 25) P0.1, P2.1 & P5.1: INDICATE HOW THE EXTERIOR MOP |
| | SINK WILL BE PROTECTED FROM VEHICLE DAMAGE, STORM WATER |
| | AND DETRIMENTAL DRAINAGE INTRUSION- SECTIONS 302.1 & |
| | 305.7 FBC P. |
| | |
| | 26) P0.1: PROVIDE AN INDIRECT WASTE DETAIL FOR THE |
| | KITCHEN SINKS AND FIXTURES- SECTIONS 802.1 & 802.1.1 |
| | FBC P. |
| | |
| | 27) P0.1, P3.1, P3.2, P6.1: LABEL THE WATER HEATERS AS |
| | EITHER IWH-1 OR IWH-2 ACCORDING TO THE EQUIPMENT |
| | SCHEDULE- SECTION 107.2.1 WPB. PLEASE NOTE THAT HOT |
| | WATER AT 110 DEGREES F OR ABOVE IS REQUIRED FOR MOP |
| | SINKS AND OTHER SINKS USED FOR CULINARY PURPOSES, |
| | CLEANSING, LAUNDRY OR BUILDING MAINTENANCE PURPOSES- |
| | SECTION 607.1 FBC P. |
| | |
| | 28) P0.1, P3.1, P3.2, P6.1: IT APPEARS HOT WATER IS |
| | BEING PROVIDED TO THE LAVATORIES. PLEASE NOTE THAT COLD |
| | OR TEMPERED WATER IS REQUIRED IN ACCORDANCE WITH |
| | SECTIONS 419.5 & 607.1.2 FBC P. CLARIFY IF MIXING |
| | VALVES WILL BE INSTALLED OR IF THE WATER HEATERS |
| | SERVING THE SINK ARE ASSE 1070 COMPLIANT. |
| | |
| | 29) P0.1, P3.1, P3.2, P6.1: SHOW THE LOCATIONS OF |
| | REQUIRED BACKFLOW PREVENTERS FOR SUPPLY LINES TO |
| | KITCHEN AND BAR EQUIPMENT- ICE MAKERS, COFFEE MAKERS, |
| | BEVERAGE DISPENSERS, DISH AND GLASS WARE WASHERS ETC. |
| | PROVIDE THE TYPES OF DEVICES TO BE INSTALLED AND |
| | PROVIDE A SCHEDULE ON THE PLANS- SECTION 608.3 FBC P. |
| | |
| | 30) P3.1 & P3.2: PLEASE LABEL ALL FIXTURES AND |
| | APPLIANCES TO BE INSTALLED IN THE SECOND FLOOR CAFE, |
| | AND ADD THE SANITARY DRAINAGE AND WATER SUPPLY DETAILS |
| | TO THE PLANS- SECTION 107.2.1 WPB. |
| | |
| | 31) P0.1: PROVIDE AN ENLARGED WATER TREATMENT DETAIL. |
| | SHOW THE PHYSICAL LOCATION OF THE SYSTEM, PIPING |
| | DETAILS AND PIPING RUNS TO FIXTURES, LOCATIONS OF |
| | VALVES AND BACKFLOW DEVICES- SECTION 608.4 FBC P. |
| | |
| | 32) P3.1 & P6.1: PROVIDE A SHUT OFF VALVE FOR THE WATER |
| | FEED UP TO THE SECOND FLOOR AND ROOF- SECTION 606.1 (4) |
| | FBC P. |
| | |
| | 33) P0.1: PLEASE ADD THE HOSE BIBS TO THE FIXTURE |
| | SCHEDULE- SECTION 608.16.4.2 FBC P. |
| | |
| | 34) P0.1: PROVIDE THE TYPE AND THICKNESS OF THE PIPE |
| | INSULATION- SECTION 607.5 FBC P AND TABLE C403.2.10 FBC |
| | EC. |
| | |
| | 35) P0.1: LIST THE MANUFACTURER OF THE WATER HEATER IN |
| | THE SCHEDULE AND SHOW THE LOCATION OF THE RECIRCULATION |
| | PUMP IN THE PIPING DETAIL. PROVIDE AN EQUIPMENT |
| | SCHEDULE FOR THE PUMP- SECTION 607.2 FBC P. |
| | |
| | 36) P3.1 & P3.3: NON POTABLE WATER SIGNAGE REQUIRED AT |
| | HOSE BIB LOCATIONS. REFER TO SECTION 608.9 FBC P AND |
| | PROVIDE DETAILS. |
| | |
| | 37) CLARIFY IF A DRAINAGE SYSTEM CONNECTED TO THE STORM |
| | DRAINAGE SYSTEM WILL BE INSTALLED IN THE GARDEN CENTER |
| | AND PROVIDE DRAWINGS AND DETAILS IF APPLICABLE TO THE |
| | SCOPE OF THE PROJECT- SECTION 107.2.1 WPB. |
| | |
| | PLEASE NOTE THAT THE REVIEW OF CORRECTED PLANS MAY |
| | RESULT WITH ADDITIONAL COMMENTS. WHEN RESUBMITTING, IT |
| | IS HELPFUL TO PROVIDE A RESPONSE LETTER ADDRESSING EACH |
| | ITEM ALONG WITH THE CITY RE-SUBMITTAL FORM. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL/PLUMBING PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |
| | [email protected] |
| | |