| Date |
Text |
| 2021-10-19 11:21:37 | 3RD REVIEW FBC-2020 FUEL GAS |
| | PERMIT- 21050671 |
| | 10/19/21 |
| | |
| | CODES IN EFFECT: |
| | FBC FG- FLORIDA FUEL GAS CODE 7TH EDITION 2020 |
| | FBC B- FLORIDA BUILDING CODE 7TH EDITION 2020 |
| | FBC EC- FLORIDA ENERGY CONSERVATION CODE 7TH EDITION |
| | 2020 |
| | FBC EX- FLORIDA EXISTING BUILDING CODE 7TH EDITION 2020 |
| | FS- FLORIDA STATUTES |
| | FAC- FLORIDA ADMINISTRATIVE CODE |
| | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC |
| | |
| | PLAN REVIEW RESULTS: DENIED. |
| | |
| | 1) SHEET 3.1P: REFER TO PREVIOUSLY FAILED COMMENT #2 |
| | FROM THE 1ST AND 2ND REVIEW PRINTED BELOW. PLEASE NOTE |
| | THAT THE LETTER FROM THE PRIMO ROASTING CEO DOES NOT |
| | PROVIDE INFORMATION OR EVIDENCE OF ANZI STANDARD |
| | APPROVAL FOR THE GAS BURNER AND ASSOCIATED COMPONENTS- |
| | SECTION 623.1 FBC FG. |
| | FAILED. 3.0P & 3.1P: SUBMIT MANUFACTURER'S |
| | SPECIFICATIONS FOR THE NEW COFFEE ROASTER- SECTION |
| | 305.1 FBC FG. PLEASE HIGHLIGHT OR MARKUP THE SPEC TO |
| | SHOW THE LISTING STANDARD, BTU LOAD, AND GAS INPUT |
| | PRESSURE. THE SUBMITTED ROASTER SPECS DO NOT SHOW THE |
| | LISTING STANDARD, GAS INPUT PRESSURE, OR CATEGORY OF |
| | THE CATEGORY OF THE APPLIANCE. PLEASE REFER TO SECTIONS |
| | 305.1 AND 623.1 FBC FG FOR LISTING REQUIREMENTS, AND |
| | SECTION 410.2- INPUT PRESSURE IS REQUIRED FOR |
| | DETERMINING THE REQUIRED SUPPLY PIPE PRESSURE AND |
| | REGULATOR SELECTION. ALSO MISSING WITH THE SUBMITTAL |
| | ARE MANUFACTURER?S INSTALLATION GUIDELINES FOR |
| | SUPPLYING COMBUSTION AIR, MAKEUP AIR, AND PROPER |
| | VENTING OF THE EQUIPMENT. THE CATEGORY OF THE APPLIANCE |
| | NEEDS TO BE ESTABLISHED IN ORDER FOR A COMPLETE REVIEW |
| | OF THE EXHAUST/VENT SYSTEM. PLEASE INDICATE CATEGORY I, |
| | II, III, OR IV PER SECTIONS 202, 503.6.9.1, & & |
| | 503.6.9.3. FBC FG. |
| | |
| | 2) SHEET 3.1P: REFER TO PREVIOUSLY FAILED COMMENT 3 |
| | FROM THE 1ST AND 2ND REVIEWS PRINTED BELOW. THE REVISED |
| | PLAN SHOWS THE COMBUSTION AIR OPENING IN THE WRONG |
| | LOCATION. THE OPENING SHALL COMMENCE WITHIN 12 INCHES |
| | OF THE TOP OF THE ENCLOSURE- SECTION 304.6.2 FBC FG. |
| | FAILED. 3.0P & 3.1P: PROVIDE COMBUSTION AIR |
| | CALCULATIONS FOR THE COFFEE ROASTER AND INDICATE HOW |
| | THE AIR IS BEING SUPPLIED- SECTION 304.1 FBC FG. THE |
| | RESPONSE NARRATIVE INDICATES INDOOR COMBUSTION AIR IS |
| | TO BE USED, HOWEVER THE PLAN SHOWS A CALCULATION FOR |
| | MECHANICALLY SUPPLIED AIR PER 304.9 USING AN OPENING TO |
| | THE OUTDOORS: A) MECHANICAL AIR MUST BE SUPPLIED BY AN |
| | AIR SUPPLY SYSTEM- MEANING CONDUCTED FROM A SUPPLY |
| | UNIT. COMBUSTION AIR THROUGH ONE WALL OPENING SHALL |
| | COMPLY WITH 304.6.2- 1 SQ. INCH PER 3000 BTUH. SEE |
| | COMMENT #3 FOR COMBUSTION AIR/VENTING COMPLIANCES. |
| | |
| | 3) SHEETS 4.0M & 4.1M: REFER TO PREVIOUS REVIEW COMMENT |
| | #4 PRINTED BELOW. |
| | FAILED. 3.0P & 3.1P: THE TYPE AND SIZE OF |
| | EXHAUST/VENTING SYSTEM IS DEPENDENT ON THE CATEGORY OF |
| | THE APPLIANCE. PLEASE INDICATE CATEGORY I, II, III, OR |
| | IV PER SECTIONS 202, 503.6.9.1 & 503.6.9.3.FBC FG. |
| | A) CLARIFY HOW THE SYSTEM WAS DESIGNED- SUBMIT COFFEE |
| | ROASTERS VENTING/MAKEUP-COMBUSTION AIR SYSTEM |
| | SPECIFICATIONS AND GUIDELINES- 305.1, 503.3, 503.3.1 & |
| | 623.1. |
| | B) PROVIDE EXHAUST/VENT DUCTS SIZING CALCULATIONS AND |
| | SUBMIT MANUFACTURER'S SPECIFICATIONS AND INSTALLATION |
| | GUIDELINES FOR THE VENT SYSTEM. |
| | C) PROVIDE A DIMENSIONED EXHAUST/VENT DIAGRAM SHOWING |
| | CONNECTOR AND TOTAL RUN LENGTH OF THE SYSTEM CONSISTENT |
| | WITH THE MANUFACTURER'S SPECIFICATIONS AND/OR |
| | ENGINEERED CALCULATIONS. |
| | |
| | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE |
| | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY |
| | RE-SUBMITTAL FORM. |
| | |
| | CHRISTOPHER L. COLE |
| | MECHANICAL/PLUMBING PLANS EXAMINER |
| | 401 CLEMATIS STREET |
| | WEST PALM BEACH FL 33401 |
| | 561-805-6719 |
| | CCOLE@WPB |
| | |