Plan Review Notes
Plan Review Notes For Permit 20080045
Permit Number 20080045
Review Stop G
Sequence Number 1
Notes
Date Text
2020-08-11 09:14:17GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN
 THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN
 PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND PLANS
 WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT
 REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE PER
 THE WPB AMENDMENTS TO FBC SEC. 107.2.1.
  
 A SUB GAS PERMIT IS REQUIRED BY A LICENSED CONTRACTOR
 FOR THE SCOPE OF WORK PER THE WPB AMENDMENTS TO THE FBC
 SEC. 105.1.
  
 A GENERIC REQUIREMENT GAS SHEET IS AVAILABLE UPON
 REQUEST AS A PDF.
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  