| Date |
Text |
| 2021-02-01 14:43:03 | SFR ADDITION |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected]. |
| | CODE USED FOR REVIEW - 2020 FBC WITH WPB CHAPTER 1 |
| | AMENDMENTS |
| | |
| | CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107 |
| | 1) CODE IN EFFECT CHANGED ON 1/1/2021 - PLEASE REVISE |
| | THE DRAWINGS TO SHOW THE DESIGN PER THE CODE IN EFFECT |
| | FBC 2020 AND ASCE 7-16 |
| | 2) JOB VALUE SHOWN ON THE BUILDING PERMIT APPLICATION |
| | APPEARS TO BE LOW - PLEASE PROVIDE A SIGNED CONTRACT TO |
| | VERIFY THE JOB COST. FBC WPB 109.3 BUILDING PERMIT |
| | VALUATIONS. IF, IN THE OPINION OF THE BUILDING |
| | OFFICIAL, THE CLAIMED VALUATION |
| | OF BUILDING, ALTERATION, STRUCTURE, ELECTRICAL, GAS, |
| | MECHANICAL OR PLUMBING SYSTEMS APPEARS TO BE |
| | UNDERESTIMATED ON THE APPLICATION, THE PERMIT SHALL BE |
| | DENIED, UNLESS THE APPLICANT CAN SHOW |
| | DETAILED, QUANTITY ESTIMATES, AND/OR BONA FIDE SIGNED |
| | CONTRACTS (EXCLUDING LAND VALUE) TO MEET THE |
| | APPROVAL OF THE BUILDING OFFICIAL. FOR PERMITTING |
| | PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL |
| | BE TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL, |
| | ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH, |
| | RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES, |
| | MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING |
| | ONLY LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE |
| | LATEST PUBLISHED DATA OF NATIONAL |
| | CONSTRUCTION COST ANALYSIS SERVICES (MARSHALL-SWIFT, |
| | MEANS, ETC.), AS PUBLISHED BY INTERNATIONAL |
| | CODE CONGRESS. FINAL BUILDING PERMIT VALUATION SHALL BE |
| | SET BY THE BUILDING OFFICIAL. |
| | |
| | DEFERRED SUBMITTALS: WINDOW AND DOOR PRODUCT APPROVALS, |
| | ROOFING SYSTEM. |
| | |