| Date |
Text |
| 2021-01-28 10:30:47 | NEW SFR |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected]. |
| | CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1 |
| | AMENDMENTS |
| | |
| | CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107 |
| | 1) ROOFING SYSTEM TO BE USED ON THE PROVIDED PRODUCT |
| | APPROVAL REQUIRES ADDITIONAL SIGNED AND SEALED |
| | ATTACHMENT DETAILS FROM AN ARCHITECT OR ENGINEER FOR |
| | ROOF WIND ZONES P1 P2 AND P3 WHICH REQUIRE A HIGHER |
| | PRESSURE THAN THE MAXIMUM SHOWN ON THE PRODUCT APPROVAL |
| | (-52.5) - SEE GENERAL LIMITATION NOTE NUMBER 7 ON THE |
| | PRODUCT APPROVAL. DRAWINGS DO NOT SHOW THE REQUIRED |
| | ROOF COMPONENT PRESSURES - REQUIRED PRESSURES FROM FBC |
| | TABLE R301.2(2) P1=(-64.11) P2=(-84.62) P3=(-115.33) |
| | 2) GUARD RAIL "VIEW RAIL" DRAWINGS CANNOT BE ACCEPTED |
| | AS SIGNED AND SEALED UNLESS SIGNED AND SEALED FROM A |
| | FLORIDA LICENSED ARCHITECT OR ENGINEER.FBC WPB 107.1 |
| | (ALSO, ALL SHOP DRAWINGS NEED TO BE REVIEWED AND MARKED |
| | APPROVED BY THE BUILDING DESIGNER OF RECORD) |
| | 3) GUARD RAILS ARE SUBJECT TO LIVE LOADS - PLEASE |
| | PROVIDE AN APPROVED PRODUCT APPROVAL - OR - PROVIDE |
| | GUARD RAIL ATTACHMENT DETAILS ALONG WITH THE STRUCTURAL |
| | CALCULATIONS THAT SHOW COMPLIANCE WITH THE REQUIRED |
| | LIVE LOADS PER FBC TABLE R301.5 (WHICH MUST BE SIGNED |
| | BY THE PERSON RESPONSIBLE FOR THE DESIGN) - OR- SIGNED |
| | AND SEALED GUARDRAIL ATTACHMENT DETAILS FROM A FLORIDA |
| | LICENSED ARCHITECT OR ENGINEER. |
| | 4) DEMO PERMIT IS (20110526) |
| | 5) ROOF PERMIT, GUARD RAIL SHOP DRAWINGS AND ALL |
| | PRODUCT APPROVALS (WINDOWS, DOORS, ROOFING ETC.) CAN BE |
| | DEFERRED SUBMITTALS IF THEY ARE LISTED TO BE DEFERRED |
| | SUBMITTALS ON THE CONSTRUCTION DOCUMENTS SEE- FBC |
| | 107.3.4.1 DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS |
| | SECTION, DEFERRED SUBMITTALS ARE |
| | DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE NOT |
| | SUBMITTED AT THE TIME OF THE APPLICATION |
| | AND THAT ARE TO BE SUBMITTED TO THE BUILDING OFFICIAL |
| | WITHIN A SPECIFIED PERIOD. DEFERRAL OF ANY |
| | SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF THE |
| | BUILDING OFFICIAL. THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE |
| | DEFERRED SUBMITTALS ON THE CONSTRUCTION |
| | DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. |
| | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| | SUBMITTED TO THE REGISTERED DESIGN |
| | PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL REVIEW |
| | THEM AND FORWARD THEM TO THE BUILDING |
| | OFFICIAL WITH A NOTATION INDICATING THAT THE DEFERRED |
| | SUBMITTAL DOCUMENTS HAVE BEEN REVIEWED |
| | AND FOUND TO BE IN GENERAL CONFORMANCE TO THE DESIGN OF |
| | THE BUILDING. THE DEFERRED |
| | SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL THE |
| | DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN |
| | APPROVED BY THE BUILDING OFFICIAL. |
| | |
| | |