| 2021-01-26 17:43:19 | 01/26/21 3RD PLUMBING REVIEW**DENIED** WITH COMMENTS |
| | |
| | NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| | TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| | GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| | |
| | 1. A SUB PLUMBING PERMIT IS REQUIRED BY A LICENSED |
| | CONTRACTOR FOR THE SCOPE OF WORK PER THE WPB AMENDMENTS |
| | TO THE FBC SEC. 105.1. |
| | |
| | 2. THE TDH CALCULATION DOES NOT SHOW THE HEATER, IT |
| | MUST INCLUDE ALL THE SYSTEM COMPONENTS INCLUDING |
| | SUCTION AND RETURN PIPING, FITTINGS, VALVES, HEATER, |
| | FILTER, AND CHLORINATOR. ALL SYSTEM COMPONENTS EXCEPT |
| | THE PUMP. |
| | |
| | 3. IDENTIFY ON THE PUMP CURVE WHICH CURVE KEY IS |
| | SPECIFIC TO THE PUMP BEING INSTALLED ON THIS POOL. THIS |
| | IS NEEDED TO CONFIRM THE MAXIMUM SYSTEM FLOW FROM THE |
| | TDH CALCULATIONS PER THE ANSI/APSP/ICC 7 - 2013 SECS. |
| | 4.4.9, 4.4.9.1. |
| | |
| | 4. SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE POOL |
| | HEATER, FOR THE CARTRIDGE FILTER, AND THE PUMP PER THE |
| | WPB AMENDMENTS TO FBC SEC. 107.2.1. |
| | |
| | 5. THE POOL HEATER SHALL HAVE A MINIMUM THERMAL |
| | EFFICIENCY OF 82% PER THE 2017 FBC-ENERGY SEC. |
| | R403.10.4. |
| | |
| | WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION & |
| | REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS |
| | NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL |
| | REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE |
| | REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION |
| | PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO |
| | EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED |
| | COOPERATION. |
| | |
| | LUIS A. CRESPO |
| | PLUMBING PLAN EXAMINER / INSPECTOR |
| | EMAIL: [email protected] OFFICE: 561 805-6720 |
| | |