2020-08-24 11:55:061ST REVIEW FBC-2017 PLUMBING
 PERMIT- 20071488
 8/24/2020
  
 CODES IN EFFECT:
  
 FBC P- FLORIDA PLUMBING CODE SIXTH EDITION 2017
 FBC ACC- FLORIDA ACCESSIBILITY CODE SIXTH ADDITION 2017
 FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017
 FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017
 FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION
 2017
 FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017
 FBC EX- FLORIDA EXISTING BUILDING CODE SIXTH EDITION
 2017
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH
 EDITION 2017
  
 PLAN REVIEW RESULTS: DENIED.
  
 1) SHEET A1.0: A SEPARATE PERMIT AND PLAN SUBMITTAL ARE
 REQUIRED FOR THE IRRIGATION WORK THAT IS NOTED ON THE
 DEMOLITION PLAN- SECTION 107.2.1 WPB.
  
 2) A4.0, P0, P2.1: SUBMIT THE ENGINEERED SHOP DRAWINGS
 FOR THE PATIO WITH APPROVAL STAMPS BY THE DESIGN
 PROFESSIONALS OF RECORD- SECTIONS 105.3 & 107.2.1 WPB.
  
 3) A4.0, P0, P2.1: ROOF DRAINAGE CALCULATIONS ARE
 REQUIRED FOR THE NEW PATIO ROOF THAT INCLUDE THE
 DRAINAGE FROM ADJACENT ROOFS OR PARTS OF THE BUILDING
 THAT ARE DRAINING WATER ONTO THE ROOF.
 THE SHOP DRAWINGS AND/OR THE SITE-SPECIFIC PLANS SHALL
 VERIFY THE ROOF HAS BEEN DESIGNED IN COMPLIANCE WITH
 SECTION 1107.1 FBC P: ROOFS SHALL BE DESIGNED FOR THE
 MAXIMUM POSSIBLE DEPTH OF WATER THAT WILL POND THEREON
 AS DETERMINED BY THE RELATIVE LEVELS OF ROOF DECK AND
 OVERFLOW WEIRS, SCUPPERS, EDGES OR SERVICEABLE DRAINS
 IN COMBINATION WITH THE DEFLECTED STRUCTURAL ELEMENTS.
 IN DETERMINING THE MAXIMUM POSSIBLE DEPTH OF WATER, ALL
 PRIMARY ROOF DRAINAGE MEANS SHALL BE ASSUMED TO BE
 BLOCKED. THE MAXIMUM POSSIBLE DEPTH OF WATER ON THE
 ROOF SHALL INCLUDE THE HEIGHT OF THE WATER REQUIRED
 ABOVE THE INLET OF THE SECONDARY ROOF DRAINAGE MEANS TO
 ACHIEVE THE REQUIRED FLOW RATE OF THE SECONDARY
 DRAINAGE MEANS TO ACCOMMODATE THE DESIGN RAINFALL RATE
 AS REQUIRED BY SECTION 1106.
 A) CALCULATIONS SHALL ALSO BE PROVIDED FOR THE VERTICAL
 DOWNSPOUTS- SECTION 1106.1 AND THE HORIZONTAL GUTTERS-
 SECTION 1106.6 AND TABLE 1106.6.
  
 4) A4.0, P0, P2.1: VERIFY THE STORM WATER FROM THE ROOF
 AND THE TRENCH DRAIN WILL FLOW AWAY FROM THE BUILDING
 AND DRAIN INTO APPROVED PERMEABLE AREA THAT WILL NOT
 POND OR FLOOD, OTHERWISE CONNECT THE DRAINS TO THE
 EXISTING STORM DRAINAGE SYSTEM ON SITE- SECTION 1101.2.
  
 5)SHEET P2.1: THE DIMENSIONS OF THE STORM DRAIN ARE NOT
 SHOWN. THE VERTICAL LEADER CALCULATIONS INDICATE THE
 SCREEN AREA ONLY AND NONE OF THE FLOOR AREA THAT WILL
 BE COLLECTING RAIN WATER. PLEASE REVISE THE
 CALCULATIONS AND SUBMIT SPECS FOR THE TRENCH DRAIN-
 SECTION 412.1 FBC P.
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM.
  
 CHRISTOPHER L. COLE
 MECHANICAL/PLUMBING PLANS EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL 33401
 561-805-6719
 [email protected]
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved