2020-08-31 12:13:22ENGINEERS MUST HAVE THE PROPER THIRD PARTY
 VERIFICATION. SHEETS E-1; M-1; M-2; M-3 MUST HAVE THE
 PROPER THIRD PARTY VERIFICATION.
 PER THE WPB AMENDMENTS TO THE FBC, EACH SHEET OF PLAN
 IS REQUIRED TO BE SIGNED AND SEALED BY THE PERSON
 RESPONSIBLE FOR THE DESIGN. A DIGITAL PLAN REQUIRES A
 DIGITAL SIGNATURE WITH THE PROPER THIRD PARTY
 VERIFICATION. PROVIDE CORRECTION. ALTERNATIVELY, A
 SIGNED/SEALED PAPER SET MAY BE SUPPLIED TO THE BUILDING
 DEPARTMENT WHEN ALL TRADES ARE APPROVED. WPB FBC 107.1;
 FS 471/481