| 2021-08-20 17:55:01 | PLAN |
| | REVIEW COMMENTS |
| | |
| | 2ND REVIEW: FBC SIXTH EDITION (2017) |
| | ROBERT MCDOUGAL, CBO |
| | COMMERCIAL COMBINATION PLANS EXAMINER |
| | (561) 805-6714 |
| | [email protected] |
| | |
| | DENIED BY BUILDING |
| | PLEASE ADDRESS THE ITEMS NOTED BELOW: |
| | |
| | 1) [THE APPLICATION IS INCORRECT. THIS IS NOT A |
| | SUB-PERMIT. GENERATORS REQUIRE A SEPARATE PERMIT. THE |
| | FURTHER DESCRIPTION OF WORK STATES NEW CONSTRUCTION OF |
| | A 2-STORY SINGLE FAMILY RESIDENCE... THIS SECTION IS |
| | INTENEDED TO DESCRIBE THE WORK THAT IS TO BE DONE UNDER |
| | THIS PERMIT.SUBMIT A CORRECTED APPLICATION.] (PREVIOUS |
| | COMMENT) THIS PERMIT IS FOR THE INSTALLATION OF A |
| | RESIDENTIAL GENERATOR. CORRECT THE DESCRIPTION OF WORK |
| | ON THE PERMIT APPLICATION. FBC 105 |
| | |
| | 2) COMPLIED. SUBMIT THE MANUFACTURER'S SPECIFICATIONS |
| | AND INSTALLATION INSTRUCTIONS FOR THE GENERATOR. FBC |
| | 107.2.1 |
| | |
| | 3) COMPLIED. PROVIDE DETAILS OF THE GENERATOR PAD AND |
| | SPECIFY HOW IT WILL BE ATTACHED TO THE SLAB IN ORDER TO |
| | RESIST THE WINDLOADS. FBC-R301 |
| | |
| | 4) COMPLIED. THIS PROJECT IS LOCATED IN A SPECIAL FLOOD |
| | HAZARD. THE GENERATOR IS REQUIRED TO ABOVE THE DFE OF |
| | 9' NAVD. FBC-R322 |
| | |
| | 5) [THIS REQUIREMENT NEEDS TO BE STATED ON THE SITE |
| | PLAN OR SHOWN ON THE DRAWINGS.] THE GENERATOR EXHAUST |
| | IS REQUIRED TO BE 10' FROM ANY OPENINGS INTO THE |
| | BUILDING PER FBC-R303.5.1. |
| | |
| | 6) AN ELECTRICAL SUB-PERMIT IS REQUIRED FOR THE |
| | GENERATOR. FBC AMENDMENTS105 |
| | |
| | 7) A SEPARATE PERMIT IS REQUIRED FOR GAS. FBC |
| | AMENDMENTS105 |