Plan Review Notes
Plan Review Notes For Permit 21010590
Permit Number 21010590
Review Stop B
Sequence Number 1
Notes
Date Text
2021-02-11 09:58:40SFR ADDITION
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
 CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) DRAWING S-2 THE EXTERIOR WALL DETAILS SHOWN APPEARS
 TO BE AN INTERIOR WALL - PLEASE REVISE SHOWING THE
 EXTERIOR WALL FRAMING AND CLADDING DETAILS.
 2) PLEASE SHOW THE EXTERIOR WALL STRAPPING - BOTTOM
 WALL PLATE TO WALL STUD - TOP WALL PLATE TO BEAM. FBC
 R301.2.1 WIND DESIGN CRITERIA. A CONTINUOUS LOAD PATH
 SHALL BE PROVIDED TO TRANSMIT THE APPLICABLE UPLIFT
 FORCES FROM THE ROOF ASSEMBLY TO THE FOUNDATION.
 3) PLEASE SHOW THE ROOF SHEATHING DETAILS TYPE AND
 FASTENING FBC R803.2.3.1SHEATHING FASTENINGS.
 WOOD STRUCTURAL PANEL SHEATHING SHALL BE FASTENED TO
 ROOF FRAMING IN ACCORDANCE WITH TABLE R803.2.3.1. WHERE
 THE SHEATHING THICKNESS IS 15/32 INCHES AND LESS,
 SHEATHING SHALL BE FASTENED WITH ASTM F1667 RSRS-01
 (23/8" ? 0.113") NAILS. WHERE THE SHEATHING THICKNESS
 IS GREATER THAN 15/32 INCHES, SHEATHING SHALL BE
 FASTENED WITH ASTM F1667 RSRS-03 (21/2" ? 0.131") NAILS
 OR ASTM F1667 RSRS-04 (3" ? 0.120") NAILS. RSRS-01,
 RSRS-03 AND RSRS-04 ARE RING SHANK NAILS MEETING THE
 SPECIFICATIONS IN ASTM F1667.
 4) PLEASE SHOW THE SOFFIT VENT - FBC R806.1VENTILATION
 REQUIRED.
 ENCLOSED ATTICS AND ENCLOSED RAFTER SPACES FORMED WHERE
 CEILINGS ARE APPLIED DIRECTLY TO THE UNDERSIDE OF ROOF
 RAFTERS SHALL HAVE CROSS VENTILATION FOR EACH SEPARATE
 SPACE BY VENTILATING OPENINGS PROTECTED AGAINST THE
 ENTRANCE OF RAIN OR SNOW. VENTILATION OPENINGS SHALL
 HAVE A LEAST DIMENSION OF 1/16 INCH (1.6 MM) MINIMUM
 AND 1/4 INCH (6.4 MM) MAXIMUM.
 FBC R806.3 VENT AND INSULATION CLEARANCE.
 WHERE EAVE OR CORNICE VENTS ARE INSTALLED, BLOCKING,
 BRIDGING AND INSULATION SHALL NOT BLOCK THE FREE FLOW
 OF AIR. NOT LESS THAN A 1-INCH (25 MM) SPACE SHALL BE
 PROVIDED BETWEEN THE INSULATION AND THE ROOF SHEATHING
 AND AT THE LOCATION OF THE VENT.
 5) PLEASE SHOW THE EXTERIOR WALL, FLOOR AND CEILING
 INSULATION TYPE AND "R" VALUE TO COMPLY WITH FBC ENERGY
 CONSERVATION R401
 6) PLEASE SHOW WHAT THE ROOF SLOPE IS.
 7) PLEASE PROVIDE A FLOOR PLAN SHOWING THE LOCATION OF
 THE EXISTING OR ADDED SMOKE DETECTORS PER FBC R314.2.2
 ALTERATIONS, REPAIRS AND ADDITIONS.
 WHERE ALTERATIONS, REPAIRS OR ADDITIONS REQUIRING A
 PERMIT OCCUR, OR WHERE ONE OR MORE SLEEPING ROOMS ARE
 ADDED OR CREATED IN EXISTING DWELLINGS, THE INDIVIDUAL
 DWELLING UNIT SHALL BE EQUIPPED WITH SMOKE ALARMS
 LOCATED AS REQUIRED FOR NEW DWELLINGS.
 8) PRODUCT APPROVAL FOR THE GLASS BLOCK REQUIRES
 SHUTTERS - PLEASE PROVIDE A COMPLETE MIAMI DADE OR
 FLORIDA STATE SHUTTER PRODUCT APPROVAL.
 9) THE CODE IN EFFECT CHANGED ON 1/1/2021 - PLEASE
 REVISE THE CODE USED FOR DESIGN TO SHOW THE CODE IN
 EFFECT (2020 FBC AND ASCE 7-16)
 10) PLEASE PROVIDE A COMPLETE PRODUCT APPROVAL FOR THE
 FLAT/LOW SLOPE DECK ROOFING = PLEASE CIRCLE THE ROOFING
 SYSTEM TO BE USED IN THE PRODUCT APPROVAL - IF NEEDED
 PLEASE PROVIDE SIGNED AND SEALED ADDITIONAL ATTACHMENT
 DETAILS FROM AN ARCHITECT OR ENGINEER FOR THE ROOF
 ZONES 2 AND 3 WHICH MAY REQUIRE A HIGHER WIND PRESSURE
 - SEE NOTES ON THE PRODUCT APPROVAL.
 11) JOB VALUE SHOWN ON THE BUILDING PERMIT APPLICATION
 APPEARS TO BE LOW - (JOB VALUE IS MATERIAL AND LABOR AS
 IF PRICED BY A CONTRACTOR) FBC 109.3 - ICC VALUATION
 TABLE = 127 SQ. FEET X 122 PER SQ. FOOT = 15,494.00 -
 PLEASE REVISE THE BUILDING PERMIT APPLICATION TO SHOW
 THE CORRECT JOB VALUE.
  
 DEFERRED = ROOFING SYSTEM PRODUCT APPROVALS MAY BE
 DEFERRED SUBMITTALS BY LISTING ITEMS TO BE DEFERRED ON
 THE CONSTRUCTION DOCUMENTS - 107.3.4.1 DEFERRED
 SUBMITTALS. FOR THE PURPOSES OF THIS SECTION, DEFERRED
 SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF THE DESIGN
 THAT ARE NOT SUBMITTED AT THE TIME OF THE APPLICATION
 AND THAT ARE TO BE SUBMITTED TO THE BUILDING OFFICIAL
 WITHIN A SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL
 ITEMS SHALL HAVE THE PRIOR APPROVAL OF THE BUILDING
 OFFICIAL. THE REGISTERED DESIGN PROFESSIONAL IN
 RESPONSIBLE CHARGE SHALL LIST THE DEFERRED SUBMITTALS
 ON THE CONSTRUCTION DOCUMENTS FOR REVIEW BY THE
 BUILDING OFFICIAL. DOCUMENTS FOR DEFERRED SUBMITTAL
 ITEMS SHALL BE SUBMITTED TO THE REGISTERED DESIGN
 PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL REVIEW
 THEM AND FORWARD THEM TO THE BUILDING OFFICIAL WITH A
 NOTATION INDICATING THAT THE DEFERRED SUBMITTAL
 DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE IN GENERAL
 CONFORMANCE TO THE DESIGN OF THE BUILDING. THE DEFERRED
 SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL THE
 DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE
 BUILDING OFFICIAL.
  