| 2022-08-29 13:34:44 | NEW SINGLE FAMILY RESIDENCE (R3), FOURTH BUILDING |
| | REVIEW COMMENTS |
| | CODE: FBC 7TH EDITION (2020) AND CITY AMENDMENTS. |
| | PERMIT #21050545 |
| | 810 34TH ST |
| | |
| | NOTE: |
| | BUILDING REVIEW MAY BE APPROVED WITH PROVISO. PROVISO |
| | MEANS CONTRACTOR WILL SUBMIT REQUIRED INFORMATION AFTER |
| | THE PERMIT IS ISSUED BUT BEFORE INSPECTIONS TO AVOID |
| | CONFLICTS/DELAYS. REVISION FEES MAY APPLY. |
| | CONTRACTOR TO ADVICE IF PROVISO OPTION IS PREFERRED AT |
| | THIS TIME OR IF RE-SUBMITTING REQUIRED INFORMATION |
| | BEFORE PERMIT ISSUANCE. |
| | |
| | ORIGINAL COMMENT: |
| | 1-PROVIDE ENERGY CALCULATIONS AS REQUIRED BY SEC. |
| | R101.5.1 FBC-ENERGY CONSERVATION. |
| | NOTE: NEED TWO SEPARATE ENERGY CALCULATIONS. ONE FOR |
| | THE MAIN HOUSE AND ONE FOR THE REAR STRUCTURE. |
| | PLEASE MAKE SURE CALCULATIONS ARE SIGNED BY ALL THE |
| | REQUIRED PARTIES, INCLUDING THE OWNER OR AUTHORIZED |
| | AGENT TO AVOID CONFLICT/DELAYS. |
| | BUILDER TO SIGN AND COMPLETE THE ENERGY PERFORMANCE |
| | LEVEL (EPL) DISPLAY CARD SUBMITTED. SEC. R405.4.3 FBC- |
| | ENERGY CONSERVATION. |
| | |
| | RESPONSE: |
| | REVISE MAIN HOUSE ENERGY CALCULATIONS: |
| | |
| | PREVIOUS COMMENT: |
| | E)REVISE WINDOWS AREA AND OVERHANG DEPTH & SEPARATION |
| | TO MATCH PLANS. |
| | NOTE: DOORS WITH GLAZING NEED TO BE CONSIDERED IN THE |
| | WINDOWS GLAZING SECTION. |
| | |
| | RESPONSE: |
| | MISSING WINDOWS ON THE EAST SIDE. SEC. R101.5.1.1.2 |
| | FBC-ENERGY CONSERVATION. |
| | |
| | REVISE REAR STRUCTURE ENERGY CALCULATIONS: |
| | |
| | PREVIOUS COMMENT: |
| | B)FLOOR INFORMATION ON ITEM #9 ON PAGE ONE DOESN'T |
| | MATCH PLANS. NEED INSULATION BETWEEN A/C AND NON A/C |
| | AREAS. ALSO, REVISE A/C SQUARE FOOTAGES. SEE PLANS AND |
| | REVISE AS REQUIRED. SEC. R101.5.1.1.2 FBC-ENERGY |
| | CONSERVATION. |
| | |
| | RESPONSE: |
| | INFORMATION DOESN'T MATCH PLANS. SQUARE FOOTAGES DON'T |
| | MATCH. WHAT IS THE INSULATION R-VALUE BETWEEN GARAGE |
| | AND SECOND FLOOR? WHAT IS "OTHER" AND WHERE ARE THE |
| | DETAILS SPECIFIED UNDER ITEM "C"?. SEC. R101.5.1.1.2 |
| | FBC-ENERGY CONSERVATION. |
| | |
| | PREVIOUS COMMENT: |
| | F)REVISE WINDOWS AREA AND OVERHANG DEPTH & SEPARATION |
| | TO MATCH PLANS. ALSO, MAKE SURE ALL WINDOWS ARE |
| | INCLUDED IN THE CALCULATIONS. SEE PLANS. |
| | NOTE: DOORS WITH GLAZING NEED TO BE CONSIDERED IN THE |
| | WINDOWS GLAZING SECTION. |
| | |
| | RESPONSE: |
| | WINDOWS INFORMATION DOESN'T MATCH PLANS. SQUARE FOOTAGE |
| | OF GLASS DOORS DOESN'T MATCH DOESN'T MATCH SIZES |
| | SPECIFIED ON PLANS. SEC. R101.5.1.1.2 FBC-ENERGY |
| | CONSERVATION. |
| | |
| | 2- OK. |
| | 3- OK. |
| | 4- OK. |
| | 5- OK. |
| | |
| | 6- PRODUCT APPROVALS |
| | PROVIDE PRODUCT APPROVAL AS REQUIRED BY FAC 61G20-3.001 |
| | FOR: |
| | (NOTE: THIS MAY BE SUBMITTED LATER AS A DEFERRED |
| | SUBMITTAL. PROVIDE COMPLETE INFORMATION FOR REVIEW |
| | PRIOR TO INSTALLATION TO AVOID CONFLICTS/DELAYS. ALL |
| | PRODUCT APPROVALS NEED TO BE APPROVED IN WRITING BY |
| | DESIGNER OF RECORD PRIOR TO SUBMITTAL): |
| | |
| | A)SLIDING GLASS DOORS NOA 19-0219.11 SUBMITTED: THE |
| | DOORS DON'T MEET THE DESIGN PRESSURES CALCULATED BY THE |
| | ENGINEER OF RECORD FOR ALL SLIDING GLASS DOORS SHOWN ON |
| | PLANS. NEED TO PROVIDE PRODUCT APPROVAL THAT MEETS OR |
| | EXCEEDS THE CALCULATED DESIGN PRESSURES. |
| | |
| | B)FRENCH DOORS NOA 20-0310.11 SUBMITTED: THE DOORS |
| | DON'T MEET THE DESIGN PRESSURES CALCULATED BY THE |
| | ENGINEER OF RECORD FOR ALL DOORS SHOWN ON PLANS. NEED |
| | TO PROVIDE PRODUCT APPROVAL THAT MEETS OR EXCEEDS THE |
| | CALCULATED DESIGN PRESSURES. |
| | |
| | C)ENTRY DOOR (SOLID WOOD AS SHOWN ON PLANS). REPEAT |
| | COMMENT. |
| | |
| | D)HURRICANE SHUTTERS IF DOORS AND WINDOWS DON'T HAVE |
| | IMPACT GLAZING. AND, PROVIDE COMPLETE INSTALLATION |
| | SCHEDULE. SEE CITY SAMPLE. |
| | NOTE: SEE COMMENT 6(A) ABOVE. |
| | |
| | E) FLAT ROOF. AND, CLEARLY MARK WHICH APPROVED ASSEMBLY |
| | IS GOING TO BE INSTALLED TO VERIFY COMPLIANCE WITH THE |
| | DESIGN PRESSURES OF SEC. R301.1 FBC-RESIDENTIAL. NEED |
| | PRODUCT APPROVAL FOR WOOD FRAMED ROOF AND FOR CONCRETE |
| | BALCONY. |
| | NOTE: IF THE SELECTED ASSEMBLY DOESN'T MEET THE DESIGN |
| | PRESSURES FOR ALL ROOF ZONES, THEN SIGNED AND SEALED |
| | RAS 117 CALCULATIONS ARE REQUIRED. |
| | REPEAT COMMENT. |
| | |
| | F) ENGINEER OF RECORD TO REVIEW AND APPROVE IN WRITING |
| | (NOT SIGNING AND SEALING) ALL PRODUCT APPROVALS AS |
| | REQUIRED BY SEC. 107.3.4.1 CITY AMENDMENTS. |
| | |
| | 7- OK. |
| | 8- OK. |
| | 9- OK. |
| | 10-OK. |
| | |
| | WHEN RESUBMITTING, A TRANSMITTAL LETTER LISTING THE |
| | ORIGINAL REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF |
| | THE REVISION MADE, IDENTIFYING THE SHEET OR |
| | SPECIFICATION PAGE WHERE THE CHANGES CAN BE FOUND WILL |
| | HELP TO EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR |
| | ANTICIPATED COOPERATION. |
| | |
| | PLEASE FEEL FREE TO CONTACT ME IF YOU HAVE ANY |
| | QUESTIONS REGARDING THESE COMMENTS, |
| | JULIO GOMEZ |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | DEVELOPMENT SERVICES DEPARTMENT |
| | BUILDING DIVISION |
| | (561)805-6712 |
| | [email protected] |
| | |
| | |