Plan Review Notes
Plan Review Notes For Permit 21031236
Permit Number 21031236
Review Stop G
Sequence Number 1
Notes
Date Text
2021-08-25 17:16:4808/25/21 1ST GAS REVIEW**DENIED** WITH COMMENTS
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME, AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1. WOULD YOU PLEASE PROVIDE THE CODE REFERENCE ON THE
 PLAN FOR THE GAS TYPE USING PER THE WPB AMENDMENTS TO
 FBC 102.3 APPLICATION OF REFERENCES?
  
 2. WOULD YOU PLEASE SUBMIT AN ISOMETRIC DRAWING THAT
 CLEARLY SHOWS THE LENGTH OF ALL CUT SECTIONS OF PIPE
 PER 2020 FBC FG SEC. 402.4.1, 402.4.2.
  
 3. WOULD YOU PLEASE SHOW THE TYPE OF PIPE MATERIAL
 BEING INSTALLED, ALL PIPE SIZES, AND THE CORRESPONDING
 EHD NUMBER OF THE CORRUGATED STAINLESS-STEEL TUBING (IF
 APPLICABLE) FOR EACH PIPE SIZE PER THE WPB AMENDMENTS
 TO THE FBC SEC.107.2.1 INFORMATION ON CONSTRUCTION
 DOCUMENTS.
  
 4. WOULD YOU PLEASE GIVE THE TYPE OF GAS (LP OR
 NATURAL) PER THE WPB AMENDMENTS TO THE FBC SEC. 107.2.1
 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 5. WOULD YOU PLEASE SHOW THE LOCATION OF ALL MP
 (STEP-DOWN) REGULATORS? A LISTED SHUTOFF VALVE SHALL BE
 INSTALLED IMMEDIATELY AHEAD OF EACH MP REGULATOR. 2020
 FBC FG SEC. 409.4 OR 2020 FBC RES. SEC. G2420.4.
  
 6. WOULD YOU PLEASE LIST THE BTU LOAD OF THE APPLIANCE
 ON THE SYSTEM? REFER TO THE 2020 FBC FG SECS. 401.8
 THROUGH 402.6.1 AND TABLES 402.4 (1) THROUGH 402.4
 (37).
  
 7. WOULD YOU PLEASE SHOW THE DISTANCE FROM THE POINT OF
 DELIVERY (GAS METER / MP REGULATOR / LP TANK) TO THE
 MOST REMOTE OUTLET IN THE BUILDING AND/OR SYSTEM PER
 THE 2020 FBC FG SEC. 402.4.1.
  
 8. WOULD YOU PLEASE INDICATE THE SYSTEM'S DELIVERY
 PRESSURE (PSI) ON THE PLAN PER THE 2020 FBC FG SEC.
 402.2.
  
 9. WOULD YOU PLEASE SUBMIT THE MANUFACTURER'S
 SPECIFICATION SHEETS/INSTALLATION MANUAL FOR ALL GAS
 EQUIPMENT TO VERIFY COMPLIANCE WITH 2020 FBC FG SEC.
 305.1.
  
 10. GAS APPLIANCES SHALL BE LISTED AND LABELED. THE
 INSTALLATION MANUALS FOR ALL GAS APPLIANCES/EQUIPMENT
 SHALL BE ONSITE AT THE TIME OF INSPECTION PER THE 2020
 FBC FG SECS. 402.2 AND 301.3.
  
 11. WOULD YOU PLEASE PLACE A NOTE ON BOTH SETS OF PLANS
 LISTING THE SIZING TABLES FROM GAS CODES OR ANOTHER
 STANDARD USED IN THIS SYSTEM'S DESIGN PER THE 2020 FBC
 FG SEC. 402.3.
  
 12. WOULD YOU PLEASE SHOW ALL UNIONS IN FRONT OF
 REGULATOR 1 FOOT OF EITHER SIDE PER THE 2020 FBC FG SEC
 410.2?
  
 13. WOULD YOU PLEASE LABEL THE SHUT-OFF, AND THEY SHALL
 BE ACCESSIBLE WITHOUT MOVING THE EQUIPMENT PER THE 2020
 FBC SEC. G2403 (202) GD, ACCESS.
  
 14. WOULD YOU PLEASE LABEL AND SHOW DRIP LEG ON
 EQUIPMENT PER THE 2020 FBC FG 408.2.
  
 15. WOULD YOU PLEASE SHOW THE EMERGENCY HOOD SHUT DOWN
 SHUTOFF VALVE THAT SHALL BE BELOW THE CEILING? THE
 MANUAL SHUTOFF VALVE SHALL BE UPSTREAM. UNION TO BE
 DOWNSTREAM OF MANUAL VALVE. SECS. 10.4, 10.5 OF NFPA
 96-08.
  
 NOTE: YOU MAY CHOOSE TO HAVE A GAS REVIEW DONE THIS
 TIME AND ADDRESS THE COMMENTS ABOVE. THIS WILL HAVE THE
 GAS APPROVE FOR A SUB PERMIT, OR IF YOU DECIDED NOT TO
 ADDRESS THESE COMMENTS, PLEASE PUT A NOTE ON THE GAS
 HEATER (A SEPARATE PERMIT BY A LICENSED CONTRACTOR FOR
 THE GAS SYSTEM). THEN PLEASE TAKE OFF ANY GAS SHOWN ON
 PLANS; THESE COMMENTS CAN BE FORWARD TO THE GAS
 CONTRACTOR FOR REFERENCE. AN N WILL BE PUT ON THIS
 REVIEW, WHICH STANDS FOR NOT REQUIRED, BUT A SUB PERMIT
 WON'T BE ISSUED ONCE A REVIEW IS DONE FOR THAT SUB
 PERMIT, SO PLEASE BE ADVISED ON THIS PROCEDURE.
  
 HTTPS://CODES.ICCSAFE.ORG/CODES/FLORIDA
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  