| Date |
Text |
| 2021-04-09 13:48:45 | CONDO REMODEL |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected] |
| | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 |
| | AMENDMENTS |
| | |
| | CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107 |
| | 1) PLEASE SPECIFY WHICH ROOMS THE NEW FLOORING IS BEING |
| | INSTALLED IN. |
| | 2) PLEASE PROVIDE THE TOTAL SQUARE FOOT OF FLOORING TO |
| | BE INSTALLED. |
| | 3) THE FOLLOWING ACUSTICAL TEST REPORTS ARE REQUIRED: |
| | |
| | MANUFACTURER SPEC SHEETS ARE NOT ACCEPTABLE DUE TO |
| | DISCREPANCIES BETWEEN SPEC SHEETS/BROCHURES AND TEST |
| | REPORTS FOR SOME MANUFACTURERS (NOT NECESSARILY THE |
| | MANUFACTURER SELECTED; THIS IS A GENERAL COMMENT) |
| | |
| | A. FBC 1207.2, FLOOR/CEILING ASSEMBLIES SEPARATING |
| | DWELLING UNITS FROM EACH OTHER OR FROM PUBLIC OR |
| | SERVICE AREAS SHALL HAVE A SOUND TRANSMISSION CLASS |
| | (STC) OF NOT LESS THAN 50 (45 IF FIELD TESTED) FOR AIR |
| | BORNE NOISE WHEN TESTED IN ACCORDANCE WITH ASTM E 90. |
| | THE TEST REPORT CANNOT INCLUDE A DROPPED GYPSUM |
| | CEILING. PROVIDE A COPY OF THE TEST REPORT. |
| | |
| | B. FBC 1207.3, FLOOR/CEILING ASSEMBLIES BETWEEN |
| | DWELLING UNITS OR BETWEEN A DWELLING UNIT AND A PUBLIC |
| | OR SERVICE AREA WITHIN THE STRUCTURE SHALL HAVE AN |
| | IMPACT INSULATION CLASS (IIC) RATING OF NOT LESS THAN |
| | 50 (45 IF FIELD TESTED) WHEN TESTED IN ACCORDANCE WITH |
| | ASTM E 492. THE TEST REPORT CANNOT INCLUDE A DROPPED |
| | GYPSUM CEILING. PROVIDE A COPY OF THE TEST REPORT. |
| | |
| | C. FBC 603.1, ALLOWABLE MATERIALS IN NON COMBUSTIBLE |
| | BUILDINGS, SEE ITEM 2, EXCEPTION 2, ACOUSTICAL |
| | INSULATION INSTALLED BETWEEN A FINISHED FLOOR AND SOLID |
| | DECKING WITHOUT INTERVENING AIRSPACE SHALL BE ALLOWED |
| | TO HAVE A FLAME SPREAD INDEX OF NOT MORE THAN 200. SEE |
| | 803.1.1, PROVIDE TEST DATA IN ACCORDANCE WITH ASTM E 84 |
| | OR UL 723. |
| | |
| | 4). PLEASE EMAIL ME THE PROPOSED TEST REPORTS TO VERIFY |
| | BEFORE RESUBMITTING TO PROJECTDOX ([email protected]) |
| | |
| | 5) THE JOB COST APPEARS TO BE LOW - PLEASE PROVIDE A |
| | COPY OF THE CONTRACT TO VERIFY THE JOB VALUE - FBC |
| | 109.3 BUILDING PERMIT VALUATIONS. IF, IN THE OPINION OF |
| | THE BUILDING OFFICIAL, THE CLAIMED VALUATION |
| | OF BUILDING, ALTERATION, STRUCTURE, ELECTRICAL, GAS, |
| | MECHANICAL OR PLUMBING SYSTEMS APPEARS TO BE |
| | UNDERESTIMATED ON THE APPLICATION, THE PERMIT SHALL BE |
| | DENIED, UNLESS THE APPLICANT CAN SHOW |
| | DETAILED, QUANTITY ESTIMATES, AND/OR BONA FIDE SIGNED |
| | CONTRACTS (EXCLUDING LAND VALUE) TO MEET THE |
| | APPROVAL OF THE BUILDING OFFICIAL. FOR PERMITTING |
| | PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL |
| | BE TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL, |
| | ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH, |
| | RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES, |
| | MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING |
| | ONLY LAND VALUE. |
| | |
| | |
| | |