2020-08-21 13:00:321) IF COMBUSTION AIR IS BEING PROVIDED BY THE
 BUILDING'S MECHANICAL VENTILATION SYSTEM,THE SYSTEM
 SHALL PROVIDE THE SPECIFIED COMBUSTION AIR RATE IN
 ADDITION TO THE REQUIRED VENTILATION AIR. FBC-FUEL GAS
 SEC. 304.9.3. PROVIDE THIS INFORMATION FOR REVIEW. THE
 PLAN NOTES THAT AHU -5 & AHU-1 IS SUPPLYING COMBUSTION
 AIR FOR THE DRYERS. IS THIS UNIT DEDICATED TO SUPPLY
 JUST THE COMBUSTION AIR FOR THE DRYERS? SHOW COMPLIANCE
 WITH FBC-FUEL GAS SEC. 304.9.2.
 2) EACH OF THE APPLIANCES SERVED SHALL BE INTERLOCKED
 WITH THE MECHANICAL AIR SUPPLY SYSTEM TO PREVENT MAIN
 BURNER OPERATION OPERATION WHEN THE MECHANICAL AIR
 SUPPLY SYSTEM IS NOT IN OPERATION. FBC-FUEL GAS
 SEC.304.9.2.
 3) WHERE CONNECTED TO RIGID PIPING, A UNION SHALL BE
 INSTALLED WITHIN ONE FOOT OF EITHER SIDE OF THE
 PRESSURE REGULATOR. FBC-FUEL GAS SEC.410.2 (7). A UNION
 WAS PLACED ON THE UTILITY SIDE OF THE GAS METER WHICH
 FALLS UNDER THE GAS UTILITY WHICH WAS NOT IN MY REVIEW
 COMMENT AND NO UNIONS ARE SHOWN AT THE REGULATORS AS
 PREVIOUSLY REQUESTED. 2ND REQUEST.
  
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  
  
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved