| Date |
Text |
| 2020-09-30 13:22:52 | SFR REMODEL AND DETACHED GUEST/GARAGE |
| | REVIEWED BY ROGER MCPHERSON |
| | 561-805-6716 |
| | [email protected] |
| | CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1 |
| | AMENDMENTS |
| | |
| | CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107 |
| | 1) PLEASE SHOW THE REQUIRED SMOKE DETECTORS FOR THE |
| | MAIN HOUSE FBC R314.2.2 ALTERATIONS, REPAIRS AND |
| | ADDITIONS. |
| | WHERE ALTERATIONS, REPAIRS OR ADDITIONS REQUIRING A |
| | PERMIT OCCUR, OR WHERE ONE OR MORE SLEEPING ROOMS ARE |
| | ADDED OR CREATED IN EXISTING DWELLINGS, THE INDIVIDUAL |
| | DWELLING UNIT SHALL BE EQUIPPED WITH SMOKE ALARMS |
| | LOCATED AS REQUIRED FOR NEW DWELLINGS. |
| | 2) PLEASE SHOW THE REQUIRED ATTIC VENTILATION FOR THE |
| | ADDITION ON THE MAIN HOUSE (TRUSSED AREA AND FLAT ROOF |
| | AREA) - R806.1VENTILATION REQUIRED. |
| | ENCLOSED ATTICS AND ENCLOSED RAFTER SPACES FORMED WHERE |
| | CEILINGS ARE APPLIED DIRECTLY TO THE UNDERSIDE OF ROOF |
| | RAFTERS SHALL HAVE CROSS VENTILATION FOR EACH SEPARATE |
| | SPACE BY VENTILATING OPENINGS PROTECTED AGAINST THE |
| | ENTRANCE OF RAIN OR SNOW. |
| | 3) R30 INSULATION WILL NOT PROVIDE THE REQUIRED AIR |
| | CLEARANCE FOR VENTILATION IN THE 2X8 RAFTERS PER FBC |
| | R806.3 VENT AND INSULATION CLEARANCE. |
| | WHERE EAVE OR CORNICE VENTS ARE INSTALLED, INSULATION |
| | SHALL NOT BLOCK THE FREE FLOW OF AIR. NOT LESS THAN A |
| | 1-INCH (25 MM) SPACE SHALL BE PROVIDED BETWEEN THE |
| | INSULATION AND THE ROOF SHEATHING AND AT THE LOCATION |
| | OF THE VENT. |
| | 4) PLEASE SHOW THE ATTACHMENT TYPE AND ON CENTER |
| | SPACING FOR THE 3/4" ROOF SHEATHING/DECKING ON THE MAIN |
| | HOUSE ADDITION. |
| | 5) THE GENERATOR LOCATION NEEDS TO BE 10' AWAY FROM |
| | OPENINGS TO COMPLY WITH FBC R303.5.1 INTAKE OPENINGS. |
| | MECHANICAL AND GRAVITY OUTDOOR AIR INTAKE OPENINGS |
| | SHALL BE LOCATED NOT LESS THAN 10 FEET (3048 MM) FROM |
| | ANY HAZARDOUS OR NOXIOUS CONTAMINANT, |
| | 6) PLEASE CIRCLE OR INDICATE HOW THE ROOF TILE IS TO BE |
| | ATTACHED ON THE ROOF TILE PRODUCT APPROVAL PROVIDED. IF |
| | ATTACHED WITH ADHESIVE PLEASE PROVIDE THE MIAMI DADE OR |
| | FLORIDA STATE PRODUCT APPROVAL FOR THE ADHESIVE. |
| | 7) PLEASE PROVIDE AN UPDATED SURVEY ALONG WITH THE SITE |
| | PLAN PROVIDED SHOWING ALL THE REQUIRED ITEMS PER FBC |
| | WPB AMENDMENTS 107.2.5 SITE PLAN. THE CONSTRUCTION |
| | DOCUMENTS SUBMITTED WITH THE APPLICATION FOR PERMIT |
| | SHALL BE ACCOMPANIED BY A SITE PLAN SHOWING TO SCALE |
| | THE SIZE AND LOCATION OF NEW CONSTRUCTION AND EXISTING |
| | STRUCTURES ON THE SITE, DISTANCES FROM LOT LINES, THE |
| | ESTABLISHED |
| | STREET GRADES AND THE PROPOSED FINISHED GRADES, |
| | DEPICTING THE PROPOSED LOT DRAINAGE AND, AS APPLICABLE, |
| | FLOOD HAZARD AREAS, FLOODWAYS, AND DESIGN FLOOD |
| | ELEVATIONS; AND IT SHALL BE DRAWN IN ACCORDANCE WITH AN |
| | ACCURATE AND INCLUDED ON A BOUNDARY LINE SURVEY. |
| | |