| 2021-04-16 14:45:47 | NEW SFR |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected]. |
| | CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1 |
| | AMENDMENTS |
| | |
| | CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107 |
| | 1) ROOFING SYSTEM TO BE USED ON THE PROVIDED PRODUCT |
| | APPROVAL PAGE 21 REQUIRES ADDITIONAL SIGNED AND SEALED |
| | ATTACHMENT DETAILS FROM AN ARCHITECT OR ENGINEER OR |
| | REGISTERED ROOF CONSULTANT FOR ROOF WIND ZONES P2 AND |
| | P3 WHICH REQUIRE A HIGHER PRESSURE THAN THE MAXIMUM |
| | SHOWN ON THE PRODUCT APPROVAL (-52.5) - SEE GENERAL |
| | LIMITATION NOTE NUMBER 7 ON THE PRODUCT APPROVAL. A |
| | ROOFING ATTACHMENT OPTION HAS NOT BEEN CIRCLED ON PAGE |
| | 21 OF THE LATEST ROOFING PRODUCT APPROVAL PROVIDED. |
| | 2) DEMO PERMIT IS (20110526) |
| | 3) ROOF PERMIT CAN BE DEFERRED SUBMITTALS IF THEY ARE |
| | LISTED TO BE DEFERRED SUBMITTALS ON THE CONSTRUCTION |
| | DOCUMENTS SEE- FBC 107.3.4.1 DEFERRED SUBMITTALS. FOR |
| | THE PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS ARE |
| | DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT |
| | SUBMITTED AT THE TIME OF THE APPLICATION |
| | AND THAT ARE TO BE SUBMITTED TO THE BUILDING OFFICIAL |
| | WITHIN A SPECIFIED PERIOD. DEFERRAL OF ANY |
| | SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF THE |
| | BUILDING OFFICIAL. THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE |
| | DEFERRED SUBMITTALS ON THE CONSTRUCTION |
| | DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL REVIEW |
| | THEM AND FORWARD THEM TO THE BUILDING |
| | OFFICIAL WITH A NOTATION INDICATING THAT THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN REVIEWED |
| | AND FOUND TO BE IN GENERAL CONFORMANCE TO THE DESIGN OF |
| | THE BUILDING. THE DEFERRED |
| | SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL THE |
| | DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN |
| | APPROVED BY THE BUILDING OFFICIAL. |
| | |
| | |