Plan Review Notes For Permit 21010663
Permit Number 21010663
Review Stop Z
Sequence Number 2
Notes
Date Text
2021-05-26 13:47:27FAILED
  
 1) THE SUBMITTED COMMUNICATION FACILITY PLACEMENT
 PERMIT - CITY RIGHTS-OF-WAY MUST BE APPROVED PRIOR TO
 THIS PERMIT BEING APPROVED. THE PLANS INCLUDED WITH
 THIS ELECTRICAL PERMIT MUST MATCH THE PLANS APPROVED
 WITH THE AFOREMENTIONED PERMIT. SOME OF THE COMMENTS
 BELOW ARE INCLUDED ON THE PLACEMENT PERMIT REVIEW AS
 WELL AS WITH THIS PERMIT.
  
 2) SHEET T1 LISTS THE SCOPE OF WORK INCLUDES THE
 INSTALLATION OF AN ENCLOSURE CABINET. NONE OF THE PLANS
 SHOW AN ENCLOSURE CABINET. PLEASE CLARIFY WHAT THIS
 MEANS. THE CITY DOES NOT PERMIT FREESTANDING OR POLE
 MOUNTED CABINETS.
  
 3) THE UTILITY POWER PLAN WAS NOT INCLUDED THAT SHOWS
 HOW THE UNDERGROUND POWER IS BEING PROVIDED TO THE
 POLE. THE UNDERGROUND POWER PATH, INCLUDING ANY BORE
 PITS AND HANDHOLES ARE REQUIRED TO BE SHOWN ON THE
 WIRELESS COMMUNICATION FACILITY ROW PERMIT APPLICATION.
  
 4) THE UTILITY ROUTING / GROUNDING PLAN IS INCLUDED
 TWICE (003 E-2 AND 006 E-5) WITH DIFFERENT INFORMATION
 SHOWN FOR THE ONE-LINE DIAGRAM AND THE PANEL SCHEDULES.
 WHICH ONE IS CORRECT?
  
 NOTE: PRIOR TO BEGINNING THE PLACEMENT OF THE POLE, THE
 UNDERGROUND FIBER, THE HANDHOLES, ETC. A RIGHT-OF-WAY
 USE PERMIT MUST BE APPROVED BY THE CITY'S ENGINEERING
 SERVICES DIVISION.
  
 CONTACT ERIC SCHNEIDER @ (561) 822-1446