| Plan Review Notes For Permit 21050199 |
| Permit Number |
21050199 |
|
| Review Stop |
Z |
| Sequence Number |
2 |
|
| Notes |
| Date |
Text |
| 2021-07-08 14:27:54 | ZONING APPROVED WITH THE FOLLOWING PROVISO: | | | | | | 1.) RIGHT-OF-WAY PERMIT REQUIRED PRIOR TO THE | | | COMMENCEMENT OF WORRK. | | | | | | | | | NOTE: | | | | | | * SPOKE TO GPETRIE IN ENGINEERING SERVICES ON 7/7/2021 | | | AND WAS INFORMED THAT THE ENGINEERING DEPARTMENT WAS | | | NOT REQUIRED TO REVIEW BUILDING PERMIT FOR THE | | | AWNING/NOT NECESSARY TO ISSUE THE BUILDING PERMIT; | | | HOWEVER, A ROW PERMIT IS REQUIRED PRIOR TO THE | | | COMMENCEMENT OF WORK. |
|