| 2021-05-12 15:44:22 | ****PROVISOS**** |
| | |
| | FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017) |
| | FBC B = FBC BUILDING |
| | FBC R = FBC RESIDENTIAL |
| | FBC EB = FBC EXISTING BUILDING |
| | FBC A = FBC ACCESSIBILITY |
| | FBC EC = FBC ENERGY CONSERVATION |
| | |
| | A SEPARATE ROOF SUB-PERMIT IS REQUIRED. PRIOR TO |
| | INSTALLATION, SUBMIT DEFERRED ROOF PRODUCT APPROVALS |
| | REVIEWED BY DESIGNER OF RECORD AND ENGINEERING. |
| | |
| | COMPONENT & CLADDING PRODUCT APPROVALS REVIEWED BY |
| | DESIGNER OF RECORD ARE TO BE SUBMITTED TO THE BUILDING |
| | DIVISION, REVIEWED AND ISSUED PRIOR TO INSTALLATION. |
| | |
| | DEFERRED SUBMITTALS REQUESTED BY ARCHITECT, SEE |
| | FOLLOWING LIST (MAY NOT BE A COMPLETE LIST); DOCUMENTS |
| | SHOWING COMPLIANCE ARE TO BE REVIEWED BY DESIGNER OF |
| | RECORD PRIOR TO SUBMITTAL (ARCHITECT OR ENGINEER FOR |
| | PRODUCT APPROVALS AND OTHER SPECIFICATION DOCUMENTS, |
| | STRUCTURAL ENGINEER OF RECORD APPROVAL AND REVIEW IS |
| | REQUIRED FOR DELEGATED ENGINEERING). SUBMITTAL, REVIEW |
| | AND APPROVAL ARE REQUIRED PRIOR TO INSTALLATION. |
| | |
| | COMPONENT & CLADDING PRODUCT APPROVALS (COMPLY WITH |
| | PRESSURES SHOWN ON SHEET S0.0.5) |
| | |
| | COMPONENT & CLADDING PRODUCT APPROVALS REVIEWED BY |
| | DESIGNER OF RECORD ARE TO BE SUBMITTED TO THE BUILDING |
| | DIVISION, REVIEWED AND ISSUED PRIOR TO INSTALLATION. |
| | CONFIRM COMPLIANCE WITH PRESSURES SHOWN ON SHEET S0.0.5 |
| | PRIOR TO SUBMITTAL. IF PRODUCT APPROVAL OFFERS OPTIONS, |
| | INDICATE OPTION PROPOSED, ESPECIALLY IF NOT ALL OPTIONS |
| | COMPLY WITH MINIMUM DESIGN PRESSURES. |
| | |
| | SEPARATE PERMITS (APPLICATIONS, PLANS, AND FEES) ARE |
| | REQUIRED FOR: |
| | LIGHT POLES/SITE LIGHTING |
| | FIRE ALARM |
| | FIRE SPRINKLER |
| | LOW VOLTAGE |
| | ACCESS |
| | LANDSCAPING |
| | IRRIGATION |
| | PARKING LOT |
| | SWIMMING POOLS |
| | ALL OTHER ITEMS OTHER THAN BMEP |
| | |
| | AIPP COMPLIANCE REQUIRED; VERIFICATION REQUIRED PRIOR |
| | TO C.O. |
| | |
| | SHORING/RESHORE ENGINEERING IS REQUIRED TO BE SUBMITTED |
| | TO THE BUILDING DIVISION FOR REVIEW. THE ENGINEERING IS |
| | TO BE SUBMITTED, REVIEWED AND ISSUED PRIOR TO CONCRETE |
| | POUR. |
| | |
| | A CONSTRUCTION GUARD RAIL ENGINEERED DETAIL IS REQUIRED |
| | TO BE PROVIDED PRIOR TO INSTALLATION. |
| | |
| | CONSTRUCTION HOURS - 7AM TO 7PM MON-FRI, 8AM TO 8PM |